Construction method for breaking and removing virtual pile head without girdling
According to the construction method for removing the virtual pile head without girdling breaking, a high-pressure jet grouting machine is used for spraying a concrete retarder to the position of the pile head needing to be cleaned, the retarder reacts with the pile head concrete, the setting time o...
Gespeichert in:
Hauptverfasser: | , , , , , |
---|---|
Format: | Patent |
Sprache: | chi ; eng |
Schlagworte: | |
Online-Zugang: | Volltext bestellen |
Tags: |
Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
|
container_end_page | |
---|---|
container_issue | |
container_start_page | |
container_title | |
container_volume | |
creator | CHO MIN-WOOK YU HAO XI JIALONG HE YINGLONG CAI TIECHEN HOU LONG |
description | According to the construction method for removing the virtual pile head without girdling breaking, a high-pressure jet grouting machine is used for spraying a concrete retarder to the position of the pile head needing to be cleaned, the retarder reacts with the pile head concrete, the setting time of the pile head concrete is delayed, pile foundation concrete below the pile head concrete is not affected, and the pile head concrete is prevented from being damaged. After the lower pile foundation concrete is finally set, the pile head concrete is not finally set, so that the pile head concrete is convenient and efficient to clean and chiseled away, manual circular cutting of the pile head and stripping of pile foundation main reinforcements are not needed, the pile head concrete chiseling construction is small in manual demand, simple in procedure and high in working strength, meanwhile, dust and noise cannot be generated in the breaking process, and the construction cost is reduced. And the environment and noi |
format | Patent |
fullrecord | <record><control><sourceid>epo_EVB</sourceid><recordid>TN_cdi_epo_espacenet_CN114837182A</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><sourcerecordid>CN114837182A</sourcerecordid><originalsourceid>FETCH-epo_espacenet_CN114837182A3</originalsourceid><addsrcrecordid>eNqNi0sKwjAQQLNxIeodxgO4iBXsVoLiSly4L2MzbQfTTMinXt8KHsDV48F7S3U34lOOpc0sHkbKg1joJMIzEr7Y94DeQqRRpq9MHHNBB4EdwUBo4c3zUjL0HK2bk7VadOgSbX5cqe3l_DDXHQVpKAVsyVNuzE3rQ10ddb0_Vf80H91fN9Q</addsrcrecordid><sourcetype>Open Access Repository</sourcetype><iscdi>true</iscdi><recordtype>patent</recordtype></control><display><type>patent</type><title>Construction method for breaking and removing virtual pile head without girdling</title><source>esp@cenet</source><creator>CHO MIN-WOOK ; YU HAO ; XI JIALONG ; HE YINGLONG ; CAI TIECHEN ; HOU LONG</creator><creatorcontrib>CHO MIN-WOOK ; YU HAO ; XI JIALONG ; HE YINGLONG ; CAI TIECHEN ; HOU LONG</creatorcontrib><description>According to the construction method for removing the virtual pile head without girdling breaking, a high-pressure jet grouting machine is used for spraying a concrete retarder to the position of the pile head needing to be cleaned, the retarder reacts with the pile head concrete, the setting time of the pile head concrete is delayed, pile foundation concrete below the pile head concrete is not affected, and the pile head concrete is prevented from being damaged. After the lower pile foundation concrete is finally set, the pile head concrete is not finally set, so that the pile head concrete is convenient and efficient to clean and chiseled away, manual circular cutting of the pile head and stripping of pile foundation main reinforcements are not needed, the pile head concrete chiseling construction is small in manual demand, simple in procedure and high in working strength, meanwhile, dust and noise cannot be generated in the breaking process, and the construction cost is reduced. And the environment and noi</description><language>chi ; eng</language><subject>EMBANKMENTS ; EXCAVATIONS ; FIXED CONSTRUCTIONS ; FOUNDATIONS ; HYDRAULIC ENGINEERING ; SOIL SHIFTING ; UNDERGROUND OR UNDERWATER STRUCTURES</subject><creationdate>2022</creationdate><oa>free_for_read</oa><woscitedreferencessubscribed>false</woscitedreferencessubscribed></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><linktohtml>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&date=20220802&DB=EPODOC&CC=CN&NR=114837182A$$EHTML$$P50$$Gepo$$Hfree_for_read</linktohtml><link.rule.ids>230,308,780,885,25564,76419</link.rule.ids><linktorsrc>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&date=20220802&DB=EPODOC&CC=CN&NR=114837182A$$EView_record_in_European_Patent_Office$$FView_record_in_$$GEuropean_Patent_Office$$Hfree_for_read</linktorsrc></links><search><creatorcontrib>CHO MIN-WOOK</creatorcontrib><creatorcontrib>YU HAO</creatorcontrib><creatorcontrib>XI JIALONG</creatorcontrib><creatorcontrib>HE YINGLONG</creatorcontrib><creatorcontrib>CAI TIECHEN</creatorcontrib><creatorcontrib>HOU LONG</creatorcontrib><title>Construction method for breaking and removing virtual pile head without girdling</title><description>According to the construction method for removing the virtual pile head