Temporary supporting structure for solving conflict between shield hole boundary beam of middle plate of subway station and shield

The temporary supporting structure system comprises a subway station structure, buttress columns are arranged on the end wall of the subway station structure, the station structure middle plate shield hole boundary beam conflicting with a shield area is lifted to avoid the shield area, and after lif...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Hauptverfasser: LI YANLONG, MAO NIANHUA, GAO XUANTAO, HOU MIANWANG, WANG LIXIN, YANG ZIGANG, WANG BO, GAO ZHIHONG, GAO SHENG
Format: Patent
Sprache:chi ; eng
Schlagworte:
Online-Zugang:Volltext bestellen
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
container_end_page
container_issue
container_start_page
container_title
container_volume
creator LI YANLONG
MAO NIANHUA
GAO XUANTAO
HOU MIANWANG
WANG LIXIN
YANG ZIGANG
WANG BO
GAO ZHIHONG
GAO SHENG
description The temporary supporting structure system comprises a subway station structure, buttress columns are arranged on the end wall of the subway station structure, the station structure middle plate shield hole boundary beam conflicting with a shield area is lifted to avoid the shield area, and after lifting, the subway station structure middle plate shield hole boundary beam conflicting with the shield area is supported by the buttress columns. The shield hole boundary beams, the end walls and the buttress columns bear horizontal loads together; meanwhile, a temporary horizontal force transmission component and a supporting bracket are vertically arranged at the position of a side beam of a shield hole after lifting, horizontal loads are transmitted to a middle plate and a middle longitudinal beam which are large in rigidity, and a complete and reliable structure stress system is formed; after shield construction is completed, the temporary force transmission component is cut off in a static force cutting mode, t
format Patent
fullrecord <record><control><sourceid>epo_EVB</sourceid><recordid>TN_cdi_epo_espacenet_CN114704309A</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><sourcerecordid>CN114704309A</sourcerecordid><originalsourceid>FETCH-epo_espacenet_CN114704309A3</originalsourceid><addsrcrecordid>eNqNTUsKwjAQ7caFqHcYDyC0tCAupSiuXHVf8pnYQJoJycTi1pPbQg_g6n14n23x7XAMFEX8QMphZmz9CxLHrDhHBEMRErn34iryxlnFIJEnRA9psOg0DOQQJGWvlxmJYgQyMFqtZz84wbjolOUk5hcWbMmD8Hrt74uNES7hYcVdcbzfuvZxwkA9piAUeuS-fVZVcy6burxc638yP5KsSsk</addsrcrecordid><sourcetype>Open Access Repository</sourcetype><iscdi>true</iscdi><recordtype>patent</recordtype></control><display><type>patent</type><title>Temporary supporting structure for solving conflict between shield hole boundary beam of middle plate of subway station and shield</title><source>esp@cenet</source><creator>LI YANLONG ; MAO NIANHUA ; GAO XUANTAO ; HOU MIANWANG ; WANG LIXIN ; YANG ZIGANG ; WANG BO ; GAO ZHIHONG ; GAO SHENG</creator><creatorcontrib>LI YANLONG ; MAO NIANHUA ; GAO XUANTAO ; HOU MIANWANG ; WANG LIXIN ; YANG ZIGANG ; WANG BO ; GAO ZHIHONG ; GAO SHENG</creatorcontrib><description>The temporary supporting structure system comprises a subway station structure, buttress columns are arranged on the end wall of the subway station structure, the station structure middle plate shield hole boundary beam conflicting with a shield area is lifted to avoid the shield area, and after lifting, the subway station structure middle plate shield hole boundary beam conflicting with the shield area is supported by the buttress columns. The shield hole boundary beams, the end walls and the buttress columns bear horizontal loads together; meanwhile, a temporary horizontal force transmission component and a supporting bracket are vertically arranged at the position of a side beam of a shield hole after lifting, horizontal loads are transmitted to a middle plate and a middle longitudinal beam which are large in rigidity, and a complete and reliable structure stress system is formed; after shield construction is completed, the temporary force transmission component is cut off in a static force cutting mode, t</description><language>chi ; eng</language><subject>EARTH DRILLING ; FIXED CONSTRUCTIONS ; GALLERIES ; LARGE UNDERGROUND CHAMBERS ; MINING ; SHAFTS ; TUNNELS</subject><creationdate>2022</creationdate><oa>free_for_read</oa><woscitedreferencessubscribed>false</woscitedreferencessubscribed></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><linktohtml>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20220705&amp;DB=EPODOC&amp;CC=CN&amp;NR=114704309A$$EHTML$$P50$$Gepo$$Hfree_for_read</linktohtml><link.rule.ids>230,308,776,881,25544,76293</link.rule.ids><linktorsrc>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20220705&amp;DB=EPODOC&amp;CC=CN&amp;NR=114704309A$$EView_record_in_European_Patent_Office$$FView_record_in_$$GEuropean_Patent_Office$$Hfree_for_read</linktorsrc></links><search><creatorcontrib>LI YANLONG</creatorcontrib><creatorcontrib>MAO NIANHUA</creatorcontrib><creatorcontrib>GAO XUANTAO</creatorcontrib><creatorcontrib>HOU MIANWANG</creatorcontrib><creatorcontrib>WANG LIXIN</creatorcontrib><creatorcontrib>YANG ZIGANG</creatorcontrib><creatorcontrib>WANG BO</creatorcontrib><creatorcontrib>GAO ZHIHONG</creatorcontrib><creatorcontrib>GAO SHENG</creatorcontrib><title>Temporary supporting structure for solving conflict between shield hole boundary beam of middle plate of subway station and shield</title><description>The temporary supporting