Construction method for plugging air gap between bottom hole of pier steel suspension box and foundation pile

The invention discloses a construction method for plugging an air gap between a bottom hole of a pier steel suspension box and a foundation pile. The method comprises the following steps of: (1) machining a skirt sleeve; (2) penetrating a skirt belt for the skirt sleeve; (3) fixing the presser foot...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Hauptverfasser: HUANG GUIHUA, ZOU XINXIANG, LIU ZHONGYOU, YE YUEPING, XI MINGJUN, XING HONGMEI, ZHOU YONGZHONG, XU ZHENGDONG
Format: Patent
Sprache:chi ; eng
Schlagworte:
Online-Zugang:Volltext bestellen
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
container_end_page
container_issue
container_start_page
container_title
container_volume
creator HUANG GUIHUA
ZOU XINXIANG
LIU ZHONGYOU
YE YUEPING
XI MINGJUN
XING HONGMEI
ZHOU YONGZHONG
XU ZHENGDONG
description The invention discloses a construction method for plugging an air gap between a bottom hole of a pier steel suspension box and a foundation pile. The method comprises the following steps of: (1) machining a skirt sleeve; (2) penetrating a skirt belt for the skirt sleeve; (3) fixing the presser foot of the skirt sleeve; (4) sleeving a pile with the skirt sleeve; (5) pretensioning the skirt belt; and (6) tensioning the skirt belt, wherein the skirt sleeve is drawn into a cone shape to clad the annular air gap between the bottom hole of the pier steel suspension box and the foundation pile. The method has high efficiency and quick and accurate skirt sleeve positioning and tensioning and solves the problems of low construction efficiency and poor plugging effect of the traditional construction method that after the steel suspension box is sunk in place, materials such as steel plates, gunny bags, concrete, and the like are used for manually plugging underwater.
format Patent
fullrecord <record><control><sourceid>epo_EVB</sourceid><recordid>TN_cdi_epo_espacenet_CN101871197A</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><sourcerecordid>CN101871197A</sourcerecordid><originalsourceid>FETCH-epo_espacenet_CN101871197A3</originalsourceid><addsrcrecordid>eNqNzLEKwjAURuEuDqK-w_UBBINDdZSiODm5l7T9GwPpvSG5QR9fKj6A01kO37KaGuGsqfTqhWmCPmWgURLFUJzz7Mj6RM5G6qAvgKkTVZnoKQEkI0WPRFmBQLnkCM4z1MmbLM9S4cF-7egD1tVitCFj8-uq2l4vj-a2Q5QWOdoeDG2bu9mbY23MqT4f_nk-oW1Cew</addsrcrecordid><sourcetype>Open Access Repository</sourcetype><iscdi>true</iscdi><recordtype>patent</recordtype></control><display><type>patent</type><title>Construction method for plugging air gap between bottom hole of pier steel suspension box and foundation pile</title><source>esp@cenet</source><creator>HUANG GUIHUA ; ZOU XINXIANG ; LIU ZHONGYOU ; YE YUEPING ; XI MINGJUN ; XING HONGMEI ; ZHOU YONGZHONG ; XU ZHENGDONG</creator><creatorcontrib>HUANG GUIHUA ; ZOU XINXIANG ; LIU ZHONGYOU ; YE YUEPING ; XI MINGJUN ; XING HONGMEI ; ZHOU YONGZHONG ; XU ZHENGDONG</creatorcontrib><description>The invention discloses a construction method for plugging an air gap between a bottom hole of a pier steel suspension box and a foundation pile. The method comprises the following steps of: (1) machining a skirt sleeve; (2) penetrating a skirt belt for the skirt sleeve; (3) fixing the presser foot of the skirt sleeve; (4) sleeving a pile with the skirt sleeve; (5) pretensioning the skirt belt; and (6) tensioning the skirt belt, wherein the skirt sleeve is drawn into a cone shape to clad the annular air gap between the bottom hole of the pier steel suspension box and the foundation pile. The method has high efficiency and quick and accurate skirt sleeve positioning and tensioning and solves the problems of low construction efficiency and poor plugging effect of the traditional construction method that after the steel suspension box is sunk in place, materials such as steel plates, gunny bags, concrete, and the like are used for manually plugging underwater.