Cavern and gate design method combining construction diversion and flood discharge adjustment

The invention discloses a construction diversion and flood discharge adjustment combined cavern and gate design method which comprises the steps that S100, a first gate and a second gate are disassembled, the disassembled first gate can move between a first position and a second position, and when t...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Hauptverfasser: SHI KAIJIAN, PENG QIAN, YANG XIAOLONG, YE BAODONG, LIN KAI, ZHANG PENG, GUO KAI, HE GAONIAN, WU DI, CAI MINGZHI, LIU XUESHAN, LI YULIN, LEI XINGCHUN, LIU TAO, YANG FENG
Format: Patent
Sprache:chi ; eng
Schlagworte:
Online-Zugang:Volltext bestellen
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
container_end_page
container_issue
container_start_page
container_title
container_volume
creator SHI KAIJIAN
PENG QIAN
YANG XIAOLONG
YE BAODONG
LIN KAI
ZHANG PENG
GUO KAI
HE GAONIAN
WU DI
CAI MINGZHI
LIU XUESHAN
LI YULIN
LEI XINGCHUN
LIU TAO
YANG FENG
description The invention discloses a construction diversion and flood discharge adjustment combined cavern and gate design method which comprises the steps that S100, a first gate and a second gate are disassembled, the disassembled first gate can move between a first position and a second position, and when the first gate is located at the first position, the second gate is located at the second position; the bottom of the first gate abuts against the top of the second gate to block the diversion tunnel, and when the first gate is located at the second position, the first gate and the second gate are separated to form a fluid channel for liquid circulation; and S200, the second gate is fixed. It should be understood that when the diversion tunnel is changed into the discharge tunnel, the first gate is more used as a service valve. And when the first gate descends to the first position, the diversion tunnel is blocked. And then the first valve located at the tail end of the diversion tunnel is opened, so that water loca
format Patent
fullrecord <record><control><sourceid>epo_EVB</sourceid><recordid>TN_cdi_epo_espacenet_CN115679908A</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><sourcerecordid>CN115679908A</sourcerecordid><originalsourceid>FETCH-epo_espacenet_CN115679908A3</originalsourceid><addsrcrecordid>eNqNizsOwjAMQLswIOAO5gBIVIhPRxSBmJhYUWUSNw1qnSp2OT-pxAGY3hvemxdPgx9KDMgOPCqBIwmeoSdtowMb-1fgwD4bi6bRaogMLuRJJpu-pos5dUFsi8kToHuPoj2xLotZg53Q6sdFsb5eHua2oSHWJANaYtLa3MtyfzhW1fZ03v3TfAEm5DzS</addsrcrecordid><sourcetype>Open Access Repository</sourcetype><iscdi>true</iscdi><recordtype>patent</recordtype></control><display><type>patent</type><title>Cavern and gate design method combining construction diversion and flood discharge adjustment</title><source>esp@cenet</source><creator>SHI KAIJIAN ; PENG QIAN ; YANG XIAOLONG ; YE BAODONG ; LIN KAI ; ZHANG PENG ; GUO KAI ; HE GAONIAN ; WU DI ; CAI MINGZHI ; LIU XUESHAN ; LI YULIN ; LEI XINGCHUN ; LIU TAO ; YANG FENG</creator><creatorcontrib>SHI KAIJIAN ; PENG QIAN ; YANG XIAOLONG ; YE BAODONG ; LIN KAI ; ZHANG PENG ; GUO KAI ; HE GAONIAN ; WU DI ; CAI MINGZHI ; LIU XUESHAN ; LI YULIN ; LEI XINGCHUN ; LIU TAO ; YANG FENG</creatorcontrib><description>The invention discloses a construction diversion and flood discharge adjustment combined cavern and gate design method which comprises the steps that S100, a first gate and a second gate are disassembled, the disassembled first gate can move between a first position and a second position, and when the first gate is located at the first position, the second gate is located at the second position; the bottom of the first gate abuts against the top of the second gate to block the diversion tunnel, and when the first gate is located at the second position, the first gate and the second gate are separated to