Risk factors affecting the ability for earned value management to accurately assess the performance of infrastructure projects in Australia
Purpose The purpose of this paper is to investigate a set of risk-related factors influencing the earned value management (EVM) concept as an assessment technique in evaluating the progress of modern sustainable infrastructure construction projects. Design/methodology/approach A qualitative research...
Gespeichert in:
Veröffentlicht in: | Construction innovation 2019-10, Vol.19 (4), p.550-569 |
---|---|
Hauptverfasser: | , , |
Format: | Artikel |
Sprache: | eng |
Schlagworte: | |
Online-Zugang: | Volltext |
Tags: |
Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
|
container_end_page | 569 |
---|---|
container_issue | 4 |
container_start_page | 550 |
container_title | Construction innovation |
container_volume | 19 |
creator | Ibrahim, Maan Nihad Thorpe, David Mahmood, Muhammad Nateque |
description | Purpose
The purpose of this paper is to investigate a set of risk-related factors influencing the earned value management (EVM) concept as an assessment technique in evaluating the progress of modern sustainable infrastructure construction projects.
Design/methodology/approach
A qualitative research approach has been adopted for identifying risk-related factors influencing EVM concept from a literature review and through interviewing industry personnel, followed by an inductive process to form sets of key factors and their measuring items.
Findings
EVM is a common method for assessing project performance. A weakness of this approach is that EVM assessment in its current form does not measure the impact of a number of project performance factors that result from the complexity of modern infrastructure construction projects, and thus does not accurately assess their impact in this performance. This paper discusses and explains a range of potential risk factors to evaluating project performance such as sustainability, stakeholder requirements, communication, procurement strategy, weather, experience of staff, site condition, design issues, financial risk, subcontractor, government requirements and material. In addition, their measuring items were identified.
Practical implications
This research assists projects managers to improve the evaluation process of infrastructure construction performance by incorporating a range of factors likely to impact on that performance and which are not included in current EVM calculations.
Originality/value
This research addresses the need to include in the EVM calculation a range of risk factors affecting the performance of infrastructure projects in Australia and therefore makes this calculation a more reliable tool for assessing project performance. |
doi_str_mv | 10.1108/CI-07-2018-0058 |
format | Article |
fullrecord | <record><control><sourceid>proquest_emera</sourceid><recordid>TN_cdi_emerald_primary_10_1108_CI-07-2018-0058</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><sourcerecordid>2293930434</sourcerecordid><originalsourceid>FETCH-LOGICAL-c349t-5285fa5613d09495eb1fb401cc86ecaf79ce7fba2d72dc570c93a85ef6c65d513</originalsourceid><addsrcrecordid>eNptkV1LwzAUhoMoOKfX3ga87pa0SdNejuLHYCCIXofT9GR2du1MUmG_wT9ttnkjeHXCOe9zPt4QcsvZjHNWzKtlwlSSMl4kjMnijEy4UCphhVTnxzdPBFfyklx5v2EsFTwXE_L90voPasGEwXkK1qIJbb-m4R0p1G3Xhj21g6MIrseGfkE3It1CD2vcYh9oGCgYMzoI2O0peI_eH-EdushFpUE6WNr21oEPbjRhdLHqhk2c5GOeLsaYh66Fa3JhofN48xun5O3h_rV6SlbPj8tqsUpMJsqQyLSQFmTOs4aVopRYc1sLxo0pcjRgVWlQ2RrSRqWNkYqZMoNCos1NLhvJsym5O_WNW3yO6IPeDKPr40idpmVWZkxkIqrmJ5Vxg_cOrd65dgturznTB8d1tdRM6YPj-uB4JGYnIloTD2r-Af58UfYD13SE2Q</addsrcrecordid><sourcetype>Aggregation Database</sourcetype><iscdi>true</iscdi><recordtype>article</recordtype><pqid>2293930434</pqid></control><display><type>article</type><title>Risk factors affecting the ability for earned value management to accurately assess the performance of infrastructure projects in Australia</title><source>Emerald Complete Journals</source><source>Standard: Emerald eJournal Premier Collection</source><creator>Ibrahim, Maan Nihad ; Thorpe, David ; Mahmood, Muhammad Nateque</creator><creatorcontrib>Ibrahim, Maan Nihad ; Thorpe, David ; Mahmood, Muhammad Nateque</creatorcontrib><description>Purpose
The purpose of this paper is to investigate a set of risk-related factors influencing the earned value management (EVM) concept as an assessment technique in evaluating the progress of modern sustainable infrastructure construction projects.
