The embodiment of the invention discloses a tunnel undercrossing construction process, and relates to the technical field of tunnel construction. The tunnel undercrossing construction process comprises the steps of S1, performing advanced support, wherein a pipe shed is combined with an advanced sma...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Hauptverfasser: HUANG HAISHAN, ZHANG XIAOKUN, GUAN DAYUAN, YU QIAN, WANG XIFENG, YANG YONGXIANG, SHAN GUOQIANG, DONG ZILONG, LI YOUKUN, PENG JINTAO, ZHANG YONGHU, DENG CHUAN, GAO QI, WANG GUOKU, XUE CHAO, QIN ZHENGYANG
Format: Patent
Sprache:chi ; eng
Schlagworte:
Online-Zugang:Volltext bestellen
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
container_end_page
container_issue
container_start_page
container_title
container_volume
creator HUANG HAISHAN
ZHANG XIAOKUN
GUAN DAYUAN
YU QIAN
WANG XIFENG
YANG YONGXIANG
SHAN GUOQIANG
DONG ZILONG
LI YOUKUN
PENG JINTAO
ZHANG YONGHU
DENG CHUAN
GAO QI
WANG GUOKU
XUE CHAO
QIN ZHENGYANG
description The embodiment of the invention discloses a tunnel undercrossing construction process, and relates to the technical field of tunnel construction. The tunnel undercrossing construction process comprises the steps of S1, performing advanced support, wherein a pipe shed is combined with an advanced small guide pipe to form the advanced support, and adjacent end parts of pipe sheds of two adjacent segments of advanced support are coincided in a radial direction of the tunnel to achieve mutual overlap joint; S2, performing advanced curtain grouting, grounding a surrounding part of the advanced support in the step S1 in advance before tunnel face excavation, and reinforcing a surrounding rock; S3, performing tunnel excavation; S4, performing tunnel support and water-proof and drainage construction; and S5, performing lining construction. Dual layers of advanced pipe sheds are combined with the advanced small guide pipe to form the advanced support, the advanced support is combined with all-fracture advanced curtain
format Patent
fullrecord <record><control><sourceid>epo_EVB</sourceid><recordid>TN_cdi_epo_espacenet_CN110374607A</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><sourcerecordid>CN110374607A</sourcerecordid><originalsourceid>FETCH-epo_espacenet_CN110374607A3</originalsourceid><addsrcrecordid>eNrjZNAMKc3LS81RKM1LSS1KLsovLs7MS1dIzs8rLikqTS7JzM9TKCjKT04tLuZhYE1LzClO5YXS3AyKbq4hzh66qQX58anFBYnJqXmpJfHOfoaGBsbmJmYG5o7GxKgBAGLrKZA</addsrcrecordid><sourcetype>Open Access Repository</sourcetype><iscdi>true</iscdi><recordtype>patent</recordtype></control><display><type>patent</type><title>Tunnel undercrossing construction process</title><source>esp@cenet</source><creator>HUANG HAISHAN ; ZHANG XIAOKUN ; GUAN DAYUAN ; YU QIAN ; WANG XIFENG ; YANG YONGXIANG ; SHAN GUOQIANG ; DONG ZILONG ; LI YOUKUN ; PENG JINTAO ; ZHANG YONGHU ; DENG CHUAN ; GAO QI ; WANG GUOKU ; XUE CHAO ; QIN ZHENGYANG</creator><creatorcontrib>HUANG HAISHAN ; ZHANG XIAOKUN ; GUAN DAYUAN ; YU QIAN ; WANG XIFENG ; YANG YONGXIANG ; SHAN GUOQIANG ; DONG ZILONG ; LI YOUKUN ; PENG JINTAO ; ZHANG YONGHU ; DENG CHUAN ; GAO QI ; WANG GUOKU ; XUE CHAO ; QIN ZHENGYANG</creatorcontrib><description>The embodiment of the invention discloses a tunnel undercrossing construction process, and relates to the technical field of tunnel construction. The tunnel undercrossing construction process comprises the steps of S1, performing advanced support, wherein a pipe shed is combined with an advanced small guide pipe to form the advanced support, and adjacent end parts of pipe sheds of two adjacent segments of advanced support are coincided in a radial direction of the tunnel to achieve mutual overlap joint; S2, performing advanced curtain grouting, grounding a surrounding part of the advanced support in the step S1 in advance before tunnel face excavation, and reinforcing a surrounding rock; S3, performing tunnel