Advance support construction method for high-strength pipe shed of tunnel

The invention discloses an advance support construction method for a high-strength pipe shed of a tunnel. A process for carrying out advance support construction on a pipe shed of one segment of a constructed tunnel comprises the following steps: (1) constructing support arches and guide pipes; (2)...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Hauptverfasser: QI FENGJUN, WANG ZHIJUN, TAN DEQING, FENG JUNWU, WU XIANRONG, LUO ZONGFAN, ZHANG QING
Format: Patent
Sprache:eng
Schlagworte:
Online-Zugang:Volltext bestellen
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
container_end_page
container_issue
container_start_page
container_title
container_volume
creator QI FENGJUN
WANG ZHIJUN
TAN DEQING
FENG JUNWU
WU XIANRONG
LUO ZONGFAN
ZHANG QING
description The invention discloses an advance support construction method for a high-strength pipe shed of a tunnel. A process for carrying out advance support construction on a pipe shed of one segment of a constructed tunnel comprises the following steps: (1) constructing support arches and guide pipes; (2) installing a drilling machine and a grouting machine in place; (3) carrying out advance support construction on the pipe shed: (301) preparing before drilling; (302) drilling pipe joints at front ends and synchronously grouting; (303) connecting the pipe joints; (304) continuously drilling and synchronously grouting; (305) repeating the steps (303) and (304) many times until the drilling processes of pipes of the current constructed pipe shed are finished; (306) blocking drill holes; (307) carrying out grouting construction on final holes; (308) repeating the steps (301) to (307) many times until all advance support construction processes of the pipes of the pipe shed are finished; and (4) carrying out excavation construction on the tunnel. The method disclosed by the invention is simple in step, reasonable in design, simple and convenient in construction and good in support effect; and by adopting automatic drilling type high-strength pipes of the pipe shed, the advance support process of the tunnel can be simply, conveniently and quickly finished.
format Patent
fullrecord <record><control><sourceid>epo_EVB</sourceid><recordid>TN_cdi_epo_espacenet_CN105201517A</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><sourcerecordid>CN105201517A</sourcerecordid><originalsourceid>FETCH-epo_espacenet_CN105201517A3</originalsourceid><addsrcrecordid>eNqNizEOwjAMALswIOAP5gGVGlDFXFUgWJjYqyhxmkjFthKH99OBBzDdcHfb5jH4jyWHUKoIZwXHVDRXp4kJ3qiRPQTOENMc29UgzRpBkqxLRA8cQCsRLvtmE-xS8PDjrjnerq_x3qLwhEWsQ0Kdxqfp-lNnenMZzv80XxqiNPc</addsrcrecordid><sourcetype>Open Access Repository</sourcetype><iscdi>true</iscdi><recordtype>patent</recordtype></control><display><type>patent</type><title>Advance support construction method for high-strength pipe shed of tunnel</title><source>esp@cenet</source><creator>QI FENGJUN ; WANG ZHIJUN ; TAN DEQING ; FENG JUNWU ; WU XIANRONG ; LUO ZONGFAN ; ZHANG QING</creator><creatorcontrib>QI FENGJUN ; WANG ZHIJUN ; TAN DEQING ; FENG JUNWU ; WU XIANRONG ; LUO ZONGFAN ; ZHANG QING</creatorcontrib><description>The invention discloses an advance support construction method for a high-strength pipe shed of a tunnel. A process for carrying out advance support construction on a pipe shed of one segment of a constructed tunnel comprises the following steps: (1) constructing support arches and guide pipes; (2) installing a drilling machine and a grouting machine in place; (3) carrying out advance support construction on the pipe shed: (301) preparing before drilling; (302) drilling pipe joints at front ends and synchronously grouting; (303) connecting the pipe joints; (304) continuously drilling and synchronously grouting; (305) repeating the steps (303) and (304) many times until the drilling processes of pipes of the current constructed pipe shed are finished; (306) blocking drill holes; (307) carrying out grouting construction on final holes; (308) repeating the steps (301) to (307) many times until all advance support construction processes of the pipes of the pipe shed are finished; and (4) carrying out excavation construction on the tunnel. The method disclosed by the invention is simple in step, reasonable in design, simple and convenient in construction and good in support effect; and by adopting automatic drilling type high-strength pipes of the pipe shed, the advance support process of the tunnel can be simply, conveniently and quickly finished.</description><language>eng</language><subject>EARTH DRILLING ; FIXED CONSTRUCTIONS ; GALLERIES ; LARGE UNDERGROUND CHAMBERS ; MINING ; SHAFTS ; TUNNELS</subject><creationdate>2015</creationdate><oa>free_for_read</oa><woscitedreferencessubscribed>false</woscitedreferencessubscribed></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><linktohtml>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20151230&amp;DB=EPODOC&amp;CC=CN&amp;NR=105201517A$$EHTML$$P50$$Gepo$$Hfree_for_read</linktohtml><link.rule.ids>230,308,780,885,25564,76547</link.rule.ids><linktorsrc>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20151230&amp;DB=EPODOC&amp;CC=CN&amp;NR=105201517A$$EView_record_in_European_Patent_Office$$FView_record_in_$$GEuropean_Patent_Office$$Hfree_for_read</linktorsrc></links><search><creatorcontrib>QI FENGJUN</creatorcontrib><creatorcontrib>WANG ZHIJUN</creatorcontrib><creatorcontrib>TAN DEQING</creatorcontrib><creatorcontrib>FENG JUNWU</creatorcontrib><creatorcontrib>WU XIANRONG</creatorcontrib><creatorcontrib>LUO ZONGFAN</creatorcontrib><creatorcontrib>ZHANG QING</creatorcontrib><title>Advance support construction method for high-strength pipe shed of tunnel</title><description>The invention discloses an advance support construction method for a high-strength pipe shed of a tunnel. A process for carrying out advance support construction on a pipe shed of one segment of a constructed tunnel comprises the following steps: (1) constructing support arches and guide pipes; (2) installing a drilling machine and a grouting machine in place; (3) carrying out advance support construction on the pipe shed: (301) preparing before drilling; (302) drilling pipe joints at front ends and synchronously grouting; (303) connecting the pipe joints; (304) continuously drilling and synchronously grouting; (305) repeating the steps (303) and (304) many times until the drilling processes of pipes of the current constructed pipe shed are finished; (306) blocking drill holes; (307) carrying out grouting construction on final holes; (308) repeating the steps (301) to (307) many times until all advance support construction processes of the pipes of the pipe shed are finished; and (4) carrying out excavation construction on the tunnel. The method disclosed by the invention is simple in step, reasonable in design, simple and convenient in construction and good in support effect; and by adopting automatic drilling type high-strength pipes of the pipe shed, the advance support process of the tunnel can be simply, conveniently and quickly finished.