form a fluid channel for liquid circulation; and S200, the second gate is fixed. It should be understood that when the diversion tunnel is changed into the discharge tunnel, the first gate is more used as a service valve. And when the first gate descends to the first position, the diversion tunnel is blocked. And then the first valve located at the tail end of the diversion tunnel is opened, so that water loca</description><language>chi ; eng</language><subject>FIXED CONSTRUCTIONS ; FOUNDATIONS ; HYDRAULIC ENGINEERING ; SOIL SHIFTING</subject><creationdate>2023</creationdate><oa>free_for_read</oa><woscitedreferencessubscribed>false</woscitedreferencessubscribed></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><linktohtml>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20230203&amp;DB=EPODOC&amp;CC=CN&amp;NR=115679908A$$EHTML$$P50$$Gepo$$Hfree_for_read</linktohtml><link.rule.ids>230,308,780,885,25564,76547</link.rule.ids><linktorsrc>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20230203&amp;DB=EPODOC&amp;CC=CN&amp;NR=115679908A$$EView_record_in_European_Patent_Office$$FView_record_in_$$GEuropean_Patent_Office$$Hfree_for_read</linktorsrc></links><search><creatorcontrib>SHI KAIJIAN</creatorcontrib><creatorcontrib>PENG QIAN</creatorcontrib><creatorcontrib>YANG XIAOLONG</creatorcontrib><creatorcontrib>YE BAODONG</creatorcontrib><creatorcontrib>LIN KAI</creatorcontrib><creatorcontrib>ZHANG PENG</creatorcontrib><creatorcontrib>GUO KAI</creatorcontrib><creatorcontrib>HE GAONIAN</creatorcontrib><creatorcontrib>WU DI</creatorcontrib><creatorcontrib>CAI MINGZHI</creatorcontrib><creatorcontrib>LIU XUESHAN</creatorcontrib><creatorcontrib>LI YULIN</creatorcontrib><creatorcontrib>LEI XINGCHUN</creatorcontrib><creatorcontrib>LIU TAO</creatorcontrib><creatorcontrib>YANG FENG</creatorcontrib><title>Cavern and gate design method combining construction diversion and flood discharge adjustment</title><description>The invention discloses a construction diversion and flood discharge adjustment combined cavern and gate design method which comprises the steps that S100, a first gate and a second gate are disassembled, the disassembled first gate can move between a first position and a second position, and when the first gate is located at the first position, the second gate is located at the second position; the bottom of the first gate abuts against the top of the second gate to block the diversion tunnel, and when the first gate is located at the second position, the first gate and the second gate are separated to form a fluid channel for liquid circulation; and S200, the second gate is fixed. It should be understood that when the diversion tunnel is changed into the discharge tunnel, the first gate is more used as a service valve. And when the first gate descends to the first position, the diversion tunnel is blocked. And then the first valve located at the tail end of the diversion tunnel is opened, so that water loca</description><subject>FIXED CONSTRUCTIONS</subject><subject>FOUNDATIONS</subject><subject>HYDRAULIC ENGINEERING</subject><subject>SOIL SHIFTING</subject><fulltext>true</fulltext><rsrctype>patent</rsrctype><creationdate>2023</creationdate><recordtype>patent</recordtype><sourceid>EVB</sourceid><recordid>eNqNizsOwjAMQLswIOAO5gBIVIhPRxSBmJhYUWUSNw1qnSp2OT-pxAGY3hvemxdPgx9KDMgOPCqBIwmeoSdtowMb-1fgwD4bi6bRaogMLuRJJpu-pos5dUFsi8kToHuPoj2xLotZg53Q6sdFsb5eHua2oSHWJANaYtLa3MtyfzhW1fZ03v3TfAEm5DzS</recordid><startdate>20230203</startdate><enddate>20230203</enddate><creator>SHI KAIJIAN</creator><creator>PENG QIAN</creator><creator>YANG XIAOLONG</creator><creator>YE BAODONG</creator><creator>LIN KAI</creator><creator>ZHANG PENG</creator><creator>GUO KAI</creator><creator>HE GAONIAN</creator><creator>WU DI</creator><creator>CAI MINGZHI</creator><creator>LIU XUESHAN</creator><creator>LI YULIN</creator><creator>LEI