structure system comprises a subway station structure, buttress columns are arranged on the end wall of the subway station structure, the station structure middle plate shield hole boundary beam conflicting with a shield area is lifted to avoid the shield area, and after lifting, the subway station structure middle plate shield hole boundary beam conflicting with the shield area is supported by the buttress columns. The shield hole boundary beams, the end walls and the buttress columns bear horizontal loads together; meanwhile, a temporary horizontal force transmission component and a supporting bracket are vertically arranged at the position of a side beam of a shield hole after lifting, horizontal loads are transmitted to a middle plate and a middle longitudinal beam which are large in rigidity, and a complete and reliable structure stress system is formed; after shield construction is completed, the temporary force transmission component is cut off in a static force cutting mode, t</description><subject>EARTH DRILLING</subject><subject>FIXED CONSTRUCTIONS</subject><subject>GALLERIES</subject><subject>LARGE UNDERGROUND CHAMBERS</subject><subject>MINING</subject><subject>SHAFTS</subject><subject>TUNNELS</subject><fulltext>true</fulltext><rsrctype>patent</rsrctype><creationdate>2022</creationdate><recordtype>patent</recordtype><sourceid>EVB</sourceid><recordid>eNqNTUsKwjAQ7caFqHcYDyC0tCAupSiuXHVf8pnYQJoJycTi1pPbQg_g6n14n23x7XAMFEX8QMphZmz9CxLHrDhHBEMRErn34iryxlnFIJEnRA9psOg0DOQQJGWvlxmJYgQyMFqtZz84wbjolOUk5hcWbMmD8Hrt74uNES7hYcVdcbzfuvZxwkA9piAUeuS-fVZVcy6burxc638yP5KsSsk</recordid><startdate>20220705</startdate><enddate>20220705</enddate><creator>LI YANLONG</creator><creator>MAO NIANHUA</creator><creator>GAO XUANTAO</creator><creator>HOU MIANWANG</creator><creator>WANG LIXIN</creator><creator>YANG ZIGANG</creator><creator>WANG BO</creator><creator>GAO ZHIHONG</creator><creator>GAO SHENG</creator><scope>EVB</scope></search><sort><creationdate>20220705</creationdate><title>Temporary supporting structure for solving conflict between shield hole boundary beam of middle plate of subway station and shield</title><author>LI YANLONG ; MAO NIANHUA ; GAO XUANTAO ; HOU MIANWANG ; WANG LIXIN ; YANG ZIGANG ; WANG BO ; GAO ZHIHONG ; GAO SHENG</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-epo_espacenet_CN114704309A3</frbrgroupid><rsrctype>patents</rsrctype><prefilter>patents</prefilter><language>chi ; eng</language><creationdate>2022</creationdate><topic>EARTH DRILLING</topic><topic>FIXED CONSTRUCTIONS</topic><topic>GALLERIES</topic><topic>LARGE UNDERGROUND CHAMBERS</topic><topic>MINING</topic><topic>SHAFTS</topic><topic>TUNNELS</topic><toplevel>online_resources</toplevel><creatorcontrib>LI YANLONG</creatorcontrib><creatorcontrib>MAO NIANHUA</creatorcontrib><creatorcontrib>GAO XUANTAO</creatorcontrib><creatorcontrib>HOU MIANWANG</creatorcontrib><creatorcontrib>WANG LIXIN</creatorcontrib><creatorcontrib>YANG ZIGANG</creatorcontrib><creatorcontrib>WANG BO</creatorcontrib><creatorcontrib>GAO ZHIHONG</creatorcontrib><creatorcontrib>GAO SHENG</creatorcontrib><collection>esp@cenet</collection></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext_linktorsrc</fulltext></delivery><addata><au>LI YANLONG</au><au>MAO NIANHUA</au><au>GAO XUANTAO</au><au>HOU MIANWANG</au><au>WANG LIXIN</au><au>YANG ZIGANG</au><au>WANG BO</au><au>GAO ZHIHONG</au><au>GAO SHENG</au><format>patent</format><genre>patent</genre><ristype>GEN</ristype><title>Temporary supporting structure for solving conflict between shield hole boundary beam of middle plate of subway station and shield</title><date>2022-07-05</date><risdate>2022</risdate><abstract>The temporary supporting structure system comprises a subway station structure, buttress columns are arranged on the end wall of the subway station structure, the station structure middle plate shield hole boundary beam conflicting with a shield area is lifted to avoid the shield area, and after lifting, the subway station structure middle plate shield hole boundary beam conflicting with the shield area is supported by the buttress columns. The shield hole boundary beams, the end walls and the buttress columns bear horizontal loads together; meanwhile, a temporary horizontal force transmission component and a supporting bracket are vertically arranged at the position of a side beam of a shield hole after lifting, horizontal loads are transmitted to a middle plate and a middle longitudinal beam which are large in rigidity, and a complete and reliable structure stress system is formed; after shield construction is completed, the temporary force transmission component is cut off in a static force cutting mode, t</abstract><oa>free_for_read</oa></addata></record>
fulltext fulltext_linktorsrc
identifier
ispartof
issn
language chi ; eng
recordid cdi_epo_espacenet_CN114704309A
source esp@cenet
subjects EARTH DRILLING
FIXED CONSTRUCTIONS
GALLERIES
LARGE UNDERGROUND CHAMBERS
MINING
SHAFTS
TUNNELS
title Temporary supporting structure for solving conflict between shield hole boundary beam of middle plate of subway station and shield
url https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2025-01-27T19%3A03%3A33IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-epo_EVB&rft_val_fmt=info:ofi/fmt:kev:mtx:patent&rft.genre=patent&rft.au=LI%20YANLONG&rft.date=2022-07-05&rft_id=info:doi/&rft_dat=%3Cepo_EVB%3ECN114704309A%3C/epo_EVB%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_id=info:pmid/&rfr_iscdi=true