Double-slurry closing construction method for sump

The invention relates to a double-slurry closing construction method for a sump. The double-slurry closing construction method for the sump comprises the following steps that (1) a drilling machine platform is laid around the grouting position; (2) slurry is prepared, first slurry is composed of liq...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Hauptverfasser: SHI JIANLU, LI SHANGMING, HU MINGWEN, WU JUN, GUO FENG, YANG GANG, FENG TIEJI, TIAN YUJIANG, LU JIAN, LIU GUOSHENG, XU YONG
Format: Patent
Sprache:eng
Schlagworte:
Online-Zugang:Volltext bestellen
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
container_end_page
container_issue
container_start_page
container_title
container_volume
creator SHI JIANLU
LI SHANGMING
HU MINGWEN
WU JUN
GUO FENG
YANG GANG
FENG TIEJI
TIAN YUJIANG
LU JIAN
LIU GUOSHENG
XU YONG
description The invention relates to a double-slurry closing construction method for a sump. The double-slurry closing construction method for the sump comprises the following steps that (1) a drilling machine platform is laid around the grouting position; (2) slurry is prepared, first slurry is composed of liquid A, liquid B and a first additive at the mass ratio of 1: 1: 0.13, and second slurry is composed of liquid A , liquid C and a second additive at the mass ratio of 1: 1: 0.17; (3) grouting holes are distributed; (4) a rotary drilling bit penetrates through the stratum by the designed hole depth of 4.5 m, then the first slurry is injected into the hole in a retreating mode, the grouting pressure is controlled to range from 0.5 Mpa to 1.0 Mpa, a drill rod retreats by one meter, the second slurry continues to be injected, the grouting pressure is controlled to range from 1.1 Mpa to 1.4 Mpa, the drill rod continues to retreat, and the steps are repeated in sequence; when only one meter of the drill rod is left through retreating, the first slurry is injected and then the next hole is grouted after completion of grouting; and (5) after the sump is dug in a grouted foundation, and the wall face of the sump is coated with waterproof paint. By the adoption of the double-slurry closing construction method for the sump, construction is rapid and convenient, the closing effect is good, and the method is suitable for the technical field of constructional engineering.
format Patent
fullrecord <record><control><sourceid>epo_EVB</sourceid><recordid>TN_cdi_epo_espacenet_CN105155541A</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><sourcerecordid>CN105155541A</sourcerecordid><originalsourceid>FETCH-epo_espacenet_CN105155541A3</originalsourceid><addsrcrecordid>eNrjZDByyS9NyknVLc4pLSqqVEjOyS_OzEtXSM7PKy4pKk0uyczPU8hNLcnIT1FIyy9SKC7NLeBhYE1LzClO5YXS3AyKbq4hzh66qQX58anFBYnJqXmpJfHOfoYGpoampqYmho7GxKgBAAk2LI8</addsrcrecordid><sourcetype>Open Access Repository</sourcetype><iscdi>true</iscdi><recordtype>patent</recordtype></control><display><type>patent</type><title>Double-slurry closing construction method for sump</title><source>esp@cenet</source><creator>SHI JIANLU ; LI SHANGMING ; HU MINGWEN ; WU JUN ; GUO FENG ; YANG GANG ; FENG TIEJI ; TIAN YUJIANG ; LU JIAN ; LIU GUOSHENG ; XU YONG</creator><creatorcontrib>SHI JIANLU ; LI SHANGMING ; HU MINGWEN ; WU JUN ; GUO FENG ; YANG GANG ; FENG TIEJI ; TIAN YUJIANG ; LU JIAN ; LIU GUOSHENG ; XU YONG</creatorcontrib><description>The invention relates to a double-slurry closing construction method for a sump. The double-slurry closing construction method for the sump comprises the following steps that (1) a drilling machine platform is laid around the grouting position; (2) slurry is prepared, first slurry is composed of liquid A, liquid B and a first additive at the mass ratio of 1: 1: 0.13, and second slurry is composed of liquid A , liquid C and a second additive at the mass ratio of 1: 1: 0.17; (3) grouting holes are distributed; (4) a rotary drilling bit penetrates through the stratum by the designed hole depth of 4.5 m, then the first slurry is injected into the hole in a retreating mode, the grouting pressure is controlled to range from 0.5 Mpa to 1.0 Mpa, a drill rod retreats by one meter, the second slurry continues to be