Design/methodology/approach
A qualitative research approach has been adopted for identifying risk-related factors influencing EVM concept from a literature review and through interviewing industry personnel, followed by an inductive process to form sets of key factors and their measuring items.
Findings
EVM is a common method for assessing project performance. A weakness of this approach is that EVM assessment in its current form does not measure the impact of a number of project performance factors that result from the complexity of modern infrastructure construction projects, and thus does not accurately assess their impact in this performance. This paper discusses and explains a range of potential risk factors to evaluating project performance such as sustainability, stakeholder requirements, communication, procurement strategy, weather, experience of staff, site condition, design issues, financial risk, subcontractor, government requirements and material. In addition, their measuring items were identified.
Practical implications
This research assists projects managers to improve the evaluation process of infrastructure construction performance by incorporating a range of factors likely to impact on that performance and which are not included in current EVM calculations.
Originality/value
This research addresses the need to include in the EVM calculation a range of risk factors affecting the performance of infrastructure projects in Australia and therefore makes this calculation a more reliable tool for assessing project performance.</description><identifier>ISSN: 1471-4175</identifier><identifier>EISSN: 1477-0857</identifier><identifier>DOI: 10.1108/CI-07-2018-0058</identifier><language>eng</language><publisher>London: Emerald Publishing Limited</publisher><subject>Communication ; Construction ; Construction contracts ; Construction industry ; Cost estimates ; Economic growth ; Government procurement ; Green infrastructure ; Infrastructure ; Literature reviews ; Mathematical analysis ; Performance assessment ; Performance evaluation ; Performance management ; Process planning ; Project engineering ; Project management ; Qualitative research ; Risk analysis ; Risk assessment ; Risk factors ; Stakeholders ; Success ; Sustainability ; Value management ; Weather</subject><ispartof>Construction innovation, 2019-10, Vol.19 (4), p.550-569</ispartof><rights>Emerald Publishing Limited</rights><rights>Emerald Publishing Limited 2019</rights><lds50>peer_reviewed</lds50><oa>free_for_read</oa><woscitedreferencessubscribed>false</woscitedreferencessubscribed><citedby>FETCH-LOGICAL-c349t-5285fa5613d09495eb1fb401cc86ecaf79ce7fba2d72dc570c93a85ef6c65d513</citedby><cites>FETCH-LOGICAL-c349t-5285fa5613d09495eb1fb401cc86ecaf79ce7fba2d72dc570c93a85ef6c65d513</cites></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><linktohtml>$$Uhttps://www.emerald.com/insight/content/doi/10.1108/CI-07-2018-0058/full/html$$EHTML$$P50$$Gemerald$$H</linktohtml><link.rule.ids>314,780,784,967,11635,21695,27924,27925,52689,53244</link.rule.ids></links><search><creatorcontrib>Ibrahim, Maan Nihad</creatorcontrib><creatorcontrib>Thorpe, David</creatorcontrib><creatorcontrib>Mahmood, Muhammad Nateque</creatorcontrib><title>Risk factors affecting the ability for earned value management to accurately assess the performance of infrastructure projects in Australia</title><title>Construction innovation</title><description>Purpose
The purpose of this paper is to investigate a set of risk-related factors influencing the earned value management (EVM) concept as an assessment technique in evaluating the progress of modern sustainable infrastructure construction projects.
Design/methodology/approach
A qualitative research approach has been adopted for identifying risk-related factors influencing EVM concept from a literature review and through interviewing industry personnel, followed by an inductive process to form sets of key factors and their measuring items.
