The invention provides a manually excavated hole broadening method and a hole broadening stabilization structure. The method comprises the following steps: 1, completing preparatory work before construction; 2, setting out a pile position; 3, excavating a hole and a protection wall to the elevation...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Hauptverfasser: HUANG XI, LYU JING, LI LIANGHUI, LIU XIAOMING, ZHOU WEI, XIONG JIN'AN, LUO YIDAO, TANG JIAMING, XIAO ZHENHUA, LI YONGHUI, QIU JIANJIN, SHI XINPENG, JI JINGSHAN, YANG YI, RONG KE, YANG LIWEI
Format: Patent
Sprache:chi ; eng
Schlagworte:
Online-Zugang:Volltext bestellen
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
container_end_page
container_issue
container_start_page
container_title
container_volume
creator HUANG XI
LYU JING
LI LIANGHUI
LIU XIAOMING
ZHOU WEI
XIONG JIN'AN
LUO YIDAO
TANG JIAMING
XIAO ZHENHUA
LI YONGHUI
QIU JIANJIN
SHI XINPENG
JI JINGSHAN
YANG YI
RONG KE
YANG LIWEI
description The invention provides a manually excavated hole broadening method and a hole broadening stabilization structure. The method comprises the following steps: 1, completing preparatory work before construction; 2, setting out a pile position; 3, excavating a hole and a protection wall to the elevation of the bottom of a broadened hole; 4, calibrating a hole part needing to be broadened on a hole wall; 5, drilling holes in soil at the beginning end of the hole part needing to be broadened along the hole wall, and inserting steel perforated pipes in the holes; 6, checking whether the positions of the steel perforated pipes in the holes remain stable and are not deviated, and clearing out dust in the holes; 7, injecting slurry, that is, injecting slurry into the steel perforated pipes for stabilizing and shaping; 8, performing manual hole broadening. In the process, the manual hole broadening stabilization structure is formed. The method provided by the invention reinforces the hole wall and guarantees the safety o
format Patent
fullrecord <record><control><sourceid>epo_EVB</sourceid><recordid>TN_cdi_epo_espacenet_CN103967025A</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><sourcerecordid>CN103967025A</sourcerecordid><originalsourceid>FETCH-epo_espacenet_CN103967025A3</originalsourceid><addsrcrecordid>eNrjZMjwTcwrTczJqVRIrUhOLEssSU1RyMjPSVVIKspPTEnNy8xLV8hNLcnIT1FIzEtRyCWsurgkMSkzJ7MqsSQzPw_IKypNLiktSuVhYE1LzClO5YXS3AyKbq4hzh66qQX58anFBYnJqXmpJfHOfoYGxpZm5gZGpo7GxKgBAH2CQWU</addsrcrecordid><sourcetype>Open Access Repository</sourcetype><iscdi>true</iscdi><recordtype>patent</recordtype></control><display><type>patent</type><title>Manually excavated hole broadening method and manually excavated hole broadening stabilization structure</title><source>esp@cenet</source><creator>HUANG XI ; LYU JING ; LI LIANGHUI ; LIU XIAOMING ; ZHOU WEI ; XIONG JIN'AN ; LUO YIDAO ; TANG JIAMING ; XIAO ZHENHUA ; LI YONGHUI ; QIU JIANJIN ; SHI XINPENG ; JI JINGSHAN ; YANG YI ; RONG KE ; YANG LIWEI</creator><creatorcontrib>HUANG XI ; LYU JING ; LI LIANGHUI ; LIU XIAOMING ; ZHOU WEI ; XIONG JIN'AN ; LUO YIDAO ; TANG JIAMING ; XIAO ZHENHUA ; LI YONGHUI ; QIU JIANJIN ; SHI XINPENG ; JI JINGSHAN ; YANG YI ; RONG KE ; YANG LIWEI</creatorcontrib><description>The invention provides a manually excavated hole broadening method and a hole broadening stabilization structure. The method comprises the following steps: 1, completing preparatory work before construction; 2, setting out a pile position; 3, excavating a hole and a protection wall to the elevation of the bottom of a broadened hole; 4, calibrating a hole part needing to be broadened on a hole wall; 5, drilling holes in soil at the beginning end of the hole part needing to be broadened along the hole wall, and inserting steel perforated pipes in the holes; 6, checking whether the positions of the steel perforated pipes in the holes remain stable and are not deviated, and clearing out dust in the holes; 7, injecting slurry, that is, injecting slurry into the steel perforated pipes for stabilizing and