Ultra-deep foundation pit group asynchronous excavation clockwise and anticlockwise combined safety construction method

The invention relates to the field of building engineering construction, and provides an ultra-deep foundation pit group asynchronous excavation clockwise and anticlockwise combined safety construction method which comprises the following steps: adopting a large-rigidity enclosure structure when a c...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Hauptverfasser: HU SHUFANG, LIU DONG, LIU ZIYANG, WANG JIE, JIN PING, WANG SHENGTAO, LIU ZIHAN, XIE TIANCI, DENG NENGWEI, LIU QIUTONG, CHEN TAO, WANG HONGQIAN, WANG YANG, WU JIALIN, LU MIAOXIANG, FANG ZHIHAI, DENG XIFEI, ZHANG GUANGHUI
Format: Patent
Sprache:chi ; eng
Schlagworte:
Online-Zugang:Volltext bestellen
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
container_end_page
container_issue
container_start_page
container_title
container_volume
creator HU SHUFANG
LIU DONG
LIU ZIYANG
WANG JIE
JIN PING
WANG SHENGTAO
LIU ZIHAN
XIE TIANCI
DENG NENGWEI
LIU QIUTONG
CHEN TAO
WANG HONGQIAN
WANG YANG
WU JIALIN
LU MIAOXIANG
FANG ZHIHAI
DENG XIFEI
ZHANG GUANGHUI
description The invention relates to the field of building engineering construction, and provides an ultra-deep foundation pit group asynchronous excavation clockwise and anticlockwise combined safety construction method which comprises the following steps: adopting a large-rigidity enclosure structure when a construction scheme is designed; arranging connecting beams between the adjacent foundation pits; arranging drawing strips in the foundation pits and between the adjacent foundation pits, and reinforcing the skirt edge foundation; controlling the error height during foundation pit excavation; predicting the deformation trend of the foundation pit group by using a data inversion system, and guiding the next foundation pit deformation control key point; when the deformation amount of the foundation pit and the surrounding buildings exceeds the limit or the displacement rate exceeds the early warning value, taking corresponding deformation control measures; excavating earth below the reversed plate and synchronously co
format Patent
fullrecord <record><control><sourceid>epo_EVB</sourceid><recordid>TN_cdi_epo_espacenet_CN114045870A</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><sourcerecordid>CN114045870A</sourcerecordid><originalsourceid>FETCH-epo_espacenet_CN114045870A3</originalsourceid><addsrcrecordid>eNqNi7EKwkAQRNNYiPoP5wcEEoxoK0GxstI6rHcbc5jsHnd7xvy9QQVbi2GYx5tp0l9a8ZAaRKdqjmRALJNyVtTNc3QKwkC68Uwcg8KnhsfH0C3re28DKiAzRuyPaO6ultCoADXKMG4K4qN-HzuUhs08mdTQBlx8e5YsD_tzeUzRcYXBgUZCqcpTnhdZsd5ust3qH-cFWg1HnA</addsrcrecordid><sourcetype>Open Access Repository</sourcetype><iscdi>true</iscdi><recordtype>patent</recordtype></control><display><type>patent</type><title>Ultra-deep foundation pit group asynchronous excavation clockwise and anticlockwise combined safety construction method</title><source>esp@cenet</source><creator>HU SHUFANG ; LIU DONG ; LIU ZIYANG ; WANG JIE ; JIN PING ; WANG SHENGTAO ; LIU ZIHAN ; XIE TIANCI ; DENG NENGWEI ; LIU QIUTONG ; CHEN TAO ; WANG HONGQIAN ; WANG YANG ; WU JIALIN ; LU MIAOXIANG ; FANG ZHIHAI ; DENG XIFEI ; ZHANG GUANGHUI</creator><creatorcontrib>HU SHUFANG ; LIU DONG ; LIU ZIYANG ; WANG JIE ; JIN PING ; WANG