Construction method for semi-hidden framing glass curtain wall of large building

The invention discloses a construction method of a semi-hidden framing glass curtain wall of a large building, which is characterized by comprising the following steps: step 1, surveying and setting out; secondly, the embedded part is checked and installed; 3, pre-assembling transverse and vertical...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Hauptverfasser: LIU YAO, XU NING, TIAN QIANG, XU LIANG, WANG ZHENLING, MENG TONGCAN, LI QI, XU HOUCAI, WANG PENGXIAO, JIA RUIYU, MA WEIGUO, LU MIN, BAI YUNPENG, WANG ZIWEI, JI ZHI, WANG LANTAO, ZHOU LEILEI, LIU XINJIA, HAN SEUNG-GYU, LIU XUEMEI, GE LIANG
Format: Patent
Sprache:chi ; eng
Schlagworte:
Online-Zugang:Volltext bestellen
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
container_end_page
container_issue
container_start_page
container_title
container_volume
creator LIU YAO
XU NING
TIAN QIANG
XU LIANG
WANG ZHENLING
MENG TONGCAN
LI QI
XU HOUCAI
WANG PENGXIAO
JIA RUIYU
MA WEIGUO
LU MIN
BAI YUNPENG
WANG ZIWEI
JI ZHI
WANG LANTAO
ZHOU LEILEI
LIU XINJIA
HAN SEUNG-GYU
LIU XUEMEI
GE LIANG
description The invention discloses a construction method of a semi-hidden framing glass curtain wall of a large building, which is characterized by comprising the following steps: step 1, surveying and setting out; secondly, the embedded part is checked and installed; 3, pre-assembling transverse and vertical keels; fourthly, galvanized connecting pieces are installed; fifthly, vertical main keels and transverse auxiliary keels are installed; sixthly, thermal insulation joints are constructed; seventhly, fireproof joints are constructed; 8, carrying out hidden acceptance inspection; ninthly, glass plates are installed; tenthly, an opening sash is installed; step 11, sealing; and step 12, completion acceptance. The stability of the semi-hidden framing glass curtain wall after installation is guaranteed through procedure arrangement and inspection of the installation method and structure of each step, and the semi-hidden framing glass curtain wall has excellent heat preservation and waterproof capacity. 本发明公开了一种大型建筑的半隐框玻璃
format Patent
fullrecord <record><control><sourceid>epo_EVB</sourceid><recordid>TN_cdi_epo_espacenet_CN114412035A</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><sourcerecordid>CN114412035A</sourcerecordid><originalsourceid>FETCH-epo_espacenet_CN114412035A3</originalsourceid><addsrcrecordid>eNqNyjEOAiEQAEAaC6P-YX3AJeKdDzBEY2Us7C8rLHcksFxYiN_XwgdYTTNr9TCZpZZma8gMieqcHfhcQCiFbg7OEYMvmAJPMEUUAdtKxcDwxhghe4hYJoJXC9F901atPEah3c-N2l8vT3PraMkjyYKWmOpo7loPgz4e-tO5_-d8AK2IN00</addsrcrecordid><sourcetype>Open Access Repository</sourcetype><iscdi>true</iscdi><recordtype>patent</recordtype></control><display><type>patent</type><title>Construction method for semi-hidden framing glass curtain wall of large building</title><source>esp@cenet</source><creator>LIU YAO ; XU NING ; TIAN QIANG ; XU LIANG ; WANG ZHENLING ; MENG TONGCAN ; LI QI ; XU HOUCAI ; WANG PENGXIAO ; JIA RUIYU ; MA WEIGUO ; LU MIN ; BAI YUNPENG ; WANG ZIWEI ; JI ZHI ; WANG LANTAO ; ZHOU LEILEI ; LIU XINJIA ; HAN SEUNG-GYU ; LIU XUEMEI ; GE LIANG</creator><creatorcontrib>LIU YAO ; XU NING ; TIAN QIANG ; XU LIANG ; WANG ZHENLING ; MENG TONGCAN ; LI QI ; XU HOUCAI ; WANG PENGXIAO ; JIA RUIYU ; MA WEIGUO ; LU MIN ; BAI YUNPENG ; WANG ZIWEI ; JI ZHI ; WANG LANTAO ; ZHOU LEILEI ; LIU XINJIA ; HAN SEUNG-GYU ; LIU XUEMEI ; GE LIANG</creatorcontrib><description>The invention