Construction method of assembled girder crane foundation for high-speed railway box girder field

The invention discloses a construction method of an assembled girder crane foundation for a high-speed railway box girder field, and belongs to the technical field of high-speed railway box girder prefabrication. The method comprises the steps that firstly, waterproof protection construction is carr...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Hauptverfasser: LIU WEI, HOU YANMING, SHEN XUESONG, HU XIBIN, TIAN DAN, YANG YUHUA, LIANG QINGKAI, CHEN JIAN, ZHANG JIUJUN, ZHANG HAOLIANG, WANG ZHENGGUO, CHEN RANGLI, QIU WUMING
Format: Patent
Sprache:chi ; eng
Schlagworte:
Online-Zugang:Volltext bestellen
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
container_end_page
container_issue
container_start_page
container_title
container_volume
creator LIU WEI
HOU YANMING
SHEN XUESONG
HU XIBIN
TIAN DAN
YANG YUHUA
LIANG QINGKAI
CHEN JIAN
ZHANG JIUJUN
ZHANG HAOLIANG
WANG ZHENGGUO
CHEN RANGLI
QIU WUMING
description The invention discloses a construction method of an assembled girder crane foundation for a high-speed railway box girder field, and belongs to the technical field of high-speed railway box girder prefabrication. The method comprises the steps that firstly, waterproof protection construction is carried out on an existing roadbed, and then the assembled girder crane foundation is hoisted on the roadbed. The assembled girder crane foundation comprises a plurality of cuboid girder crane foundation single bodies, the plurality of girder crane foundation single bodies are spliced into a column, andthe front end faces and the rear end faces of every two adjacent girder crane foundation single bodies are fixedly connected through connecting steel plates and fixing bolts. The method is green andenvironment-friendly, the construction process is simple, universality is high, the popularization and practical value is high, girder crane foundation concrete components can be recycled, energy consumption is reduced, and th
format Patent
fullrecord <record><control><sourceid>epo_EVB</sourceid><recordid>TN_cdi_epo_espacenet_CN112095652A</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><sourcerecordid>CN112095652A</sourcerecordid><originalsourceid>FETCH-epo_espacenet_CN112095652A3</originalsourceid><addsrcrecordid>eNqNy7EKwjAQgOEsDqK-w_kABVup4ChBcXJyr9fk0gTSXEhS1LdXRHenf_n-ubhJDrmkSRXHAUYqljWwAcyZxt6ThsElTQlUwkBgeAoaP9ZwAusGW-VIb5bQ-Ts-oefHbzGOvF6KmUGfafXtQqxPx6s8VxS5oxxRUaDSyUtdN5t9u2ubw_Yf8wLvcT17</addsrcrecordid><sourcetype>Open Access Repository</sourcetype><iscdi>true</iscdi><recordtype>patent</recordtype></control><display><type>patent</type><title>Construction method of assembled girder crane foundation for high-speed railway box girder field</title><source>esp@cenet</source><creator>LIU WEI ; HOU YANMING ; SHEN XUESONG ; HU XIBIN ; TIAN DAN ; YANG YUHUA ; LIANG QINGKAI ; CHEN JIAN ; ZHANG JIUJUN ; ZHANG HAOLIANG ; WANG ZHENGGUO ; CHEN RANGLI ; QIU WUMING</creator><creatorcontrib>LIU WEI ; HOU YANMING ; SHEN XUESONG ; HU XIBIN ; TIAN DAN ; YANG YUHUA ; LIANG QINGKAI ; CHEN JIAN ; ZHANG JIUJUN ; ZHANG HAOLIANG ; WANG ZHENGGUO ; CHEN RANGLI ; QIU WUMING</creatorcontrib><description>The invention discloses a construction method of an assembled girder crane foundation for a high-speed railway box girder field, and belongs to the technical field of high-speed railway box girder prefabrication. The method comprises the steps that firstly, waterproof protection construction is carried out on an existing roadbed, and then the assembled girder crane foundation is hoisted on the roadbed. The assembled girder crane foundation comprises a plurality of cuboid girder crane foundation single bodies, the plurality of girder crane foundation single bodies are spliced into a column, andthe front end faces and the rear end faces of every two adjacent girder crane