injected, the grouting pressure is controlled to range from 1.1 Mpa to 1.4 Mpa, the drill rod continues to retreat, and the steps are repeated in sequence; when only one meter of the drill rod is left through retreating, the first slurry is injected and then the next hole is grouted after completion of grouting; and (5) after the sump is dug in a grouted foundation, and the wall face of the sump is coated with waterproof paint. By the adoption of the double-slurry closing construction method for the sump, construction is rapid and convenient, the closing effect is good, and the method is suitable for the technical field of constructional engineering.</description><language>eng</language><subject>EMBANKMENTS ; EXCAVATIONS ; FIXED CONSTRUCTIONS ; FOUNDATIONS ; HYDRAULIC ENGINEERING ; SOIL SHIFTING ; UNDERGROUND OR UNDERWATER STRUCTURES</subject><creationdate>2015</creationdate><oa>free_for_read</oa><woscitedreferencessubscribed>false</woscitedreferencessubscribed></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><linktohtml>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20151216&amp;DB=EPODOC&amp;CC=CN&amp;NR=105155541A$$EHTML$$P50$$Gepo$$Hfree_for_read</linktohtml><link.rule.ids>230,308,780,885,25564,76419</link.rule.ids><linktorsrc>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20151216&amp;DB=EPODOC&amp;CC=CN&amp;NR=105155541A$$EView_record_in_European_Patent_Office$$FView_record_in_$$GEuropean_Patent_Office$$Hfree_for_read</linktorsrc></links><search><creatorcontrib>SHI JIANLU</creatorcontrib><creatorcontrib>LI SHANGMING</creatorcontrib><creatorcontrib>HU MINGWEN</creatorcontrib><creatorcontrib>WU JUN</creatorcontrib><creatorcontrib>GUO FENG</creatorcontrib><creatorcontrib>YANG GANG</creatorcontrib><creatorcontrib>FENG TIEJI</creatorcontrib><creatorcontrib>TIAN YUJIANG</creatorcontrib><creatorcontrib>LU JIAN</creatorcontrib><creatorcontrib>LIU GUOSHENG</creatorcontrib><creatorcontrib>XU YONG</creatorcontrib><title>Double-slurry closing construction method for sump</title><description>The invention relates to a double-slurry closing construction method for a sump. The double-slurry closing construction method for the sump comprises the following steps that (1) a drilling machine platform is laid around the grouting position; (2) slurry is prepared, first slurry is composed of liquid A, liquid B and a first additive at the mass ratio of 1: 1: 0.13, and second slurry is composed of liquid A , liquid C and a second additive at the mass ratio of 1: 1: 0.17; (3) grouting holes are distributed; (4) a rotary drilling bit penetrates through the stratum by the designed hole depth of 4.5 m, then the first slurry is injected into the hole in a retreating mode, the grouting pressure is controlled to range from 0.5 Mpa to 1.0 Mpa, a drill rod retreats by one meter, the second slurry continues to be injected, the grouting pressure is controlled to range from 1.1 Mpa to 1.4 Mpa, the drill rod continues to retreat, and the steps are repeated in sequence; when only one meter of the drill rod is left through retreating, the first slurry is injected and then the next hole is grouted after completion of grouting; and (5) after the sump is dug in a grouted foundation, and the wall face of the sump is coated with waterproof paint. By the adoption of the double-slurry closing construction method for the sump, construction is rapid and convenient, the closing effect is good, and the method is suitable for the technical field of constructional engineering.</description><subject>EMBANKMENTS</subject><subject>EXCAVATIONS</subject><subject>FIXED CONSTRUCTIONS</subject><subject>FOUNDATIONS</subject><subject>HYDRAULIC ENGINEERING</subject><subject>SOIL SHIFTING</subject><subject>UNDERGROUND OR UNDERWATER STRUCTURES</subject><fulltext>true</fulltext><rsrctype>patent</rsrctype><creationdate>2015</creationdate><recordtype>patent</recordtype><sourceid>EVB</sourceid><recordid>eNrjZDByyS9NyknVLc4pLSqqVEjOyS_OzEtXSM7PKy4pKk0uyczPU8hNLcnIT1FIyy9SKC7NLeBhYE1LzClO5YXS3AyKbq4hzh66qQX58anFBYnJqXmpJfHOfoYGpoampqYmho7GxKgBAAk2LI8</recordid><startdate>20151216</startdate><enddate>20151216</enddate><creator>SHI JIANLU</creator><creator>LI SHANGMING</creator><creator>HU