SHENGTAO ; LIU ZIHAN ; XIE TIANCI ; DENG NENGWEI ; LIU QIUTONG ; CHEN TAO ; WANG HONGQIAN ; WANG YANG ; WU JIALIN ; LU MIAOXIANG ; FANG ZHIHAI ; DENG XIFEI ; ZHANG GUANGHUI</creatorcontrib><description>The invention relates to the field of building engineering construction, and provides an ultra-deep foundation pit group asynchronous excavation clockwise and anticlockwise combined safety construction method which comprises the following steps: adopting a large-rigidity enclosure structure when a construction scheme is designed; arranging connecting beams between the adjacent foundation pits; arranging drawing strips in the foundation pits and between the adjacent foundation pits, and reinforcing the skirt edge foundation; controlling the error height during foundation pit excavation; predicting the deformation trend of the foundation pit group by using a data inversion system, and guiding the next foundation pit deformation control key point; when the deformation amount of the foundation pit and the surrounding buildings exceeds the limit or the displacement rate exceeds the early warning value, taking corresponding deformation control measures; excavating earth below the reversed plate and synchronously co</description><language>chi ; eng</language><subject>CALCULATING ; COMPUTING ; COUNTING ; ELECTRIC DIGITAL DATA PROCESSING ; EMBANKMENTS ; EXCAVATIONS ; FIXED CONSTRUCTIONS ; FOUNDATIONS ; HYDRAULIC ENGINEERING ; PHYSICS ; SOIL SHIFTING ; UNDERGROUND OR UNDERWATER STRUCTURES</subject><creationdate>2022</creationdate><oa>free_for_read</oa><woscitedreferencessubscribed>false</woscitedreferencessubscribed></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><linktohtml>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20220215&amp;DB=EPODOC&amp;CC=CN&amp;NR=114045870A$$EHTML$$P50$$Gepo$$Hfree_for_read</linktohtml><link.rule.ids>230,308,780,885,25564,76547</link.rule.ids><linktorsrc>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20220215&amp;DB=EPODOC&amp;CC=CN&amp;NR=114045870A$$EView_record_in_European_Patent_Office$$FView_record_in_$$GEuropean_Patent_Office$$Hfree_for_read</linktorsrc></links><search><creatorcontrib>HU SHUFANG</creatorcontrib><creatorcontrib>LIU DONG</creatorcontrib><creatorcontrib>LIU ZIYANG</creatorcontrib><creatorcontrib>WANG JIE</creatorcontrib><creatorcontrib>JIN PING</creatorcontrib><creatorcontrib>WANG SHENGTAO</creatorcontrib><creatorcontrib>LIU ZIHAN</creatorcontrib><creatorcontrib>XIE TIANCI</creatorcontrib><creatorcontrib>DENG NENGWEI</creatorcontrib><creatorcontrib>LIU QIUTONG</creatorcontrib><creatorcontrib>CHEN TAO</creatorcontrib><creatorcontrib>WANG HONGQIAN</creatorcontrib><creatorcontrib>WANG YANG</creatorcontrib><creatorcontrib>WU JIALIN</creatorcontrib><creatorcontrib>LU MIAOXIANG</creatorcontrib><creatorcontrib>FANG ZHIHAI</creatorcontrib><creatorcontrib>DENG XIFEI</creatorcontrib><creatorcontrib>ZHANG GUANGHUI</creatorcontrib><title>Ultra-deep foundation pit group asynchronous excavation clockwise and anticlockwise combined safety construction method</title><description>The invention relates to the field of building engineering construction, and provides an ultra-deep foundation pit group asynchronous excavation clockwise and anticlockwise combined safety construction method which comprises the following steps: adopting