Findings
EVM is a common method for assessing project performance. A weakness of this approach is that EVM assessment in its current form does not measure the impact of a number of project performance factors that result from the complexity of modern infrastructure construction projects, and thus does not accurately assess their impact in this performance. This paper discusses and explains a range of potential risk factors to evaluating project performance such as sustainability, stakeholder requirements, communication, procurement strategy, weather, experience of staff, site condition, design issues, financial risk, subcontractor, government requirements and material. In addition, their measuring items were identified.
Practical implications
This research assists projects managers to improve the evaluation process of infrastructure construction performance by incorporating a range of factors likely to impact on that performance and which are not included in current EVM calculations.
Originality/value
This research addresses the need to include in the EVM calculation a range of risk factors affecting the performance of infrastructure projects in Australia and therefore makes this calculation a more reliable tool for assessing project performance.</description><subject>Communication</subject><subject>Construction</subject><subject>Construction contracts</subject><subject>Construction industry</subject><subject>Cost estimates</subject><subject>Economic growth</subject><subject>Government procurement</subject><subject>Green infrastructure</subject><subject>Infrastructure</subject><subject>Literature reviews</subject><subject>Mathematical analysis</subject><subject>Performance assessment</subject><subject>Performance evaluation</subject><subject>Performance management</subject><subject>Process planning</subject><subject>Project engineering</subject><subject>Project management</subject><subject>Qualitative research</subject><subject>Risk analysis</subject><subject>Risk assessment</subject><subject>Risk factors</subject><subject>Stakeholders</subject><subject>Success</subject><subject>Sustainability</subject><subject>Value management</subject><subject>Weather</subject><issn>1471-4175</issn><issn>1477-0857</issn><fulltext>true</fulltext><rsrctype>article</rsrctype><creationdate>2019</creationdate><recordtype>article</recordtype><sourceid>AFKRA</sourceid><sourceid>AZQEC</sourceid><sourceid>BENPR</sourceid><sourceid>CCPQU</sourceid><sourceid>DWQXO</sourceid><sourceid>GNUQQ</sourceid><sourceid>GUQSH</sourceid><sourceid>M2O</sourceid><recordid>eNptkV1LwzAUhoMoOKfX3ga87pa0SdNejuLHYCCIXofT9GR2du1MUmG_wT9ttnkjeHXCOe9zPt4QcsvZjHNWzKtlwlSSMl4kjMnijEy4UCphhVTnxzdPBFfyklx5v2EsFTwXE_L90voPasGEwXkK1qIJbb-m4R0p1G3Xhj21g6MIrseGfkE3It1CD2vcYh9oGCgYMzoI2O0peI_eH-EdushFpUE6WNr21oEPbjRhdLHqhk2c5GOeLsaYh66Fa3JhofN48xun5O3h_rV6SlbPj8tqsUpMJsqQyLSQFmTOs4aVopRYc1sLxo0pcjRgVWlQ2RrSRqWNkYqZMoNCos1NLhvJsym5O_WNW3yO6IPeDKPr40idpmVWZkxkIqrmJ5Vxg_cOrd65dgturznTB8d1tdRM6YPj-uB4JGYnIloTD2r-Af58UfYD13SE2Q</recordid><startdate>20191007</startdate><enddate>20191007</enddate><creator>Ibrahim, Maan Nihad</creator><creator>Thorpe, David</creator><creator>Mahmood, Muhammad Nateque</creator><general>Emerald Publishing Limited</general><general>Emerald Group Publishing Limited</general><scope>AAYXX</scope><scope>CITATION</scope><scope>0U~</scope><scope>1-H</scope><scope>7RQ</scope><scope>7WY</scope><scope>7WZ</scope><scope>7XB</scope><scope>8FD</scope><scope>8FE</scope><scope>8FG</scope><scope>ABJCF</scope><scope>AFKRA</scope><scope>AZQEC</scope><scope>BENPR</scope><scope>BEZIV</scope><scope>BGLVJ</scope><scope>CCPQU</scope><scope>D1I</scope><scope>DWQXO</scope><scope>FR3</scope><scope>F~G</scope><scope>GNUQQ</scope><scope>GUQSH</scope><scope>HCIFZ</scope><scope>K6~</scope><scope>KB.</scope><scope>KR7</scope><scope>L.