shaping; 8, performing manual hole broadening. In the process, the manual hole broadening stabilization structure is formed. The method provided by the invention reinforces the hole wall and guarantees the safety o</description><language>chi ; eng</language><subject>EMBANKMENTS ; EXCAVATIONS ; FIXED CONSTRUCTIONS ; FOUNDATIONS ; HYDRAULIC ENGINEERING ; SOIL SHIFTING ; UNDERGROUND OR UNDERWATER STRUCTURES</subject><creationdate>2014</creationdate><oa>free_for_read</oa><woscitedreferencessubscribed>false</woscitedreferencessubscribed></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><linktohtml>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20140806&amp;DB=EPODOC&amp;CC=CN&amp;NR=103967025A$$EHTML$$P50$$Gepo$$Hfree_for_read</linktohtml><link.rule.ids>230,308,776,881,25542,76289</link.rule.ids><linktorsrc>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20140806&amp;DB=EPODOC&amp;CC=CN&amp;NR=103967025A$$EView_record_in_European_Patent_Office$$FView_record_in_$$GEuropean_Patent_Office$$Hfree_for_read</linktorsrc></links><search><creatorcontrib>HUANG XI</creatorcontrib><creatorcontrib>LYU JING</creatorcontrib><creatorcontrib>LI LIANGHUI</creatorcontrib><creatorcontrib>LIU XIAOMING</creatorcontrib><creatorcontrib>ZHOU WEI</creatorcontrib><creatorcontrib>XIONG JIN'AN</creatorcontrib><creatorcontrib>LUO YIDAO</creatorcontrib><creatorcontrib>TANG JIAMING</creatorcontrib><creatorcontrib>XIAO ZHENHUA</creatorcontrib><creatorcontrib>LI YONGHUI</creatorcontrib><creatorcontrib>QIU JIANJIN</creatorcontrib><creatorcontrib>SHI XINPENG</creatorcontrib><creatorcontrib>JI JINGSHAN</creatorcontrib><creatorcontrib>YANG YI</creatorcontrib><creatorcontrib>RONG KE</creatorcontrib><creatorcontrib>YANG LIWEI</creatorcontrib><title>Manually excavated hole broadening method and manually excavated hole broadening stabilization structure</title><description>The invention provides a manually excavated hole broadening method and a hole broadening stabilization structure. The method comprises the following steps: 1, completing preparatory work before construction; 2, setting out a pile position; 3, excavating a hole and a protection wall to the elevation of the bottom of a broadened hole; 4, calibrating a hole part needing to be broadened on a hole wall; 5, drilling holes in soil at the beginning end of the hole part needing to be broadened along the hole wall, and inserting steel perforated pipes in the holes; 6, checking whether the positions of the steel perforated pipes in the holes remain stable and are not deviated, and clearing out dust in the holes; 7, injecting slurry, that is, injecting slurry into the steel perforated pipes for stabilizing and shaping; 8, performing manual hole broadening. In the process, the manual hole broadening stabilization structure is formed. The method provided by the invention reinforces the hole wall and guarantees the safety o</description><subject>EMBANKMENTS</subject><subject>EXCAVATIONS</subject><subject>FIXED CONSTRUCTIONS</subject><subject>FOUNDATIONS</subject><subject>HYDRAULIC ENGINEERING</subject><subject>SOIL SHIFTING</subject><subject>UNDERGROUND OR UNDERWATER STRUCTURES</subject><fulltext>true</fulltext><rsrctype>patent</rsrctype><creationdate>2014</creationdate><recordtype>patent</recordtype><sourceid>EVB</sourceid><recordid>eNrjZMjwTcwrTczJqVRIrUhOLEssSU1RyMjPSVVIKspPTEnNy8xLV8hNLcnIT1FIzEtRyCWsurgkMSkzJ7MqsSQzPw_IKypNLiktSuVhYE1LzClO5YXS3AyKbq4hzh66qQX58anFBYnJqXmpJfHOfoYGxpZm5gZGpo7GxKgBAH2CQWU</recordid><startdate>20140806</startdate><enddate>20140806</enddate><creator>HUANG XI</creator><creator>LYU JING</creator><creator>LI LIANGHUI</creator><creator>LIU XIAOMING</creator><creator>ZHOU WEI</creator><creator>XIONG JIN'AN</creator><creator>LUO YIDAO</creator><creator>TANG JIAMING</creator><creator>XIAO ZHENHUA</creator><creator>LI YONGHUI</creator><creator>QIU JIANJIN</creator><creator>SHI XINPENG</creator><creator>JI JINGSHAN</creator><creator>YANG YI</creator><creator>RONG KE</creator><creator>YANG