discloses a construction method of a semi-hidden framing glass curtain wall of a large building, which is characterized by comprising the following steps: step 1, surveying and setting out; secondly, the embedded part is checked and installed; 3, pre-assembling transverse and vertical keels; fourthly, galvanized connecting pieces are installed; fifthly, vertical main keels and transverse auxiliary keels are installed; sixthly, thermal insulation joints are constructed; seventhly, fireproof joints are constructed; 8, carrying out hidden acceptance inspection; ninthly, glass plates are installed; tenthly, an opening sash is installed; step 11, sealing; and step 12, completion acceptance. The stability of the semi-hidden framing glass curtain wall after installation is guaranteed through procedure arrangement and inspection of the installation method and structure of each step, and the semi-hidden framing glass curtain wall has excellent heat preservation and waterproof capacity. 本发明公开了一种大型建筑的半隐框玻璃</description><language>chi ; eng</language><subject>BUILDING ; BUILDING IMPLEMENTS OR OTHER BUILDING AIDS, OR THEIRUSE ; CEILINGS ; FIXED CONSTRUCTIONS ; FLOORS ; FORMS ; GENERAL BUILDING CONSTRUCTIONS ; HANDLING BUILDING MATERIALS ON THE SITE ; INSULATION OR OTHER PROTECTION OF BUILDINGS ; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTINGBUILDINGS ; ROOFS ; SCAFFOLDING ; SHUTTERING ; WALLS, e.g. PARTITIONS</subject><creationdate>2022</creationdate><oa>free_for_read</oa><woscitedreferencessubscribed>false</woscitedreferencessubscribed></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><linktohtml>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20220429&amp;DB=EPODOC&amp;CC=CN&amp;NR=114412035A$$EHTML$$P50$$Gepo$$Hfree_for_read</linktohtml><link.rule.ids>230,308,776,881,25542,76289</link.rule.ids><linktorsrc>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20220429&amp;DB=EPODOC&amp;CC=CN&amp;NR=114412035A$$EView_record_in_European_Patent_Office$$FView_record_in_$$GEuropean_Patent_Office$$Hfree_for_read</linktorsrc></links><search><creatorcontrib>LIU YAO</creatorcontrib><creatorcontrib>XU NING</creatorcontrib><creatorcontrib>TIAN QIANG</creatorcontrib><creatorcontrib>XU LIANG</creatorcontrib><creatorcontrib>WANG ZHENLING</creatorcontrib><creatorcontrib>MENG TONGCAN</creatorcontrib><creatorcontrib>LI QI</creatorcontrib><creatorcontrib>XU HOUCAI</creatorcontrib><creatorcontrib>WANG PENGXIAO</creatorcontrib><creatorcontrib>JIA RUIYU</creatorcontrib><creatorcontrib>MA WEIGUO</creatorcontrib><creatorcontrib>LU MIN</creatorcontrib><creatorcontrib>BAI YUNPENG</creatorcontrib><creatorcontrib>WANG ZIWEI</creatorcontrib><creatorcontrib>JI ZHI</creatorcontrib><creatorcontrib>WANG LANTAO</creatorcontrib><creatorcontrib>ZHOU LEILEI</creatorcontrib><creatorcontrib>LIU XINJIA</creatorcontrib><creatorcontrib>HAN SEUNG-GYU</creatorcontrib><creatorcontrib>LIU XUEMEI</creatorcontrib><creatorcontrib>GE LIANG</creatorcontrib><title>Construction method for semi-hidden framing glass curtain wall of large building</title><description>The invention discloses a construction method of a semi-hidden framing glass curtain wall of a large building, which is characterized by comprising the following steps: step 1, surveying and setting out; secondly, the embedded part is checked and installed; 3, pre-assembling transverse and vertical keels; fourthly, galvanized connecting pieces are installed; fifthly, vertical main keels and transverse auxiliary keels are installed; sixthly, thermal