a large-rigidity enclosure structure when a construction scheme is designed; arranging connecting beams between the adjacent foundation pits; arranging drawing strips in the foundation pits and between the adjacent foundation pits, and reinforcing the skirt edge foundation; controlling the error height during foundation pit excavation; predicting the deformation trend of the foundation pit group by using a data inversion system, and guiding the next foundation pit deformation control key point; when the deformation amount of the foundation pit and the surrounding buildings exceeds the limit or the displacement rate exceeds the early warning value, taking corresponding deformation control measures; excavating earth below the reversed plate and synchronously co</description><subject>CALCULATING</subject><subject>COMPUTING</subject><subject>COUNTING</subject><subject>ELECTRIC DIGITAL DATA PROCESSING</subject><subject>EMBANKMENTS</subject><subject>EXCAVATIONS</subject><subject>FIXED CONSTRUCTIONS</subject><subject>FOUNDATIONS</subject><subject>HYDRAULIC ENGINEERING</subject><subject>PHYSICS</subject><subject>SOIL SHIFTING</subject><subject>UNDERGROUND OR UNDERWATER STRUCTURES</subject><fulltext>true</fulltext><rsrctype>patent</rsrctype><creationdate>2022</creationdate><recordtype>patent</recordtype><sourceid>EVB</sourceid><recordid>eNqNi7EKwkAQRNNYiPoP5wcEEoxoK0GxstI6rHcbc5jsHnd7xvy9QQVbi2GYx5tp0l9a8ZAaRKdqjmRALJNyVtTNc3QKwkC68Uwcg8KnhsfH0C3re28DKiAzRuyPaO6ultCoADXKMG4K4qN-HzuUhs08mdTQBlx8e5YsD_tzeUzRcYXBgUZCqcpTnhdZsd5ust3qH-cFWg1HnA</recordid><startdate>20220215</startdate><enddate>20220215</enddate><creator>HU SHUFANG</creator><creator>LIU DONG</creator><creator>LIU ZIYANG</creator><creator>WANG JIE</creator><creator>JIN PING</creator><creator>WANG SHENGTAO</creator><creator>LIU ZIHAN</creator><creator>XIE TIANCI</creator><creator>DENG NENGWEI</creator><creator>LIU QIUTONG</creator><creator>CHEN TAO</creator><creator>WANG HONGQIAN</creator><creator>WANG YANG</creator><creator>WU JIALIN</creator><creator>LU MIAOXIANG</creator><creator>FANG ZHIHAI</creator><creator>DENG XIFEI</creator><creator>ZHANG GUANGHUI</creator><scope>EVB</scope></search><sort><creationdate>20220215</creationdate><title>Ultra-deep foundation pit group asynchronous excavation clockwise and anticlockwise combined safety construction method</title><author>HU SHUFANG ; LIU DONG ; LIU ZIYANG ; WANG JIE ; JIN PING ; WANG SHENGTAO ; LIU ZIHAN ; XIE TIANCI ; DENG NENGWEI ; LIU QIUTONG ; CHEN TAO ; WANG HONGQIAN ; WANG YANG ; WU JIALIN ; LU MIAOXIANG ; FANG ZHIHAI ; DENG XIFEI ; ZHANG GUANGHUI</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-epo_espacenet_CN114045870A3</frbrgroupid><rsrctype>patents</rsrctype><prefilter>patents</prefilter><language>chi ; eng</language><creationdate>2022</creationdate><topic>CALCULATING</topic><topic>COMPUTING</topic><topic>COUNTING</topic><topic>ELECTRIC DIGITAL DATA PROCESSING</topic><topic>EMBANKMENTS</topic><topic>EXCAVATIONS</topic><topic>FIXED CONSTRUCTIONS</topic><topic>FOUNDATIONS</topic><topic>HYDRAULIC ENGINEERING</topic><topic>PHYSICS</topic><topic>SOIL SHIFTING</topic><topic>UNDERGROUND OR UNDERWATER STRUCTURES</topic><toplevel>online_resources</toplevel><creatorcontrib>HU SHUFANG</creatorcontrib><creatorcontrib>LIU DONG</creatorcontrib><creatorcontrib>LIU