</description><language>chi ; eng</language><subject>ASSEMBLY OF BRIDGES ; CONSTRUCTION OF BRIDGES ; CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES ; FIXED CONSTRUCTIONS ; OR VIADUCTS</subject><creationdate>2010</creationdate><oa>free_for_read</oa><woscitedreferencessubscribed>false</woscitedreferencessubscribed></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><linktohtml>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20101027&amp;DB=EPODOC&amp;CC=CN&amp;NR=101871197A$$EHTML$$P50$$Gepo$$Hfree_for_read</linktohtml><link.rule.ids>230,308,780,885,25564,76547</link.rule.ids><linktorsrc>$$Uhttps://worldwide.espacenet.com/publicationDetails/biblio?FT=D&amp;date=20101027&amp;DB=EPODOC&amp;CC=CN&amp;NR=101871197A$$EView_record_in_European_Patent_Office$$FView_record_in_$$GEuropean_Patent_Office$$Hfree_for_read</linktorsrc></links><search><creatorcontrib>HUANG GUIHUA</creatorcontrib><creatorcontrib>ZOU XINXIANG</creatorcontrib><creatorcontrib>LIU ZHONGYOU</creatorcontrib><creatorcontrib>YE YUEPING</creatorcontrib><creatorcontrib>XI MINGJUN</creatorcontrib><creatorcontrib>XING HONGMEI</creatorcontrib><creatorcontrib>ZHOU YONGZHONG</creatorcontrib><creatorcontrib>XU ZHENGDONG</creatorcontrib><title>Construction method for plugging air gap between bottom hole of pier steel suspension box and foundation pile</title><description>The invention discloses a construction method for plugging an air gap between a bottom hole of a pier steel suspension box and a foundation pile. The method comprises the following steps of: (1) machining a skirt sleeve; (2) penetrating a skirt belt for the skirt sleeve; (3) fixing the presser foot of the skirt sleeve; (4) sleeving a pile with the skirt sleeve; (5) pretensioning the skirt belt; and (6) tensioning the skirt belt, wherein the skirt sleeve is drawn into a cone shape to clad the annular air gap between the bottom hole of the pier steel suspension box and the foundation pile. The method has high efficiency and quick and accurate skirt sleeve positioning and tensioning and solves the problems of low construction efficiency and poor plugging effect of the traditional construction method that after the steel suspension box is sunk in place, materials such as steel plates, gunny bags, concrete, and the like are used for manually plugging underwater.</description><subject>ASSEMBLY OF BRIDGES</subject><subject>CONSTRUCTION OF BRIDGES</subject><subject>CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES</subject><subject>FIXED CONSTRUCTIONS</subject><subject>OR VIADUCTS</subject><fulltext>true</fulltext><rsrctype>patent</rsrctype><creationdate>2010</creationdate><recordtype>patent</recordtype><sourceid>EVB</sourceid><recordid>eNqNzLEKwjAURuEuDqK-w_UBBINDdZSiODm5l7T9GwPpvSG5QR9fKj6A01kO37KaGuGsqfTqhWmCPmWgURLFUJzz7Mj6RM5G6qAvgKkTVZnoKQEkI0WPRFmBQLnkCM4z1MmbLM9S4cF-7egD1tVitCFj8-uq2l4vj-a2Q5QWOdoeDG2bu9mbY23MqT4f_nk-oW1Cew</recordid><startdate>20101027</startdate><enddate>20101027</enddate><creator>HUANG GUIHUA</creator><creator>ZOU XINXIANG</creator><creator>LIU ZHONGYOU</creator><creator>YE YUEPING</creator><creator>XI MINGJUN</creator><creator>XING