Method for electrified spanning construction of high-voltage power transmission and transformation line

The invention discloses a method for electrified spanning construction of a high-voltage power transmission and transformation line. The method comprises the following steps of: (1) preparation for construction: computing the position, the height and the width of a spanning frame; (2) building of th...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Hauptverfasser: YU QIUAN, PENG SHIJIAN, LV MING, ZHANG SONGHUA, GAO WENLIN, TANG ZUPENG
Format: Patent
Sprache:chi ; eng
Schlagworte:
Online-Zugang:Volltext bestellen
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
container_end_page
container_issue
container_start_page
container_title
container_volume
creator YU QIUAN
PENG SHIJIAN
LV MING
ZHANG SONGHUA
GAO WENLIN
TANG ZUPENG
description The invention discloses a method for electrified spanning construction of a high-voltage power transmission and transformation line. The method comprises the following steps of: (1) preparation for construction: computing the position, the height and the width of a spanning frame; (2) building of the spanning frame: according to the designed spanning frame model, installing an auxiliary lifting pole for suspending pulleys on towers at two sides of a span of a newly-built line, suspending double-layer pulleys on the lifting pole, penetrating the double-layer pulleys by Deenyma ropes to form ropeways which are regarded as carrying ropes of a safety net and suspending the safety net under the carrying ropes through suspending belts and small pulleys; (3) extension of insulation guide ropes; (4) extension of conducting wires and ground wires: extending the conducting wires, the ground wires and installation accessories above the safety net by utilizing the insulation guide ropes; and (5) dismantling of the built
format Patent
fullrecord <record><control><sourceid>epo_EVB</sourceid><recordid>TN_cdi_epo_espacenet_CN102324712A</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><sourcerecordid>CN102324712A</sourcerecordid><originalsourceid>FETCH-epo_espacenet_CN102324712A3</originalsourceid><addsrcrecordid>eNqNjU0KwjAQhbtxIeodxgMUbCu4LkVxoyv3JaSTdCCdCcmo17f-HMDVg8f3vbcs_AV1lAGcJMCAVhM5wgFyNMzEHqxw1nS3SsIgDkbyY_mQoMYjRHliAk2G80Q5vxHDw7eYFyfzsQIxrouFMyHj5perYns63rpziVF6nN8sMmrfXatd3dT7Q1W3zT_MC0uXQQg</addsrcrecordid><sourcetype>Open Access Repository</sourcetype><iscdi>true</iscdi><recordtype>patent</recordtype></control><display><type>patent</type><title>Method for electrified spanning construction of high-voltage power transmission and transformation line</title><source>esp@cenet</source><creator>YU QIUAN ; PENG SHIJIAN ; LV MING ; ZHANG SONGHUA ; GAO WENLIN ; TANG ZUPENG</creator><creatorcontrib>YU QIUAN ; PENG SHIJIAN ; LV MING ; ZHANG SONGHUA ; GAO WENLIN ; TANG ZUPENG</creatorcontrib><description>The invention discloses a method for electrified spanning construction of a high-voltage power transmission and transformation line. The method comprises the following steps of: (1) preparation for construction: computing the position, the height and the width of a spanning frame; (2) building of the spanning frame: according to the designed spanning frame model, installing an auxiliary lifting pole for suspending pulleys on towers at two sides of a span of a newly-built line, suspending double-layer pulleys on the lifting pole, penetrating the double-layer pulleys by Deenyma ropes to form ropeways which are regarded as carrying ropes of a safety net and suspending the safety net under the carrying ropes through suspending belts and small pulleys; (3) extension of insulation guide ropes; (4) extension of conducting wires and ground wires: extending the conducting wires, the ground wires and installation accessories above the safety net by utilizing the insulation guide ropes; and (5) dismantling of the built</description><language>chi ; eng</language><subject>CONVERSION OR DISTRIBUTION OF ELECTRIC POWER ; ELECTRICITY ; GENERATION ; INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINEDOPTICAL AND ELECTRIC CABLES OR LINES</subject><creationdate>2012</creationdate><oa>free_for_read</oa><woscitedreferencessubscribed>false</woscitedreferencessubscribed></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><linktohtml>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20120118&amp;DB=EPODOC&amp;CC=CN&amp;NR=102324712A$$EHTML$$P50$$Gepo$$Hfree_for_read</linktohtml><link.rule.ids>230,308,780,885,25564,76547</link.rule.ids><linktorsrc>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20120118&amp;DB=EPODOC&amp;CC=CN&amp;NR=102324712A$$EView_record_in_European_Patent_Office$$FView_record_in_$$GEuropean_Patent_Office$$Hfree_for_read</linktorsrc></links><search><creatorcontrib>YU QIUAN</creatorcontrib><creatorcontrib>PENG SHIJIAN</creatorcontrib><creatorcontrib>LV MING</creatorcontrib><creatorcontrib>ZHANG SONGHUA</creatorcontrib><creatorcontrib>GAO WENLIN</creatorcontrib><creatorcontrib>TANG ZUPENG</creatorcontrib><title>Method for electrified spanning construction of high-voltage power transmission and transformation line</title><description>The invention discloses a method