Construction method for penetrating through gas pipeline with pressure downwards at ultra-close distance by using shield tunneling machine
The invention discloses a construction method for penetrating through a gas pipeline with pressure downwards at an ultra-close distance by using a shield tunneling machine, and relates to the technical field of shield tunneling machine construction methods. The construction method comprises the foll...
Gespeichert in:
Hauptverfasser: | , , , , , , , , , , |
---|---|
Format: | Patent |
Sprache: | chi ; eng |
Schlagworte: | |
Online-Zugang: | Volltext bestellen |
Tags: |
Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
|
container_end_page | |
---|---|
container_issue | |
container_start_page | |
container_title | |
container_volume | |
creator | ZHANG JIALE SUN YINGRUI LI KAIJUN QI YUSHEN PENG BIWU TAN CONGLONG ZHAO ZERU LIU BOTAO FAN ZUNFENG WANG FENG BI HAORAN |
description | The invention discloses a construction method for penetrating through a gas pipeline with pressure downwards at an ultra-close distance by using a shield tunneling machine, and relates to the technical field of shield tunneling machine construction methods. The construction method comprises the following steps of stopping the shield tunneling machine; accurately positioning the gas pipeline; performing three-dimensional modeling; adjusting the slope of the line, and calculating the nearest distance between the shield tunneling machine and the gas pipeline; replacing fuel gas; re-pushing the shield tunneling machine; grouting for the second time; and recovering the fuel gas. According to the construction method, nitrogen is adopted for replacing fuel gas for pressure maintaining, and the risk when the shield tunneling machine passes is reduced; the soil settlement at a shield body is guaranteed by adopting an anti-mud-effect construction method, and the soil pressure balance in the crossing process is guarante |
format | Patent |
fullrecord | <record><control><sourceid>epo_EVB</sourceid><recordid>TN_cdi_epo_espacenet_CN112983442A</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><sourcerecordid>CN112983442A</sourcerecordid><originalsourceid>FETCH-epo_espacenet_CN112983442A3</originalsourceid><addsrcrecordid>eNqNjjsOwjAQRNNQIOAOywFS5FNAiSIQFRV9ZOxNbMlZW961Iq7AqUkkDkA1xcx7mm3x6QKxpKzFBYIJxQYDQ0gQkVCSEkcjiE0hjxZGxRBdRO8IYXZiISZkzgnBhJlmlQyDEsh-IUvtAy-FY1GkEV5vyLza2Dr0BiQTraYRJqXtYtwXm0F5xsMvd8Xxdn129xJj6JGj0uulvntUVX0-NW1bX5p_Nl9oRk5X</addsrcrecordid><sourcetype>Open Access Repository</sourcetype><iscdi>true</iscdi><recordtype>patent</recordtype></control><display><type>patent</type><title>Construction method for penetrating through gas pipeline with pressure downwards at ultra-close distance by using shield tunneling machine</title><source>esp@cenet</source><creator>ZHANG JIALE ; SUN YINGRUI ; LI KAIJUN ; QI YUSHEN ; PENG BIWU ; TAN CONGLONG ; ZHAO ZERU ; LIU BOTAO ; FAN ZUNFENG ; WANG FENG ; BI HAORAN</creator><creatorcontrib>ZHANG JIALE ; SUN YINGRUI ; LI KAIJUN ; QI YUSHEN ; PENG BIWU ; TAN CONGLONG ; ZHAO ZERU ; LIU BOTAO ; FAN ZUNFENG ; WANG FENG ; BI HAORAN</creatorcontrib><description>The invention discloses a construction method for penetrating through a gas pipeline with pressure downwards at an ultra-close distance by using a shield tunneling machine, and relates to the technical field of shield tunneling machine construction methods. The construction method comprises the following steps of stopping the shield tunneling machine; accurately positioning the gas pipeline; performing three-dimensional modeling; adjusting the slope of the line, and calculating the nearest distance between the shield tunneling machine and the gas pipeline; replacing fuel gas; re-pushing the shield tunneling machine; grouting for the second time; and recovering the fuel gas. According to the construction method, nitrogen is adopted for replacing fuel gas for pressure maintaining, and the risk when the shield tunneling machine passes is reduced; the soil settlement at a shield body is guaranteed