foundation single bodies are fixedly connected through connecting steel plates and fixing bolts. The method is green andenvironment-friendly, the construction process is simple, universality is high, the popularization and practical value is high, girder crane foundation concrete components can be recycled, energy consumption is reduced, and th</description><language>chi ; eng</language><subject>EMBANKMENTS ; EXCAVATIONS ; FIXED CONSTRUCTIONS ; FOUNDATIONS ; HYDRAULIC ENGINEERING ; SOIL SHIFTING ; UNDERGROUND OR UNDERWATER STRUCTURES</subject><creationdate>2020</creationdate><oa>free_for_read</oa><woscitedreferencessubscribed>false</woscitedreferencessubscribed></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><linktohtml>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20201218&amp;DB=EPODOC&amp;CC=CN&amp;NR=112095652A$$EHTML$$P50$$Gepo$$Hfree_for_read</linktohtml><link.rule.ids>230,308,776,881,25542,76290</link.rule.ids><linktorsrc>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20201218&amp;DB=EPODOC&amp;CC=CN&amp;NR=112095652A$$EView_record_in_European_Patent_Office$$FView_record_in_$$GEuropean_Patent_Office$$Hfree_for_read</linktorsrc></links><search><creatorcontrib>LIU WEI</creatorcontrib><creatorcontrib>HOU YANMING</creatorcontrib><creatorcontrib>SHEN XUESONG</creatorcontrib><creatorcontrib>HU XIBIN</creatorcontrib><creatorcontrib>TIAN DAN</creatorcontrib><creatorcontrib>YANG YUHUA</creatorcontrib><creatorcontrib>LIANG QINGKAI</creatorcontrib><creatorcontrib>CHEN JIAN</creatorcontrib><creatorcontrib>ZHANG JIUJUN</creatorcontrib><creatorcontrib>ZHANG HAOLIANG</creatorcontrib><creatorcontrib>WANG ZHENGGUO</creatorcontrib><creatorcontrib>CHEN RANGLI</creatorcontrib><creatorcontrib>QIU WUMING</creatorcontrib><title>Construction method of assembled girder crane foundation for high-speed railway box girder field</title><description>The invention discloses a construction method of an assembled girder crane foundation for a high-speed railway box girder field, and belongs to the technical field of high-speed railway box girder prefabrication. The method comprises the steps that firstly, waterproof protection construction is carried out on an existing roadbed, and then the assembled girder crane foundation is hoisted on the roadbed. The assembled girder crane foundation comprises a plurality of cuboid girder crane foundation single bodies, the plurality of girder crane foundation single bodies are spliced into a column, andthe front end faces and the rear end faces of every two adjacent girder crane foundation single bodies are fixedly connected through connecting steel plates and fixing bolts. The method is green andenvironment-friendly, the construction process is simple, universality is high, the popularization and practical value is high, girder crane foundation concrete components can be recycled, energy consumption is reduced, and th</description><subject>EMBANKMENTS</subject><subject>EXCAVATIONS</subject><subject>FIXED CONSTRUCTIONS</subject><subject>FOUNDATIONS</subject><subject>HYDRAULIC ENGINEERING</subject><subject>SOIL SHIFTING</subject><subject>UNDERGROUND OR UNDERWATER STRUCTURES</subject><fulltext>true</fulltext><rsrctype>patent</rsrctype><creationdate>2020</creationdate><recordtype>patent</recordtype><sourceid>EVB</sourceid><recordid>eNqNy7EKwjAQgOEsDqK-w_kABVup4ChBcXJyr9fk0gTSXEhS1LdXRHenf_n-ubhJDrmkSRXHAUYqljWwAcyZxt6ThsElTQlUwkBgeAoaP9ZwAusGW-VIb5bQ-Ts-oefHbzGOvF6KmUGfafXtQqxPx6s8VxS5oxxRUaDSyUtdN5t9u2ubw_Yf8wLvcT17</recordid><startdate>20201218</startdate><enddate>20201218</enddate><creator>LIU WEI</creator><creator>HOU YANMING</creator><creator>SHEN XUESONG</creator><creator>HU XIBIN</creator><creator>TIAN DAN</creator><creator>YANG YUHUA</creator><creator>LIANG QINGKAI</creator><creator>CHEN JIAN</creator><creator>ZHANG JIUJUN</creator><creator>ZHANG HAOLIANG</creator><creator>WANG ZHENGGUO</creator><creator>CHEN