LIWEI</creator><scope>EVB</scope></search><sort><creationdate>20140806</creationdate><title>Manually excavated hole broadening method and manually excavated hole broadening stabilization structure</title><author>HUANG XI ; LYU JING ; LI LIANGHUI ; LIU XIAOMING ; ZHOU WEI ; XIONG JIN'AN ; LUO YIDAO ; TANG JIAMING ; XIAO ZHENHUA ; LI YONGHUI ; QIU JIANJIN ; SHI XINPENG ; JI JINGSHAN ; YANG YI ; RONG KE ; YANG LIWEI</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-epo_espacenet_CN103967025A3</frbrgroupid><rsrctype>patents</rsrctype><prefilter>patents</prefilter><language>chi ; eng</language><creationdate>2014</creationdate><topic>EMBANKMENTS</topic><topic>EXCAVATIONS</topic><topic>FIXED CONSTRUCTIONS</topic><topic>FOUNDATIONS</topic><topic>HYDRAULIC ENGINEERING</topic><topic>SOIL SHIFTING</topic><topic>UNDERGROUND OR UNDERWATER STRUCTURES</topic><toplevel>online_resources</toplevel><creatorcontrib>HUANG XI</creatorcontrib><creatorcontrib>LYU JING</creatorcontrib><creatorcontrib>LI LIANGHUI</creatorcontrib><creatorcontrib>LIU XIAOMING</creatorcontrib><creatorcontrib>ZHOU WEI</creatorcontrib><creatorcontrib>XIONG JIN'AN</creatorcontrib><creatorcontrib>LUO YIDAO</creatorcontrib><creatorcontrib>TANG JIAMING</creatorcontrib><creatorcontrib>XIAO ZHENHUA</creatorcontrib><creatorcontrib>LI YONGHUI</creatorcontrib><creatorcontrib>QIU JIANJIN</creatorcontrib><creatorcontrib>SHI XINPENG</creatorcontrib><creatorcontrib>JI JINGSHAN</creatorcontrib><creatorcontrib>YANG YI</creatorcontrib><creatorcontrib>RONG KE</creatorcontrib><creatorcontrib>YANG LIWEI</creatorcontrib><collection>esp@cenet</collection></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext_linktorsrc</fulltext></delivery><addata><au>HUANG XI</au><au>LYU JING</au><au>LI LIANGHUI</au><au>LIU XIAOMING</au><au>ZHOU WEI</au><au>XIONG JIN'AN</au><au>LUO YIDAO</au><au>TANG JIAMING</au><au>XIAO ZHENHUA</au><au>LI YONGHUI</au><au>QIU JIANJIN</au><au>SHI XINPENG</au><au>JI JINGSHAN</au><au>YANG YI</au><au>RONG KE</au><au>YANG LIWEI</au><format>patent</format><genre>patent</genre><ristype>GEN</ristype><title>Manually excavated hole broadening method and manually excavated hole broadening stabilization structure</title><date>2014-08-06</date><risdate>2014</risdate><abstract>The invention provides a manually excavated hole broadening method and a hole broadening stabilization structure. The method comprises the following steps: 1, completing preparatory work before construction; 2, setting out a pile position; 3, excavating a hole and a protection wall to the elevation of the bottom of a broadened hole; 4, calibrating a hole part needing to be broadened on a hole wall; 5, drilling holes in soil at the beginning end of the hole part needing to be broadened along the hole wall, and inserting steel perforated pipes in the holes; 6, checking whether the positions of the steel perforated pipes in the holes remain stable and are not deviated, and clearing out dust in the holes; 7, injecting slurry, that is, injecting slurry into the steel perforated pipes for stabilizing and shaping; 8, performing manual hole broadening. In the process, the manual hole broadening stabilization structure is formed. The method provided by the invention reinforces the hole wall and guarantees the safety o</abstract><oa>free_for_read</oa></addata></record>
fulltext fulltext_linktorsrc
identifier
ispartof
issn
language chi ; eng
recordid cdi_epo_espacenet_CN103967025A
source esp@cenet
subjects EMBANKMENTS
EXCAVATIONS
FIXED CONSTRUCTIONS
FOUNDATIONS
HYDRAULIC ENGINEERING
SOIL SHIFTING
UNDERGROUND OR UNDERWATER STRUCTURES
title Manually excavated hole broadening method and manually excavated hole broadening stabilization structure
url https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2025-02-07T11%3A02%3A54IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-epo_EVB&rft_val_fmt=info:ofi/fmt:kev:mtx:patent&rft.genre=patent&rft.au=HUANG%20XI&rft.date=2014-08-06&rft_id=info:doi/&rft_dat=%3Cepo_EVB%3ECN103967025A%3C/epo_EVB%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_id=info:pmid/&rfr_iscdi=true