by adopting an anti-mud-effect construction method, and the soil pressure balance in the crossing process is guarante</description><language>chi ; eng</language><subject>BLASTING ; EARTH DRILLING ; FIXED CONSTRUCTIONS ; GALLERIES ; HEATING ; LARGE UNDERGROUND CHAMBERS ; LIGHTING ; MECHANICAL ENGINEERING ; MINING ; PIPE-LINE SYSTEMS ; PIPE-LINES ; SHAFTS ; STORING OF DISTRIBUTING GASES OR LIQUIDS ; TUNNELS ; WEAPONS</subject><creationdate>2021</creationdate><oa>free_for_read</oa><woscitedreferencessubscribed>false</woscitedreferencessubscribed></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><linktohtml>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&date=20210618&DB=EPODOC&CC=CN&NR=112983442A$$EHTML$$P50$$Gepo$$Hfree_for_read</linktohtml><link.rule.ids>230,308,780,885,25555,76308</link.rule.ids><linktorsrc>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&date=20210618&DB=EPODOC&CC=CN&NR=112983442A$$EView_record_in_European_Patent_Office$$FView_record_in_$$GEuropean_Patent_Office$$Hfree_for_read</linktorsrc></links><search><creatorcontrib>ZHANG JIALE</creatorcontrib><creatorcontrib>SUN YINGRUI</creatorcontrib><creatorcontrib>LI KAIJUN</creatorcontrib><creatorcontrib>QI YUSHEN</creatorcontrib><creatorcontrib>PENG BIWU</creatorcontrib><creatorcontrib>TAN CONGLONG</creatorcontrib><creatorcontrib>ZHAO ZERU</creatorcontrib><creatorcontrib>LIU BOTAO</creatorcontrib><creatorcontrib>FAN ZUNFENG</creatorcontrib><creatorcontrib>WANG FENG</creatorcontrib><creatorcontrib>BI HAORAN</creatorcontrib><title>Construction method for penetrating through gas pipeline with pressure downwards at ultra-close distance by using shield tunneling machine</title><description>The invention discloses a construction method for penetrating through a gas pipeline with pressure downwards at an ultra-close distance by using a shield tunneling machine, and relates to the technical field of shield tunneling machine construction methods. The construction method comprises the following steps of stopping the shield tunneling machine; accurately positioning the gas pipeline; performing three-dimensional modeling; adjusting the slope of the line, and calculating the nearest distance between the shield tunneling machine and the gas pipeline; replacing fuel gas; re-pushing the shield tunneling machine; grouting for the second time; and recovering the fuel gas. According to the construction method, nitrogen is adopted for replacing fuel gas for pressure maintaining, and the risk when the shield tunneling machine passes is reduced; the soil settlement at a shield body is guaranteed by adopting an anti-mud-effect construction method, and the soil pressure balance in the crossing process is guarante</description><subject>BLASTING</subject><subject>EARTH DRILLING</subject><subject>FIXED CONSTRUCTIONS</subject><subject>GALLERIES</subject><subject>HEATING</subject><subject>LARGE UNDERGROUND CHAMBERS</subject><subject>LIGHTING</subject><subject>MECHANICAL ENGINEERING</subject><subject>MINING</subject><subject>PIPE-LINE SYSTEMS</subject><subject>PIPE-LINES</subject><subject>SHAFTS</subject><subject>STORING OF DISTRIBUTING GASES OR LIQUIDS</subject><subject>TUNNELS</subject><subject>WEAPONS</subject><fulltext>true</fulltext><rsrctype>patent</rsrctype><creationdate>2021</creationdate><recordtype>patent</recordtype><sourceid>EVB</sourceid><recordid>eNqNjjsOwjAQRNNQIOAOywFS5FNAiSIQFRV9ZOxNbMlZW961Iq7AqUkkDkA1xcx7mm3x6QKxpKzFBYIJxQYDQ0gQkVCSEkcjiE0hjxZGxRBdRO8IYXZiISZkzgnBhJlmlQyDEsh-IUvtAy-FY1GkEV5vyLza2Dr0BiQTraYRJqXtYtwXm0F5xsMvd8Xxdn129xJj6JGj0uulvntUVX0-NW1bX5p_Nl9oRk5X</recordid><startdate>20210618</startdate><enddate>20210618</enddate><creator>ZHANG JIALE</creator><creator>SUN YINGRUI</creator><creator>LI KAIJUN</creator><creator>QI YUSHEN</creator><creator>PENG BIWU</creator><creator>TAN CONGLONG</creator><creator>ZHAO ZERU</creator><creator>LIU BOTAO</creator><creator>FAN ZUNFENG</creator><creator>WANG FENG</creator><creator>BI HAORAN</creator><scope>EVB</scope></search><sort><creationdate>20210618</creationdate><title>Construction