-</scope><scope>L.0</scope><scope>L6V</scope><scope>M0C</scope><scope>M2O</scope><scope>M2P</scope><scope>M7S</scope><scope>MBDVC</scope><scope>PADUT</scope><scope>PDBOC</scope><scope>PQBIZ</scope><scope>PQEST</scope><scope>PQQKQ</scope><scope>PQUKI</scope><scope>PTHSS</scope><scope>PYYUZ</scope><scope>Q9U</scope></search><sort><creationdate>20191007</creationdate><title>Risk factors affecting the ability for earned value management to accurately assess the performance of infrastructure projects in Australia</title><author>Ibrahim, Maan Nihad ; Thorpe, David ; Mahmood, Muhammad Nateque</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-LOGICAL-c349t-5285fa5613d09495eb1fb401cc86ecaf79ce7fba2d72dc570c93a85ef6c65d513</frbrgroupid><rsrctype>articles</rsrctype><prefilter>articles</prefilter><language>eng</language><creationdate>2019</creationdate><topic>Communication</topic><topic>Construction</topic><topic>Construction contracts</topic><topic>Construction industry</topic><topic>Cost estimates</topic><topic>Economic growth</topic><topic>Government procurement</topic><topic>Green infrastructure</topic><topic>Infrastructure</topic><topic>Literature reviews</topic><topic>Mathematical analysis</topic><topic>Performance assessment</topic><topic>Performance evaluation</topic><topic>Performance management</topic><topic>Process planning</topic><topic>Project engineering</topic><topic>Project management</topic><topic>Qualitative research</topic><topic>Risk analysis</topic><topic>Risk assessment</topic><topic>Risk factors</topic><topic>Stakeholders</topic><topic>Success</topic><topic>Sustainability</topic><topic>Value management</topic><topic>Weather</topic><toplevel>peer_reviewed</toplevel><toplevel>online_resources</toplevel><creatorcontrib>Ibrahim, Maan Nihad</creatorcontrib><creatorcontrib>Thorpe, David</creatorcontrib><creatorcontrib>Mahmood, Muhammad Nateque</creatorcontrib><collection>CrossRef</collection><collection>Global News & ABI/Inform Professional</collection><collection>Trade PRO</collection><collection>Career & Technical Education Database</collection><collection>Access via ABI/INFORM (ProQuest)</collection><collection>ABI/INFORM Global (PDF only)</collection><collection>ProQuest Central (purchase pre-March 2016)</collection><collection>Technology Research Database</collection><collection>ProQuest SciTech Collection</collection><collection>ProQuest Technology Collection</collection><collection>Materials Science & Engineering Collection</collection><collection>ProQuest Central UK/Ireland</collection><collection>ProQuest Central Essentials</collection><collection>ProQuest Central</collection><collection>Business Premium Collection</collection><collection>Technology Collection</collection><collection>ProQuest One Community College</collection><collection>ProQuest Materials Science Collection</collection><collection>ProQuest Central Korea</collection><collection>Engineering Research Database</collection><collection>ABI/INFORM Global (Corporate)</collection><collection>ProQuest Central Student</collection><collection>Research Library Prep</collection><collection>SciTech Premium Collection</collection><collection>ProQuest Business Collection</collection><collection>Materials Science Database</collection><collection>Civil Engineering Abstracts</collection><collection>ABI/INFORM Professional Advanced</collection><collection>ABI/INFORM Professional Standard</collection><collection>ProQuest Engineering Collection</collection><collection>ABI/INFORM Global</collection><collection>Research Library</collection><collection>Science Database</collection><collection>Engineering Database</collection><collection>Research Library (Corporate)</collection><collection>Research Library China</collection><collection>Materials Science Collection</collection><collection>ProQuest One Business</collection><collection>ProQuest One Academic Eastern Edition (DO NOT USE)</collection><collection>ProQuest One Academic</collection><collection>ProQuest One Academic UKI Edition</collection><collection>Engineering Collection</collection><collection>ABI/INFORM Collection China</collection><collection>ProQuest Central Basic</collection><jtitle>Construction innovation</jtitle></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext</fulltext></delivery><addata><au>Ibrahim, Maan Nihad</au><au>Thorpe, David</au><au>Mahmood, Muhammad Nateque</au><format>journal</format><genre>article</genre><ristype>JOUR</ristype><atitle>Risk factors affecting the ability for earned value management to accurately assess the performance of infrastructure projects in Australia</atitle><jtitle>Construction innovation</jtitle><date>2019-10-07</date><risdate>2019</risdate><volume>19</volume><issue>4</issue><spage>550</spage><epage>569</epage><pages>550-569</pages><issn>1471-4175</issn><eissn>1477-0857</eissn><abstract>Purpose
The purpose of this paper is to investigate a set of risk-related factors influencing the earned value management (EVM) concept as an assessment technique in evaluating the progress of modern sustainable infrastructure construction projects.