insulation joints are constructed; seventhly, fireproof joints are constructed; 8, carrying out hidden acceptance inspection; ninthly, glass plates are installed; tenthly, an opening sash is installed; step 11, sealing; and step 12, completion acceptance. The stability of the semi-hidden framing glass curtain wall after installation is guaranteed through procedure arrangement and inspection of the installation method and structure of each step, and the semi-hidden framing glass curtain wall has excellent heat preservation and waterproof capacity. 本发明公开了一种大型建筑的半隐框玻璃</description><subject>BUILDING</subject><subject>BUILDING IMPLEMENTS OR OTHER BUILDING AIDS, OR THEIRUSE</subject><subject>CEILINGS</subject><subject>FIXED CONSTRUCTIONS</subject><subject>FLOORS</subject><subject>FORMS</subject><subject>GENERAL BUILDING CONSTRUCTIONS</subject><subject>HANDLING BUILDING MATERIALS ON THE SITE</subject><subject>INSULATION OR OTHER PROTECTION OF BUILDINGS</subject><subject>REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTINGBUILDINGS</subject><subject>ROOFS</subject><subject>SCAFFOLDING</subject><subject>SHUTTERING</subject><subject>WALLS, e.g. PARTITIONS</subject><fulltext>true</fulltext><rsrctype>patent</rsrctype><creationdate>2022</creationdate><recordtype>patent</recordtype><sourceid>EVB</sourceid><recordid>eNqNyjEOAiEQAEAaC6P-YX3AJeKdDzBEY2Us7C8rLHcksFxYiN_XwgdYTTNr9TCZpZZma8gMieqcHfhcQCiFbg7OEYMvmAJPMEUUAdtKxcDwxhghe4hYJoJXC9F901atPEah3c-N2l8vT3PraMkjyYKWmOpo7loPgz4e-tO5_-d8AK2IN00</recordid><startdate>20220429</startdate><enddate>20220429</enddate><creator>LIU YAO</creator><creator>XU NING</creator><creator>TIAN QIANG</creator><creator>XU LIANG</creator><creator>WANG ZHENLING</creator><creator>MENG TONGCAN</creator><creator>LI QI</creator><creator>XU HOUCAI</creator><creator>WANG PENGXIAO</creator><creator>JIA RUIYU</creator><creator>MA WEIGUO</creator><creator>LU MIN</creator><creator>BAI YUNPENG</creator><creator>WANG ZIWEI</creator><creator>JI ZHI</creator><creator>WANG LANTAO</creator><creator>ZHOU LEILEI</creator><creator>LIU XINJIA</creator><creator>HAN SEUNG-GYU</creator><creator>LIU XUEMEI</creator><creator>GE LIANG</creator><scope>EVB</scope></search><sort><creationdate>20220429</creationdate><title>Construction method for semi-hidden framing glass curtain wall of large building</title><author>LIU YAO ; XU NING ; TIAN QIANG ; XU LIANG ; WANG ZHENLING ; MENG TONGCAN ; LI QI ; XU HOUCAI ; WANG PENGXIAO ; JIA RUIYU ; MA WEIGUO ; LU MIN ; BAI YUNPENG ; WANG ZIWEI ; JI ZHI ; WANG LANTAO ; ZHOU LEILEI ; LIU XINJIA ; HAN SEUNG-GYU ; LIU XUEMEI ; GE LIANG</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-epo_espacenet_CN114412035A3</frbrgroupid><rsrctype>patents</rsrctype><prefilter>patents</prefilter><language>chi ; eng</language><creationdate>2022</creationdate><topic>BUILDING</topic><topic>BUILDING IMPLEMENTS OR OTHER BUILDING AIDS, OR THEIRUSE</topic><topic>CEILINGS</topic><topic>FIXED CONSTRUCTIONS</topic><topic>FLOORS</topic><topic>FORMS</topic><topic>GENERAL BUILDING CONSTRUCTIONS</topic><topic>HANDLING BUILDING MATERIALS ON THE SITE</topic><topic>INSULATION OR OTHER PROTECTION OF BUILDINGS</topic><topic>REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTINGBUILDINGS</topic><topic>ROOFS</topic><topic>SCAFFOLDING</topic><topic>SHUTTERING</topic><topic>WALLS, e.g. PARTITIONS</topic><toplevel>online_resources</toplevel><creatorcontrib>LIU YAO</creatorcontrib><creatorcontrib>XU NING</creatorcontrib><creatorcontrib>TIAN QIANG</creatorcontrib><creatorcontrib>XU