excavation; S4, performing tunnel support and water-proof and drainage construction; and S5, performing lining construction. Dual layers of advanced pipe sheds are combined with the advanced small guide pipe to form the advanced support, the advanced support is combined with all-fracture advanced curtain</description><language>chi ; eng</language><subject>EARTH DRILLING ; FIXED CONSTRUCTIONS ; GALLERIES ; LARGE UNDERGROUND CHAMBERS ; MINING ; SHAFTS ; TUNNELS</subject><creationdate>2019</creationdate><oa>free_for_read</oa><woscitedreferencessubscribed>false</woscitedreferencessubscribed></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><linktohtml>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20191025&amp;DB=EPODOC&amp;CC=CN&amp;NR=110374607A$$EHTML$$P50$$Gepo$$Hfree_for_read</linktohtml><link.rule.ids>230,308,780,885,25564,76547</link.rule.ids><linktorsrc>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20191025&amp;DB=EPODOC&amp;CC=CN&amp;NR=110374607A$$EView_record_in_European_Patent_Office$$FView_record_in_$$GEuropean_Patent_Office$$Hfree_for_read</linktorsrc></links><search><creatorcontrib>HUANG HAISHAN</creatorcontrib><creatorcontrib>ZHANG XIAOKUN</creatorcontrib><creatorcontrib>GUAN DAYUAN</creatorcontrib><creatorcontrib>YU QIAN</creatorcontrib><creatorcontrib>WANG XIFENG</creatorcontrib><creatorcontrib>YANG YONGXIANG</creatorcontrib><creatorcontrib>SHAN GUOQIANG</creatorcontrib><creatorcontrib>DONG ZILONG</creatorcontrib><creatorcontrib>LI YOUKUN</creatorcontrib><creatorcontrib>PENG JINTAO</creatorcontrib><creatorcontrib>ZHANG YONGHU</creatorcontrib><creatorcontrib>DENG CHUAN</creatorcontrib><creatorcontrib>GAO QI</creatorcontrib><creatorcontrib>WANG GUOKU</creatorcontrib><creatorcontrib>XUE CHAO</creatorcontrib><creatorcontrib>QIN ZHENGYANG</creatorcontrib><title>Tunnel undercrossing construction process</title><description>The embodiment of the invention discloses a tunnel undercrossing construction process, and relates to the technical field of tunnel construction. The tunnel undercrossing construction process comprises the steps of S1, performing advanced support, wherein a pipe shed is combined with an advanced small guide pipe to form the advanced support, and adjacent end parts of pipe sheds of two adjacent segments of advanced support are coincided in a radial direction of the tunnel to achieve mutual overlap joint; S2, performing advanced curtain grouting, grounding a surrounding part of the advanced support in the step S1 in advance before tunnel face excavation, and reinforcing a surrounding rock; S3, performing tunnel excavation; S4, performing tunnel support and water-proof and drainage construction; and S5, performing lining construction. Dual layers of advanced pipe sheds are combined with the advanced small guide pipe to form the advanced support, the advanced support is combined with all-fracture advanced curtain</description><subject>EARTH DRILLING</subject><subject>FIXED CONSTRUCTIONS</subject><subject>GALLERIES</subject><subject>LARGE UNDERGROUND CHAMBERS</subject><subject>MINING</subject><subject>SHAFTS</subject><subject>TUNNELS</subject><fulltext>true</fulltext><rsrctype>patent</rsrctype><creationdate>2019</creationdate><recordtype>patent</recordtype><sourceid>EVB</sourceid><recordid>eNrjZNAMKc3LS81RKM1LSS1KLsovLs7MS1dIzs8rLikqTS7JzM9TKCjKT04tLuZhYE1LzClO5YXS3AyKbq4hzh66qQX58anFBYnJqXmpJfHOfoaGBsbmJmYG5o7GxKgBAGLrKZA</recordid><startdate>20191025</startdate><enddate>20191025</enddate><creator>HUANG HAISHAN</creator><creator>ZHANG XIAOKUN</creator><creator>GUAN DAYUAN</creator><creator>YU QIAN</creator><creator>WANG XIFENG</creator><creator>YANG YONGXIANG</creator><creator>SHAN GUOQIANG</creator><creator>DONG ZILONG</creator><creator>LI YOUKUN</creator><creator>PENG JINTAO</creator><creator>ZHANG YONGHU</creator><creator>DENG CHUAN</creator><creator>GAO QI</creator><creator>WANG GUOKU</creator><creator>XUE