for electrified spanning construction of a high-voltage power transmission and transformation line. The method comprises the following steps of: (1) preparation for construction: computing the position, the height and the width of a spanning frame; (2) building of the spanning frame: according to the designed spanning frame model, installing an auxiliary lifting pole for suspending pulleys on towers at two sides of a span of a newly-built line, suspending double-layer pulleys on the lifting pole, penetrating the double-layer pulleys by Deenyma ropes to form ropeways which are regarded as carrying ropes of a safety net and suspending the safety net under the carrying ropes through suspending belts and small pulleys; (3) extension of insulation guide ropes; (4) extension of conducting wires and ground wires: extending the conducting wires, the ground wires and installation accessories above the safety net by utilizing the insulation guide ropes; and (5) dismantling of the built</description><subject>CONVERSION OR DISTRIBUTION OF ELECTRIC POWER</subject><subject>ELECTRICITY</subject><subject>GENERATION</subject><subject>INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINEDOPTICAL AND ELECTRIC CABLES OR LINES</subject><fulltext>true</fulltext><rsrctype>patent</rsrctype><creationdate>2012</creationdate><recordtype>patent</recordtype><sourceid>EVB</sourceid><recordid>eNqNjU0KwjAQhbtxIeodxgMUbCu4LkVxoyv3JaSTdCCdCcmo17f-HMDVg8f3vbcs_AV1lAGcJMCAVhM5wgFyNMzEHqxw1nS3SsIgDkbyY_mQoMYjRHliAk2G80Q5vxHDw7eYFyfzsQIxrouFMyHj5perYns63rpziVF6nN8sMmrfXatd3dT7Q1W3zT_MC0uXQQg</recordid><startdate>20120118</startdate><enddate>20120118</enddate><creator>YU QIUAN</creator><creator>PENG SHIJIAN</creator><creator>LV MING</creator><creator>ZHANG SONGHUA</creator><creator>GAO WENLIN</creator><creator>TANG ZUPENG</creator><scope>EVB</scope></search><sort><creationdate>20120118</creationdate><title>Method for electrified spanning construction of high-voltage power transmission and transformation line</title><author>YU QIUAN ; PENG SHIJIAN ; LV MING ; ZHANG SONGHUA ; GAO WENLIN ; TANG ZUPENG</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-epo_espacenet_CN102324712A3</frbrgroupid><rsrctype>patents</rsrctype><prefilter>patents</prefilter><language>chi ; eng</language><creationdate>2012</creationdate><topic>CONVERSION OR DISTRIBUTION OF ELECTRIC POWER</topic><topic>ELECTRICITY</topic><topic>GENERATION</topic><topic>INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINEDOPTICAL AND ELECTRIC CABLES OR LINES</topic><toplevel>online_resources</toplevel><creatorcontrib>YU QIUAN</creatorcontrib><creatorcontrib>PENG SHIJIAN</creatorcontrib><creatorcontrib>LV MING</creatorcontrib><creatorcontrib>ZHANG SONGHUA</creatorcontrib><creatorcontrib>GAO WENLIN</creatorcontrib><creatorcontrib>TANG ZUPENG</creatorcontrib><collection>esp@cenet</collection></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext_linktorsrc</fulltext></delivery><addata><au>YU QIUAN</au><au>PENG SHIJIAN</au><au>LV MING</au><au>ZHANG SONGHUA</au><au>GAO WENLIN</au><au>TANG ZUPENG</au><format>patent</format><genre>patent</genre><ristype>GEN</ristype><title>Method for electrified spanning construction of high-voltage power transmission and transformation line</title><date>2012-01-18</date><risdate>2012</risdate><abstract>The invention discloses a method for electrified spanning construction of a high-voltage power transmission and transformation line. The method comprises the following steps of: (1) preparation for construction: computing the position, the height and the width of a spanning frame; (2) building of the spanning frame: according to the designed spanning frame model, installing an auxiliary lifting pole for suspending pulleys on towers at two sides of a span of a newly-built line, suspending double-layer pulleys on the lifting pole, penetrating the double-layer pulleys by Deenyma ropes to form ropeways which are regarded as carrying ropes of a safety net and suspending the safety net under the carrying ropes through suspending belts and small pulleys; (3) extension of insulation guide ropes; (4) extension of conducting wires and ground wires: extending the conducting wires, the ground wires and installation accessories above the safety net by utilizing the insulation guide ropes; and (5) dismantling of the built</abstract><oa>free_for_read</oa></addata></record>
fulltext fulltext_linktorsrc
identifier
ispartof
issn
language chi ; eng
recordid cdi_epo_espacenet_CN102324712A
source esp@cenet
subjects CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
ELECTRICITY
GENERATION
INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINEDOPTICAL AND ELECTRIC CABLES OR LINES
title Method for electrified spanning construction of high-voltage power transmission and transformation line
url https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2024-12-26T20%3A03%3A15IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-epo_EVB&rft_val_fmt=info:ofi/fmt:kev:mtx:patent&rft.genre=patent&rft.au=YU%20QIUAN&rft.date=2012-01-18&rft_id=info:doi/&rft_dat=%3Cepo_EVB%3ECN102324712A%3C/epo_EVB%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_id=info:pmid/&rfr_iscdi=true