XINGCHUN</creator><creator>LIU TAO</creator><creator>YANG FENG</creator><scope>EVB</scope></search><sort><creationdate>20230203</creationdate><title>Cavern and gate design method combining construction diversion and flood discharge adjustment</title><author>SHI KAIJIAN ; PENG QIAN ; YANG XIAOLONG ; YE BAODONG ; LIN KAI ; ZHANG PENG ; GUO KAI ; HE GAONIAN ; WU DI ; CAI MINGZHI ; LIU XUESHAN ; LI YULIN ; LEI XINGCHUN ; LIU TAO ; YANG FENG</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-epo_espacenet_CN115679908A3</frbrgroupid><rsrctype>patents</rsrctype><prefilter>patents</prefilter><language>chi ; eng</language><creationdate>2023</creationdate><topic>FIXED CONSTRUCTIONS</topic><topic>FOUNDATIONS</topic><topic>HYDRAULIC ENGINEERING</topic><topic>SOIL SHIFTING</topic><toplevel>online_resources</toplevel><creatorcontrib>SHI KAIJIAN</creatorcontrib><creatorcontrib>PENG QIAN</creatorcontrib><creatorcontrib>YANG XIAOLONG</creatorcontrib><creatorcontrib>YE BAODONG</creatorcontrib><creatorcontrib>LIN KAI</creatorcontrib><creatorcontrib>ZHANG PENG</creatorcontrib><creatorcontrib>GUO KAI</creatorcontrib><creatorcontrib>HE GAONIAN</creatorcontrib><creatorcontrib>WU DI</creatorcontrib><creatorcontrib>CAI MINGZHI</creatorcontrib><creatorcontrib>LIU XUESHAN</creatorcontrib><creatorcontrib>LI YULIN</creatorcontrib><creatorcontrib>LEI XINGCHUN</creatorcontrib><creatorcontrib>LIU TAO</creatorcontrib><creatorcontrib>YANG FENG</creatorcontrib><collection>esp@cenet</collection></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext_linktorsrc</fulltext></delivery><addata><au>SHI KAIJIAN</au><au>PENG QIAN</au><au>YANG XIAOLONG</au><au>YE BAODONG</au><au>LIN KAI</au><au>ZHANG PENG</au><au>GUO KAI</au><au>HE GAONIAN</au><au>WU DI</au><au>CAI MINGZHI</au><au>LIU XUESHAN</au><au>LI YULIN</au><au>LEI XINGCHUN</au><au>LIU TAO</au><au>YANG FENG</au><format>patent</format><genre>patent</genre><ristype>GEN</ristype><title>Cavern and gate design method combining construction diversion and flood discharge adjustment</title><date>2023-02-03</date><risdate>2023</risdate><abstract>The invention discloses a construction diversion and flood discharge adjustment combined cavern and gate design method which comprises the steps that S100, a first gate and a second gate are disassembled, the disassembled first gate can move between a first position and a second position, and when the first gate is located at the first position, the second gate is located at the second position; the bottom of the first gate abuts against the top of the second gate to block the diversion tunnel, and when the first gate is located at the second position, the first gate and the second gate are separated to form a fluid channel for liquid circulation; and S200, the second gate is fixed. It should be understood that when the diversion tunnel is changed into the discharge tunnel, the first gate is more used as a service valve. And when the first gate descends to the first position, the diversion tunnel is blocked. And then the first valve located at the tail end of the diversion tunnel is opened, so that water loca</abstract><oa>free_for_read</oa></addata></record>
fulltext fulltext_linktorsrc
identifier
ispartof
issn
language chi ; eng
recordid cdi_epo_espacenet_CN115679908A
source esp@cenet
subjects FIXED CONSTRUCTIONS
FOUNDATIONS
HYDRAULIC ENGINEERING
SOIL SHIFTING
title Cavern and gate design method combining construction diversion and flood discharge adjustment
url https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2025-01-05T01%3A10%3A40IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-epo_EVB&rft_val_fmt=info:ofi/fmt:kev:mtx:patent&rft.genre=patent&rft.au=SHI%20KAIJIAN&rft.date=2023-02-03&rft_id=info:doi/&rft_dat=%3Cepo_EVB%3ECN115679908A%3C/epo_EVB%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_id=info:pmid/&rfr_iscdi=true