CHAO</creator><creator>QIN ZHENGYANG</creator><scope>EVB</scope></search><sort><creationdate>20191025</creationdate><title>Tunnel undercrossing construction process</title><author>HUANG HAISHAN ; ZHANG XIAOKUN ; GUAN DAYUAN ; YU QIAN ; WANG XIFENG ; YANG YONGXIANG ; SHAN GUOQIANG ; DONG ZILONG ; LI YOUKUN ; PENG JINTAO ; ZHANG YONGHU ; DENG CHUAN ; GAO QI ; WANG GUOKU ; XUE CHAO ; QIN ZHENGYANG</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-epo_espacenet_CN110374607A3</frbrgroupid><rsrctype>patents</rsrctype><prefilter>patents</prefilter><language>chi ; eng</language><creationdate>2019</creationdate><topic>EARTH DRILLING</topic><topic>FIXED CONSTRUCTIONS</topic><topic>GALLERIES</topic><topic>LARGE UNDERGROUND CHAMBERS</topic><topic>MINING</topic><topic>SHAFTS</topic><topic>TUNNELS</topic><toplevel>online_resources</toplevel><creatorcontrib>HUANG HAISHAN</creatorcontrib><creatorcontrib>ZHANG XIAOKUN</creatorcontrib><creatorcontrib>GUAN DAYUAN</creatorcontrib><creatorcontrib>YU QIAN</creatorcontrib><creatorcontrib>WANG XIFENG</creatorcontrib><creatorcontrib>YANG YONGXIANG</creatorcontrib><creatorcontrib>SHAN GUOQIANG</creatorcontrib><creatorcontrib>DONG ZILONG</creatorcontrib><creatorcontrib>LI YOUKUN</creatorcontrib><creatorcontrib>PENG JINTAO</creatorcontrib><creatorcontrib>ZHANG YONGHU</creatorcontrib><creatorcontrib>DENG CHUAN</creatorcontrib><creatorcontrib>GAO QI</creatorcontrib><creatorcontrib>WANG GUOKU</creatorcontrib><creatorcontrib>XUE CHAO</creatorcontrib><creatorcontrib>QIN ZHENGYANG</creatorcontrib><collection>esp@cenet</collection></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext_linktorsrc</fulltext></delivery><addata><au>HUANG HAISHAN</au><au>ZHANG XIAOKUN</au><au>GUAN DAYUAN</au><au>YU QIAN</au><au>WANG XIFENG</au><au>YANG YONGXIANG</au><au>SHAN GUOQIANG</au><au>DONG ZILONG</au><au>LI YOUKUN</au><au>PENG JINTAO</au><au>ZHANG YONGHU</au><au>DENG CHUAN</au><au>GAO QI</au><au>WANG GUOKU</au><au>XUE CHAO</au><au>QIN ZHENGYANG</au><format>patent</format><genre>patent</genre><ristype>GEN</ristype><title>Tunnel undercrossing construction process</title><date>2019-10-25</date><risdate>2019</risdate><abstract>The embodiment of the invention discloses a tunnel undercrossing construction process, and relates to the technical field of tunnel construction. The tunnel undercrossing construction process comprises the steps of S1, performing advanced support, wherein a pipe shed is combined with an advanced small guide pipe to form the advanced support, and adjacent end parts of pipe sheds of two adjacent segments of advanced support are coincided in a radial direction of the tunnel to achieve mutual overlap joint; S2, performing advanced curtain grouting, grounding a surrounding part of the advanced support in the step S1 in advance before tunnel face excavation, and reinforcing a surrounding rock; S3, performing tunnel excavation; S4, performing tunnel support and water-proof and drainage construction; and S5, performing lining construction. Dual layers of advanced pipe sheds are combined with the advanced small guide pipe to form the advanced support, the advanced support is combined with all-fracture advanced curtain</abstract><oa>free_for_read</oa></addata></record>
fulltext fulltext_linktorsrc
identifier
ispartof
issn
language chi ; eng
recordid cdi_epo_espacenet_CN110374607A
source esp@cenet
subjects EARTH DRILLING
FIXED CONSTRUCTIONS
GALLERIES
LARGE UNDERGROUND CHAMBERS
MINING
SHAFTS
TUNNELS
title Tunnel undercrossing construction process
url https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2025-01-01T01%3A49%3A03IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-epo_EVB&rft_val_fmt=info:ofi/fmt:kev:mtx:patent&rft.genre=patent&rft.au=HUANG%20HAISHAN&rft.date=2019-10-25&rft_id=info:doi/&rft_dat=%3Cepo_EVB%3ECN110374607A%3C/epo_EVB%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_id=info:pmid/&rfr_iscdi=true