HONGMEI</creator><creator>ZHOU YONGZHONG</creator><creator>XU ZHENGDONG</creator><scope>EVB</scope></search><sort><creationdate>20101027</creationdate><title>Construction method for plugging air gap between bottom hole of pier steel suspension box and foundation pile</title><author>HUANG GUIHUA ; ZOU XINXIANG ; LIU ZHONGYOU ; YE YUEPING ; XI MINGJUN ; XING HONGMEI ; ZHOU YONGZHONG ; XU ZHENGDONG</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-epo_espacenet_CN101871197A3</frbrgroupid><rsrctype>patents</rsrctype><prefilter>patents</prefilter><language>chi ; eng</language><creationdate>2010</creationdate><topic>ASSEMBLY OF BRIDGES</topic><topic>CONSTRUCTION OF BRIDGES</topic><topic>CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES</topic><topic>FIXED CONSTRUCTIONS</topic><topic>OR VIADUCTS</topic><toplevel>online_resources</toplevel><creatorcontrib>HUANG GUIHUA</creatorcontrib><creatorcontrib>ZOU XINXIANG</creatorcontrib><creatorcontrib>LIU ZHONGYOU</creatorcontrib><creatorcontrib>YE YUEPING</creatorcontrib><creatorcontrib>XI MINGJUN</creatorcontrib><creatorcontrib>XING HONGMEI</creatorcontrib><creatorcontrib>ZHOU YONGZHONG</creatorcontrib><creatorcontrib>XU ZHENGDONG</creatorcontrib><collection>esp@cenet</collection></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext_linktorsrc</fulltext></delivery><addata><au>HUANG GUIHUA</au><au>ZOU XINXIANG</au><au>LIU ZHONGYOU</au><au>YE YUEPING</au><au>XI MINGJUN</au><au>XING HONGMEI</au><au>ZHOU YONGZHONG</au><au>XU ZHENGDONG</au><format>patent</format><genre>patent</genre><ristype>GEN</ristype><title>Construction method for plugging air gap between bottom hole of pier steel suspension box and foundation pile</title><date>2010-10-27</date><risdate>2010</risdate><abstract>The invention discloses a construction method for plugging an air gap between a bottom hole of a pier steel suspension box and a foundation pile. The method comprises the following steps of: (1) machining a skirt sleeve; (2) penetrating a skirt belt for the skirt sleeve; (3) fixing the presser foot of the skirt sleeve; (4) sleeving a pile with the skirt sleeve; (5) pretensioning the skirt belt; and (6) tensioning the skirt belt, wherein the skirt sleeve is drawn into a cone shape to clad the annular air gap between the bottom hole of the pier steel suspension box and the foundation pile. The method has high efficiency and quick and accurate skirt sleeve positioning and tensioning and solves the problems of low construction efficiency and poor plugging effect of the traditional construction method that after the steel suspension box is sunk in place, materials such as steel plates, gunny bags, concrete, and the like are used for manually plugging underwater.</abstract><oa>free_for_read</oa></addata></record>
fulltext fulltext_linktorsrc
identifier
ispartof
issn
language chi ; eng
recordid cdi_epo_espacenet_CN101871197A
source esp@cenet
subjects ASSEMBLY OF BRIDGES
CONSTRUCTION OF BRIDGES
CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
FIXED CONSTRUCTIONS
OR VIADUCTS
title Construction method for plugging air gap between bottom hole of pier steel suspension box and foundation pile
url https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2024-12-26T01%3A50%3A09IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-epo_EVB&rft_val_fmt=info:ofi/fmt:kev:mtx:patent&rft.genre=patent&rft.au=HUANG%20GUIHUA&rft.date=2010-10-27&rft_id=info:doi/&rft_dat=%3Cepo_EVB%3ECN101871197A%3C/epo_EVB%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_id=info:pmid/&rfr_iscdi=true