ZIYANG</creatorcontrib><creatorcontrib>WANG JIE</creatorcontrib><creatorcontrib>JIN PING</creatorcontrib><creatorcontrib>WANG SHENGTAO</creatorcontrib><creatorcontrib>LIU ZIHAN</creatorcontrib><creatorcontrib>XIE TIANCI</creatorcontrib><creatorcontrib>DENG NENGWEI</creatorcontrib><creatorcontrib>LIU QIUTONG</creatorcontrib><creatorcontrib>CHEN TAO</creatorcontrib><creatorcontrib>WANG HONGQIAN</creatorcontrib><creatorcontrib>WANG YANG</creatorcontrib><creatorcontrib>WU JIALIN</creatorcontrib><creatorcontrib>LU MIAOXIANG</creatorcontrib><creatorcontrib>FANG ZHIHAI</creatorcontrib><creatorcontrib>DENG XIFEI</creatorcontrib><creatorcontrib>ZHANG GUANGHUI</creatorcontrib><collection>esp@cenet</collection></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext_linktorsrc</fulltext></delivery><addata><au>HU SHUFANG</au><au>LIU DONG</au><au>LIU ZIYANG</au><au>WANG JIE</au><au>JIN PING</au><au>WANG SHENGTAO</au><au>LIU ZIHAN</au><au>XIE TIANCI</au><au>DENG NENGWEI</au><au>LIU QIUTONG</au><au>CHEN TAO</au><au>WANG HONGQIAN</au><au>WANG YANG</au><au>WU JIALIN</au><au>LU MIAOXIANG</au><au>FANG ZHIHAI</au><au>DENG XIFEI</au><au>ZHANG GUANGHUI</au><format>patent</format><genre>patent</genre><ristype>GEN</ristype><title>Ultra-deep foundation pit group asynchronous excavation clockwise and anticlockwise combined safety construction method</title><date>2022-02-15</date><risdate>2022</risdate><abstract>The invention relates to the field of building engineering construction, and provides an ultra-deep foundation pit group asynchronous excavation clockwise and anticlockwise combined safety construction method which comprises the following steps: adopting a large-rigidity enclosure structure when a construction scheme is designed; arranging connecting beams between the adjacent foundation pits; arranging drawing strips in the foundation pits and between the adjacent foundation pits, and reinforcing the skirt edge foundation; controlling the error height during foundation pit excavation; predicting the deformation trend of the foundation pit group by using a data inversion system, and guiding the next foundation pit deformation control key point; when the deformation amount of the foundation pit and the surrounding buildings exceeds the limit or the displacement rate exceeds the early warning value, taking corresponding deformation control measures; excavating earth below the reversed plate and synchronously co</abstract><oa>free_for_read</oa></addata></record>
fulltext fulltext_linktorsrc
identifier
ispartof
issn
language chi ; eng
recordid cdi_epo_espacenet_CN114045870A
source esp@cenet
subjects CALCULATING
COMPUTING
COUNTING
ELECTRIC DIGITAL DATA PROCESSING
EMBANKMENTS
EXCAVATIONS
FIXED CONSTRUCTIONS
FOUNDATIONS
HYDRAULIC ENGINEERING
PHYSICS
SOIL SHIFTING
UNDERGROUND OR UNDERWATER STRUCTURES
title Ultra-deep foundation pit group asynchronous excavation clockwise and anticlockwise combined safety construction method
url https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2024-12-29T20%3A44%3A36IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-epo_EVB&rft_val_fmt=info:ofi/fmt:kev:mtx:patent&rft.genre=patent&rft.au=HU%20SHUFANG&rft.date=2022-02-15&rft_id=info:doi/&rft_dat=%3Cepo_EVB%3ECN114045870A%3C/epo_EVB%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_id=info:pmid/&rfr_iscdi=true