method for penetrating through gas pipeline with pressure downwards at ultra-close distance by using shield tunneling machine</title><author>ZHANG JIALE ; SUN YINGRUI ; LI KAIJUN ; QI YUSHEN ; PENG BIWU ; TAN CONGLONG ; ZHAO ZERU ; LIU BOTAO ; FAN ZUNFENG ; WANG FENG ; BI HAORAN</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-epo_espacenet_CN112983442A3</frbrgroupid><rsrctype>patents</rsrctype><prefilter>patents</prefilter><language>chi ; eng</language><creationdate>2021</creationdate><topic>BLASTING</topic><topic>EARTH DRILLING</topic><topic>FIXED CONSTRUCTIONS</topic><topic>GALLERIES</topic><topic>HEATING</topic><topic>LARGE UNDERGROUND CHAMBERS</topic><topic>LIGHTING</topic><topic>MECHANICAL ENGINEERING</topic><topic>MINING</topic><topic>PIPE-LINE SYSTEMS</topic><topic>PIPE-LINES</topic><topic>SHAFTS</topic><topic>STORING OF DISTRIBUTING GASES OR LIQUIDS</topic><topic>TUNNELS</topic><topic>WEAPONS</topic><toplevel>online_resources</toplevel><creatorcontrib>ZHANG JIALE</creatorcontrib><creatorcontrib>SUN YINGRUI</creatorcontrib><creatorcontrib>LI KAIJUN</creatorcontrib><creatorcontrib>QI YUSHEN</creatorcontrib><creatorcontrib>PENG BIWU</creatorcontrib><creatorcontrib>TAN CONGLONG</creatorcontrib><creatorcontrib>ZHAO ZERU</creatorcontrib><creatorcontrib>LIU BOTAO</creatorcontrib><creatorcontrib>FAN ZUNFENG</creatorcontrib><creatorcontrib>WANG FENG</creatorcontrib><creatorcontrib>BI HAORAN</creatorcontrib><collection>esp@cenet</collection></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext_linktorsrc</fulltext></delivery><addata><au>ZHANG JIALE</au><au>SUN YINGRUI</au><au>LI KAIJUN</au><au>QI YUSHEN</au><au>PENG BIWU</au><au>TAN CONGLONG</au><au>ZHAO ZERU</au><au>LIU BOTAO</au><au>FAN ZUNFENG</au><au>WANG FENG</au><au>BI HAORAN</au><format>patent</format><genre>patent</genre><ristype>GEN</ristype><title>Construction method for penetrating through gas pipeline with pressure downwards at ultra-close distance by using shield tunneling machine</title><date>2021-06-18</date><risdate>2021</risdate><abstract>The invention discloses a construction method for penetrating through a gas pipeline with pressure downwards at an ultra-close distance by using a shield tunneling machine, and relates to the technical field of shield tunneling machine construction methods. The construction method comprises the following steps of stopping the shield tunneling machine; accurately positioning the gas pipeline; performing three-dimensional modeling; adjusting the slope of the line, and calculating the nearest distance between the shield tunneling machine and the gas pipeline; replacing fuel gas; re-pushing the shield tunneling machine; grouting for the second time; and recovering the fuel gas. According to the construction method, nitrogen is adopted for replacing fuel gas for pressure maintaining, and the risk when the shield tunneling machine passes is reduced; the soil settlement at a shield body is guaranteed by adopting an anti-mud-effect construction method, and the soil pressure balance in the crossing process is guarante</abstract><oa>free_for_read</oa></addata></record> |
fulltext | fulltext_linktorsrc |
identifier | |
ispartof | |
issn | |
language | chi ; eng |
recordid | cdi_epo_espacenet_CN112983442A |
source | esp@cenet |
subjects | BLASTING EARTH DRILLING FIXED CONSTRUCTIONS GALLERIES HEATING LARGE UNDERGROUND CHAMBERS LIGHTING MECHANICAL ENGINEERING MINING PIPE-LINE SYSTEMS PIPE-LINES SHAFTS STORING OF DISTRIBUTING GASES OR LIQUIDS TUNNELS WEAPONS |
title | Construction method for penetrating through gas pipeline with pressure downwards at ultra-close distance by using shield tunneling machine |
url | https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2025-01-15T03%3A58%3A08IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-epo_EVB&rft_val_fmt=info:ofi/fmt:kev:mtx:patent&rft.genre=patent&rft.au=ZHANG%20JIALE&rft.date=2021-06-18&rft_id=info:doi/&rft_dat=%3Cepo_EVB%3ECN112983442A%3C/epo_EVB%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_id=info:pmid/&rfr_iscdi=true |