RANGLI</creator><creator>QIU WUMING</creator><scope>EVB</scope></search><sort><creationdate>20201218</creationdate><title>Construction method of assembled girder crane foundation for high-speed railway box girder field</title><author>LIU WEI ; HOU YANMING ; SHEN XUESONG ; HU XIBIN ; TIAN DAN ; YANG YUHUA ; LIANG QINGKAI ; CHEN JIAN ; ZHANG JIUJUN ; ZHANG HAOLIANG ; WANG ZHENGGUO ; CHEN RANGLI ; QIU WUMING</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-epo_espacenet_CN112095652A3</frbrgroupid><rsrctype>patents</rsrctype><prefilter>patents</prefilter><language>chi ; eng</language><creationdate>2020</creationdate><topic>EMBANKMENTS</topic><topic>EXCAVATIONS</topic><topic>FIXED CONSTRUCTIONS</topic><topic>FOUNDATIONS</topic><topic>HYDRAULIC ENGINEERING</topic><topic>SOIL SHIFTING</topic><topic>UNDERGROUND OR UNDERWATER STRUCTURES</topic><toplevel>online_resources</toplevel><creatorcontrib>LIU WEI</creatorcontrib><creatorcontrib>HOU YANMING</creatorcontrib><creatorcontrib>SHEN XUESONG</creatorcontrib><creatorcontrib>HU XIBIN</creatorcontrib><creatorcontrib>TIAN DAN</creatorcontrib><creatorcontrib>YANG YUHUA</creatorcontrib><creatorcontrib>LIANG QINGKAI</creatorcontrib><creatorcontrib>CHEN JIAN</creatorcontrib><creatorcontrib>ZHANG JIUJUN</creatorcontrib><creatorcontrib>ZHANG HAOLIANG</creatorcontrib><creatorcontrib>WANG ZHENGGUO</creatorcontrib><creatorcontrib>CHEN RANGLI</creatorcontrib><creatorcontrib>QIU WUMING</creatorcontrib><collection>esp@cenet</collection></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext_linktorsrc</fulltext></delivery><addata><au>LIU WEI</au><au>HOU YANMING</au><au>SHEN XUESONG</au><au>HU XIBIN</au><au>TIAN DAN</au><au>YANG YUHUA</au><au>LIANG QINGKAI</au><au>CHEN JIAN</au><au>ZHANG JIUJUN</au><au>ZHANG HAOLIANG</au><au>WANG ZHENGGUO</au><au>CHEN RANGLI</au><au>QIU WUMING</au><format>patent</format><genre>patent</genre><ristype>GEN</ristype><title>Construction method of assembled girder crane foundation for high-speed railway box girder field</title><date>2020-12-18</date><risdate>2020</risdate><abstract>The invention discloses a construction method of an assembled girder crane foundation for a high-speed railway box girder field, and belongs to the technical field of high-speed railway box girder prefabrication. The method comprises the steps that firstly, waterproof protection construction is carried out on an existing roadbed, and then the assembled girder crane foundation is hoisted on the roadbed. The assembled girder crane foundation comprises a plurality of cuboid girder crane foundation single bodies, the plurality of girder crane foundation single bodies are spliced into a column, andthe front end faces and the rear end faces of every two adjacent girder crane foundation single bodies are fixedly connected through connecting steel plates and fixing bolts. The method is green andenvironment-friendly, the construction process is simple, universality is high, the popularization and practical value is high, girder crane foundation concrete components can be recycled, energy consumption is reduced, and th</abstract><oa>free_for_read</oa></addata></record>
fulltext fulltext_linktorsrc
identifier
ispartof
issn
language chi ; eng
recordid cdi_epo_espacenet_CN112095652A
source esp@cenet
subjects EMBANKMENTS
EXCAVATIONS
FIXED CONSTRUCTIONS
FOUNDATIONS
HYDRAULIC ENGINEERING
SOIL SHIFTING
UNDERGROUND OR UNDERWATER STRUCTURES
title Construction method of assembled girder crane foundation for high-speed railway box girder field
url https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2025-02-03T05%3A13%3A57IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-epo_EVB&rft_val_fmt=info:ofi/fmt:kev:mtx:patent&rft.genre=patent&rft.au=LIU%20WEI&rft.date=2020-12-18&rft_id=info:doi/&rft_dat=%3Cepo_EVB%3ECN112095652A%3C/epo_EVB%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_id=info:pmid/&rfr_iscdi=true