Reconversion of the shipbuilding sector: from production by project to mass production. What is its effect on the LCOE of a wave energy farm?

The objective of this work has been to analyze the variation of different economic parameters (Levelized Cost Of Energy and Internal Rate of Return) for two possible ways of manufacturing: production by project to mass production. For this, 6 possible scenarios have been considered, taking into acco...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Veröffentlicht in:RE&PQJ 2023-12, Vol.21 (1)
Hauptverfasser: L. Castro-Santos, P. Rubial-Yáñez, I. Lamas-Galdo, D. Cordal Iglesias, A. Alcayde, F.G. Montoya, A. Filgueira-Vizoso
Format: Artikel
Sprache:eng
Online-Zugang:Volltext
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
container_end_page
container_issue 1
container_start_page
container_title RE&PQJ
container_volume 21
creator L. Castro-Santos
P. Rubial-Yáñez
I. Lamas-Galdo
D. Cordal Iglesias
A. Alcayde
F.G. Montoya
A. Filgueira-Vizoso
description The objective of this work has been to analyze the variation of different economic parameters (Levelized Cost Of Energy and Internal Rate of Return) for two possible ways of manufacturing: production by project to mass production. For this, 6 possible scenarios have been considered, taking into account the number of equipment manufactured and the economic parameters have been calculated in order to know which alternative provides greater economic viability, thus making the project more profitable.
doi_str_mv 10.24084/repqj21.214
format Article
fullrecord <record><control><sourceid>crossref</sourceid><recordid>TN_cdi_crossref_primary_10_24084_repqj21_214</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><sourcerecordid>10_24084_repqj21_214</sourcerecordid><originalsourceid>FETCH-LOGICAL-c1454-db3303993f106b92e033277f43f112b355db42f2615a3e687d0a749c350bf1333</originalsourceid><addsrcrecordid>eNpNkNtKAzEQhoMoWGrvfIB5ALcmmezJG5FSD1AoiKJ3S7KbtCndzZpsK30I39ld7UWv5vD_8w98hFwzOuWCZuLW6_Zrw9mUM3FGRpylPKKYfZ6f9JdkEoJVVCQJz1jOR-TnVZeu2WsfrGvAGejWGsLatmpnt5VtVhB02Tl_B8a7Glrvql3ZDV51GKZNr0LnoJYhnKhT-FjLDmwA2wXQxgy2_mhIX8yW8-GThG-516Ab7VcHMNLX91fkwsht0JNjHZP3x_nb7DlaLJ9eZg-LqGQiFlGlECnmORpGE5VzTRF5mhrRLxhXGMeVEtzwhMUSdZKlFZWpyEuMqTIMEcfk5j-39C4Er03ReltLfygYLf5oFkeaRU8TfwFHsWme</addsrcrecordid><sourcetype>Aggregation Database</sourcetype><iscdi>true</iscdi><recordtype>article</recordtype></control><display><type>article</type><title>Reconversion of the shipbuilding sector: from production by project to mass production. What is its effect on the LCOE of a wave energy farm?</title><source>EZB-FREE-00999 freely available EZB journals</source><creator>L. Castro-Santos ; P. Rubial-Yáñez ; I. Lamas-Galdo ; D. Cordal Iglesias ; A. Alcayde ; F.G. Montoya ; A. Filgueira-Vizoso</creator><creatorcontrib>L. Castro-Santos ; P. Rubial-Yáñez ; I. Lamas-Galdo ; D. Cordal Iglesias ; A. Alcayde ; F.G. Montoya ; A. Filgueira-Vizoso</creatorcontrib><description>The objective of this work has been to analyze the variation of different economic parameters (Levelized Cost Of Energy and Internal Rate of Return) for two possible ways of manufacturing: production by project to mass production. For this, 6 possible scenarios have been considered, taking into account the number of equipment manufactured and the economic parameters have been calculated in order to know which alternative provides greater economic viability, thus making the project more profitable.