MINGWEN</creator><creator>WU JUN</creator><creator>GUO FENG</creator><creator>YANG GANG</creator><creator>FENG TIEJI</creator><creator>TIAN YUJIANG</creator><creator>LU JIAN</creator><creator>LIU GUOSHENG</creator><creator>XU YONG</creator><scope>EVB</scope></search><sort><creationdate>20151216</creationdate><title>Double-slurry closing construction method for sump</title><author>SHI JIANLU ; LI SHANGMING ; HU MINGWEN ; WU JUN ; GUO FENG ; YANG GANG ; FENG TIEJI ; TIAN YUJIANG ; LU JIAN ; LIU GUOSHENG ; XU YONG</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-epo_espacenet_CN105155541A3</frbrgroupid><rsrctype>patents</rsrctype><prefilter>patents</prefilter><language>eng</language><creationdate>2015</creationdate><topic>EMBANKMENTS</topic><topic>EXCAVATIONS</topic><topic>FIXED CONSTRUCTIONS</topic><topic>FOUNDATIONS</topic><topic>HYDRAULIC ENGINEERING</topic><topic>SOIL SHIFTING</topic><topic>UNDERGROUND OR UNDERWATER STRUCTURES</topic><toplevel>online_resources</toplevel><creatorcontrib>SHI JIANLU</creatorcontrib><creatorcontrib>LI SHANGMING</creatorcontrib><creatorcontrib>HU MINGWEN</creatorcontrib><creatorcontrib>WU JUN</creatorcontrib><creatorcontrib>GUO FENG</creatorcontrib><creatorcontrib>YANG GANG</creatorcontrib><creatorcontrib>FENG TIEJI</creatorcontrib><creatorcontrib>TIAN YUJIANG</creatorcontrib><creatorcontrib>LU JIAN</creatorcontrib><creatorcontrib>LIU GUOSHENG</creatorcontrib><creatorcontrib>XU YONG</creatorcontrib><collection>esp@cenet</collection></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext_linktorsrc</fulltext></delivery><addata><au>SHI JIANLU</au><au>LI SHANGMING</au><au>HU MINGWEN</au><au>WU JUN</au><au>GUO FENG</au><au>YANG GANG</au><au>FENG TIEJI</au><au>TIAN YUJIANG</au><au>LU JIAN</au><au>LIU GUOSHENG</au><au>XU YONG</au><format>patent</format><genre>patent</genre><ristype>GEN</ristype><title>Double-slurry closing construction method for sump</title><date>2015-12-16</date><risdate>2015</risdate><abstract>The invention relates to a double-slurry closing construction method for a sump. The double-slurry closing construction method for the sump comprises the following steps that (1) a drilling machine platform is laid around the grouting position; (2) slurry is prepared, first slurry is composed of liquid A, liquid B and a first additive at the mass ratio of 1: 1: 0.13, and second slurry is composed of liquid A , liquid C and a second additive at the mass ratio of 1: 1: 0.17; (3) grouting holes are distributed; (4) a rotary drilling bit penetrates through the stratum by the designed hole depth of 4.5 m, then the first slurry is injected into the hole in a retreating mode, the grouting pressure is controlled to range from 0.5 Mpa to 1.0 Mpa, a drill rod retreats by one meter, the second slurry continues to be injected, the grouting pressure is controlled to range from 1.1 Mpa to 1.4 Mpa, the drill rod continues to retreat, and the steps are repeated in sequence; when only one meter of the drill rod is left through retreating, the first slurry is injected and then the next hole is grouted after completion of grouting; and (5) after the sump is dug in a grouted foundation, and the wall face of the sump is coated with waterproof paint. By the adoption of the double-slurry closing construction method for the sump, construction is rapid and convenient, the closing effect is good, and the method is suitable for the technical field of constructional engineering.</abstract><oa>free_for_read</oa></addata></record>
fulltext fulltext_linktorsrc
identifier
ispartof
issn
language eng
recordid cdi_epo_espacenet_CN105155541A
source esp@cenet
subjects EMBANKMENTS
EXCAVATIONS
FIXED CONSTRUCTIONS
FOUNDATIONS
HYDRAULIC ENGINEERING
SOIL SHIFTING
UNDERGROUND OR UNDERWATER STRUCTURES
title Double-slurry closing construction method for sump
url https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2025-01-08T00%3A22%3A20IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-epo_EVB&rft_val_fmt=info:ofi/fmt:kev:mtx:patent&rft.genre=patent&rft.au=SHI%20JIANLU&rft.date=2015-12-16&rft_id=info:doi/&rft_dat=%3Cepo_EVB%3ECN105155541A%3C/epo_EVB%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_id=info:pmid/&rfr_iscdi=true