without girdling breaking, a high-pressure jet grouting machine is used for spraying a concrete retarder to the position of the pile head needing to be cleaned, the retarder reacts with the pile head concrete, the setting time of the pile head concrete is delayed, pile foundation concrete below the pile head concrete is not affected, and the pile head concrete is prevented from being damaged. After the lower pile foundation concrete is finally set, the pile head concrete is not finally set, so that the pile head concrete is convenient and efficient to clean and chiseled away, manual circular cutting of the pile head and stripping of pile foundation main reinforcements are not needed, the pile head concrete chiseling construction is small in manual demand, simple in procedure and high in working strength, meanwhile, dust and noise cannot be generated in the breaking process, and the construction cost is reduced. And the environment and noi</description><subject>EMBANKMENTS</subject><subject>EXCAVATIONS</subject><subject>FIXED CONSTRUCTIONS</subject><subject>FOUNDATIONS</subject><subject>HYDRAULIC ENGINEERING</subject><subject>SOIL SHIFTING</subject><subject>UNDERGROUND OR UNDERWATER STRUCTURES</subject><fulltext>true</fulltext><rsrctype>patent</rsrctype><creationdate>2022</creationdate><recordtype>patent</recordtype><sourceid>EVB</sourceid><recordid>eNqNi0sKwjAQQLNxIeodxgO4iBXsVoLiSly4L2MzbQfTTMinXt8KHsDV48F7S3U34lOOpc0sHkbKg1joJMIzEr7Y94DeQqRRpq9MHHNBB4EdwUBo4c3zUjL0HK2bk7VadOgSbX5cqe3l_DDXHQVpKAVsyVNuzE3rQ10ddb0_Vf80H91fN9Q</recordid><startdate>20220802</startdate><enddate>20220802</enddate><creator>CHO MIN-WOOK</creator><creator>YU HAO</creator><creator>XI JIALONG</creator><creator>HE YINGLONG</creator><creator>CAI TIECHEN</creator><creator>HOU LONG</creator><scope>EVB</scope></search><sort><creationdate>20220802</creationdate><title>Construction method for breaking and removing virtual pile head without girdling</title><author>CHO MIN-WOOK ; YU HAO ; XI JIALONG ; HE YINGLONG ; CAI TIECHEN ; HOU LONG</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-epo_espacenet_CN114837182A3</frbrgroupid><rsrctype>patents</rsrctype><prefilter>patents</prefilter><language>chi ; eng</language><creationdate>2022</creationdate><topic>EMBANKMENTS</topic><topic>EXCAVATIONS</topic><topic>FIXED CONSTRUCTIONS</topic><topic>FOUNDATIONS</topic><topic>HYDRAULIC ENGINEERING</topic><topic>SOIL SHIFTING</topic><topic>UNDERGROUND OR UNDERWATER STRUCTURES</topic><toplevel>online_resources</toplevel><creatorcontrib>CHO MIN-WOOK</creatorcontrib><creatorcontrib>YU HAO</creatorcontrib><creatorcontrib>XI JIALONG</creatorcontrib><creatorcontrib>HE YINGLONG</creatorcontrib><creatorcontrib>CAI TIECHEN</creatorcontrib><creatorcontrib>HOU LONG</creatorcontrib><collection>esp@cenet</collection></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext_linktorsrc</fulltext></delivery><addata><au>CHO MIN-WOOK</au><au>YU HAO</au><au>XI JIALONG</au><au>HE YINGLONG</au><au>CAI TIECHEN</au><au>HOU LONG</au><format>patent</format><genre>patent</genre><ristype>GEN</ristype><title>Construction method for breaking and removing virtual pile head without girdling</title><date>2022-08-02</date><risdate>2022</risdate><abstract>According to the construction method for removing the virtual pile head without girdling breaking, a high-pressure jet grouting machine is used for spraying a concrete retarder to the position of the pile head needing to be cleaned, the retarder reacts with the pile head concrete, the setting time of the pile head concrete is delayed, pile foundation concrete below the pile head concrete is not affected, and the pile head concrete is prevented from being damaged. After the lower pile foundation concrete is finally set, the pile head concrete is not finally set, so that the pile head concrete is convenient and efficient to clean and chiseled away, manual circular cutting of the pile head and stripping of pile foundation main reinforcements are not needed, the pile head concrete chiseling construction is small in manual demand, simple in procedure and high in working strength, meanwhile, dust and noise cannot be generated in the breaking process, and the construction cost is reduced. And the environment and noi</abstract><oa>free_for_read</oa></addata></record> |
fulltext | fulltext_linktorsrc |
identifier | |
ispartof | |
issn | |
language | chi ; eng |
recordid | cdi_epo_espacenet_CN114837182A |
source | esp@cenet |
subjects | EMBANKMENTS EXCAVATIONS FIXED CONSTRUCTIONS FOUNDATIONS HYDRAULIC ENGINEERING SOIL SHIFTING UNDERGROUND OR UNDERWATER STRUCTURES |
title | Construction method for breaking and removing virtual pile head without girdling |
url | https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2025-01-07T20%3A21%3A46IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-epo_EVB&rft_val_fmt=info:ofi/fmt:kev:mtx:patent&rft.genre=patent&rft.au=CHO%20MIN-WOOK&rft.date=2022-08-02&rft_id=info:doi/&rft_dat=%3Cepo_EVB%3ECN114837182A%3C/epo_EVB%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_id=info:pmid/&rfr_iscdi=true |