Design/methodology/approach
A qualitative research approach has been adopted for identifying risk-related factors influencing EVM concept from a literature review and through interviewing industry personnel, followed by an inductive process to form sets of key factors and their measuring items.
Findings
EVM is a common method for assessing project performance. A weakness of this approach is that EVM assessment in its current form does not measure the impact of a number of project performance factors that result from the complexity of modern infrastructure construction projects, and thus does not accurately assess their impact in this performance. This paper discusses and explains a range of potential risk factors to evaluating project performance such as sustainability, stakeholder requirements, communication, procurement strategy, weather, experience of staff, site condition, design issues, financial risk, subcontractor, government requirements and material. In addition, their measuring items were identified.
Practical implications
This research assists projects managers to improve the evaluation process of infrastructure construction performance by incorporating a range of factors likely to impact on that performance and which are not included in current EVM calculations.
Originality/value
This research addresses the need to include in the EVM calculation a range of risk factors affecting the performance of infrastructure projects in Australia and therefore makes this calculation a more reliable tool for assessing project performance.</abstract><cop>London</cop><pub>Emerald Publishing Limited</pub><doi>10.1108/CI-07-2018-0058</doi><tpages>20</tpages><oa>free_for_read</oa></addata></record> |
fulltext | fulltext |
identifier | ISSN: 1471-4175 |
ispartof | Construction innovation, 2019-10, Vol.19 (4), p.550-569 |
issn | 1471-4175 1477-0857 |
language | eng |
recordid | cdi_emerald_primary_10_1108_CI-07-2018-0058 |
source | Emerald Complete Journals; Standard: Emerald eJournal Premier Collection |
subjects | Communication Construction Construction contracts Construction industry Cost estimates Economic growth Government procurement Green infrastructure Infrastructure Literature reviews Mathematical analysis Performance assessment Performance evaluation Performance management Process planning Project engineering Project management Qualitative research Risk analysis Risk assessment Risk factors Stakeholders Success Sustainability Value management Weather |
title | Risk factors affecting the ability for earned value management to accurately assess the performance of infrastructure projects in Australia |
url | https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2024-12-27T05%3A11%3A50IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-proquest_emera&rft_val_fmt=info:ofi/fmt:kev:mtx:journal&rft.genre=article&rft.atitle=Risk%20factors%20affecting%20the%20ability%20for%20earned%20value%20management%20to%20accurately%20assess%20the%20performance%20of%20infrastructure%20projects%20in%20Australia&rft.jtitle=Construction%20innovation&rft.au=Ibrahim,%20Maan%20Nihad&rft.date=2019-10-07&rft.volume=19&rft.issue=4&rft.spage=550&rft.epage=569&rft.pages=550-569&rft.issn=1471-4175&rft.eissn=1477-0857&rft_id=info:doi/10.1108/CI-07-2018-0058&rft_dat=%3Cproquest_emera%3E2293930434%3C/proquest_emera%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_pqid=2293930434&rft_id=info:pmid/&rfr_iscdi=true |