</description><subject>EARTH DRILLING</subject><subject>FIXED CONSTRUCTIONS</subject><subject>GALLERIES</subject><subject>LARGE UNDERGROUND CHAMBERS</subject><subject>MINING</subject><subject>SHAFTS</subject><subject>TUNNELS</subject><fulltext>true</fulltext><rsrctype>patent</rsrctype><creationdate>2015</creationdate><recordtype>patent</recordtype><sourceid>EVB</sourceid><recordid>eNqNizEOwjAMALswIOAP5gGVGlDFXFUgWJjYqyhxmkjFthKH99OBBzDdcHfb5jH4jyWHUKoIZwXHVDRXp4kJ3qiRPQTOENMc29UgzRpBkqxLRA8cQCsRLvtmE-xS8PDjrjnerq_x3qLwhEWsQ0Kdxqfp-lNnenMZzv80XxqiNPc</recordid><startdate>20151230</startdate><enddate>20151230</enddate><creator>QI FENGJUN</creator><creator>WANG ZHIJUN</creator><creator>TAN DEQING</creator><creator>FENG JUNWU</creator><creator>WU XIANRONG</creator><creator>LUO ZONGFAN</creator><creator>ZHANG QING</creator><scope>EVB</scope></search><sort><creationdate>20151230</creationdate><title>Advance support construction method for high-strength pipe shed of tunnel</title><author>QI FENGJUN ; WANG ZHIJUN ; TAN DEQING ; FENG JUNWU ; WU XIANRONG ; LUO ZONGFAN ; ZHANG QING</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-epo_espacenet_CN105201517A3</frbrgroupid><rsrctype>patents</rsrctype><prefilter>patents</prefilter><language>eng</language><creationdate>2015</creationdate><topic>EARTH DRILLING</topic><topic>FIXED CONSTRUCTIONS</topic><topic>GALLERIES</topic><topic>LARGE UNDERGROUND CHAMBERS</topic><topic>MINING</topic><topic>SHAFTS</topic><topic>TUNNELS</topic><toplevel>online_resources</toplevel><creatorcontrib>QI FENGJUN</creatorcontrib><creatorcontrib>WANG ZHIJUN</creatorcontrib><creatorcontrib>TAN DEQING</creatorcontrib><creatorcontrib>FENG JUNWU</creatorcontrib><creatorcontrib>WU XIANRONG</creatorcontrib><creatorcontrib>LUO ZONGFAN</creatorcontrib><creatorcontrib>ZHANG QING</creatorcontrib><collection>esp@cenet</collection></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext_linktorsrc</fulltext></delivery><addata><au>QI FENGJUN</au><au>WANG ZHIJUN</au><au>TAN DEQING</au><au>FENG JUNWU</au><au>WU XIANRONG</au><au>LUO ZONGFAN</au><au>ZHANG QING</au><format>patent</format><genre>patent</genre><ristype>GEN</ristype><title>Advance support construction method for high-strength pipe shed of tunnel</title><date>2015-12-30</date><risdate>2015</risdate><abstract>The invention discloses an advance support construction method for a high-strength pipe shed of a tunnel. A process for carrying out advance support construction on a pipe shed of one segment of a constructed tunnel comprises the following steps: (1) constructing support arches and guide pipes; (2) installing a drilling machine and a grouting machine in place; (3) carrying out advance support construction on the pipe shed: (301) preparing before drilling; (302) drilling pipe joints at front ends and synchronously grouting; (303) connecting the pipe joints; (304) continuously drilling and synchronously grouting; (305) repeating the steps (303) and (304) many times until the drilling processes of pipes of the current constructed pipe shed are finished; (306) blocking drill holes; (307) carrying out grouting construction on final holes; (308) repeating the steps (301) to (307) many times until all advance support construction processes of the pipes of the pipe shed are finished; and (4) carrying out excavation construction on the tunnel. The method disclosed by the invention is simple in step, reasonable in design, simple and convenient in construction and good in support effect; and by adopting automatic drilling type high-strength pipes of the pipe shed, the advance support process of the tunnel can be simply, conveniently and quickly finished.</abstract><oa>free_for_read</oa></addata></record>
fulltext fulltext_linktorsrc
identifier
ispartof
issn
language eng
recordid cdi_epo_espacenet_CN105201517A
source esp@cenet
subjects EARTH DRILLING
FIXED CONSTRUCTIONS
GALLERIES
LARGE UNDERGROUND CHAMBERS
MINING
SHAFTS
TUNNELS
title Advance support construction method for high-strength pipe shed of tunnel
url https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2024-12-20T08%3A26%3A14IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-epo_EVB&rft_val_fmt=info:ofi/fmt:kev:mtx:patent&rft.genre=patent&rft.au=QI%20FENGJUN&rft.date=2015-12-30&rft_id=info:doi/&rft_dat=%3Cepo_EVB%3ECN105201517A%3C/epo_EVB%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_id=info:pmid/&rfr_iscdi=true