LIANG</creatorcontrib><creatorcontrib>WANG ZHENLING</creatorcontrib><creatorcontrib>MENG TONGCAN</creatorcontrib><creatorcontrib>LI QI</creatorcontrib><creatorcontrib>XU HOUCAI</creatorcontrib><creatorcontrib>WANG PENGXIAO</creatorcontrib><creatorcontrib>JIA RUIYU</creatorcontrib><creatorcontrib>MA WEIGUO</creatorcontrib><creatorcontrib>LU MIN</creatorcontrib><creatorcontrib>BAI YUNPENG</creatorcontrib><creatorcontrib>WANG ZIWEI</creatorcontrib><creatorcontrib>JI ZHI</creatorcontrib><creatorcontrib>WANG LANTAO</creatorcontrib><creatorcontrib>ZHOU LEILEI</creatorcontrib><creatorcontrib>LIU XINJIA</creatorcontrib><creatorcontrib>HAN SEUNG-GYU</creatorcontrib><creatorcontrib>LIU XUEMEI</creatorcontrib><creatorcontrib>GE LIANG</creatorcontrib><collection>esp@cenet</collection></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext_linktorsrc</fulltext></delivery><addata><au>LIU YAO</au><au>XU NING</au><au>TIAN QIANG</au><au>XU LIANG</au><au>WANG ZHENLING</au><au>MENG TONGCAN</au><au>LI QI</au><au>XU HOUCAI</au><au>WANG PENGXIAO</au><au>JIA RUIYU</au><au>MA WEIGUO</au><au>LU MIN</au><au>BAI YUNPENG</au><au>WANG ZIWEI</au><au>JI ZHI</au><au>WANG LANTAO</au><au>ZHOU LEILEI</au><au>LIU XINJIA</au><au>HAN SEUNG-GYU</au><au>LIU XUEMEI</au><au>GE LIANG</au><format>patent</format><genre>patent</genre><ristype>GEN</ristype><title>Construction method for semi-hidden framing glass curtain wall of large building</title><date>2022-04-29</date><risdate>2022</risdate><abstract>The invention discloses a construction method of a semi-hidden framing glass curtain wall of a large building, which is characterized by comprising the following steps: step 1, surveying and setting out; secondly, the embedded part is checked and installed; 3, pre-assembling transverse and vertical keels; fourthly, galvanized connecting pieces are installed; fifthly, vertical main keels and transverse auxiliary keels are installed; sixthly, thermal insulation joints are constructed; seventhly, fireproof joints are constructed; 8, carrying out hidden acceptance inspection; ninthly, glass plates are installed; tenthly, an opening sash is installed; step 11, sealing; and step 12, completion acceptance. The stability of the semi-hidden framing glass curtain wall after installation is guaranteed through procedure arrangement and inspection of the installation method and structure of each step, and the semi-hidden framing glass curtain wall has excellent heat preservation and waterproof capacity. 本发明公开了一种大型建筑的半隐框玻璃</abstract><oa>free_for_read</oa></addata></record>
fulltext fulltext_linktorsrc
identifier
ispartof
issn
language chi ; eng
recordid cdi_epo_espacenet_CN114412035A
source esp@cenet
subjects BUILDING
BUILDING IMPLEMENTS OR OTHER BUILDING AIDS, OR THEIRUSE
CEILINGS
FIXED CONSTRUCTIONS
FLOORS
FORMS
GENERAL BUILDING CONSTRUCTIONS
HANDLING BUILDING MATERIALS ON THE SITE
INSULATION OR OTHER PROTECTION OF BUILDINGS
REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTINGBUILDINGS
ROOFS
SCAFFOLDING
SHUTTERING
WALLS, e.g. PARTITIONS
title Construction method for semi-hidden framing glass curtain wall of large building
url https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2025-02-05T02%3A34%3A38IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-epo_EVB&rft_val_fmt=info:ofi/fmt:kev:mtx:patent&rft.genre=patent&rft.au=LIU%20YAO&rft.date=2022-04-29&rft_id=info:doi/&rft_dat=%3Cepo_EVB%3ECN114412035A%3C/epo_EVB%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_id=info:pmid/&rfr_iscdi=true