</description><identifier>ISSN: 2172-038X</identifier><identifier>EISSN: 2172-038X</identifier><identifier>DOI: 10.24084/repqj21.214</identifier><language>eng</language><ispartof>RE&amp;PQJ, 2023-12, Vol.21 (1)</ispartof><oa>free_for_read</oa><woscitedreferencessubscribed>false</woscitedreferencessubscribed></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><link.rule.ids>314,780,784,27924,27925</link.rule.ids></links><search><creatorcontrib>L. Castro-Santos</creatorcontrib><creatorcontrib>P. Rubial-Yáñez</creatorcontrib><creatorcontrib>I. Lamas-Galdo</creatorcontrib><creatorcontrib>D. Cordal Iglesias</creatorcontrib><creatorcontrib>A. Alcayde</creatorcontrib><creatorcontrib>F.G. Montoya</creatorcontrib><creatorcontrib>A. Filgueira-Vizoso</creatorcontrib><title>Reconversion of the shipbuilding sector: from production by project to mass production. What is its effect on the LCOE of a wave energy farm?</title><title>RE&amp;PQJ</title><description>The objective of this work has been to analyze the variation of different economic parameters (Levelized Cost Of Energy and Internal Rate of Return) for two possible ways of manufacturing: production by project to mass production. For this, 6 possible scenarios have been considered, taking into account the number of equipment manufactured and the economic parameters have been calculated in order to know which alternative provides greater economic viability, thus making the project more profitable.</description><issn>2172-038X</issn><issn>2172-038X</issn><fulltext>true</fulltext><rsrctype>article</rsrctype><creationdate>2023</creationdate><recordtype>article</recordtype><recordid>eNpNkNtKAzEQhoMoWGrvfIB5ALcmmezJG5FSD1AoiKJ3S7KbtCndzZpsK30I39ld7UWv5vD_8w98hFwzOuWCZuLW6_Zrw9mUM3FGRpylPKKYfZ6f9JdkEoJVVCQJz1jOR-TnVZeu2WsfrGvAGejWGsLatmpnt5VtVhB02Tl_B8a7Glrvql3ZDV51GKZNr0LnoJYhnKhT-FjLDmwA2wXQxgy2_mhIX8yW8-GThG-516Ab7VcHMNLX91fkwsht0JNjHZP3x_nb7DlaLJ9eZg-LqGQiFlGlECnmORpGE5VzTRF5mhrRLxhXGMeVEtzwhMUSdZKlFZWpyEuMqTIMEcfk5j-39C4Er03ReltLfygYLf5oFkeaRU8TfwFHsWme</recordid><startdate>20231228</startdate><enddate>20231228</enddate><creator>L. Castro-Santos</creator><creator>P. Rubial-Yáñez</creator><creator>I. Lamas-Galdo</creator><creator>D. Cordal Iglesias</creator><creator>A. Alcayde</creator><creator>F.G. Montoya</creator><creator>A. Filgueira-Vizoso</creator><scope>AAYXX</scope><scope>CITATION</scope></search><sort><creationdate>20231228</creationdate><title>Reconversion of the shipbuilding sector: from production by project to mass production. What is its effect on the LCOE of a wave energy farm?</title><author>L. Castro-Santos ; P. Rubial-Yáñez ; I. Lamas-Galdo ; D. Cordal Iglesias ; A. Alcayde ; F.G. Montoya ; A. Filgueira-Vizoso</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-LOGICAL-c1454-db3303993f106b92e033277f43f112b355db42f2615a3e687d0a749c350bf1333</frbrgroupid><rsrctype>articles</rsrctype><prefilter>articles</prefilter><language>eng</language><creationdate>2023</creationdate><toplevel>online_resources</toplevel><creatorcontrib>L. Castro-Santos</creatorcontrib><creatorcontrib>P. Rubial-Yáñez</creatorcontrib><creatorcontrib>I. Lamas-Galdo</creatorcontrib><creatorcontrib>D. Cordal Iglesias</creatorcontrib><creatorcontrib>A. Alcayde</creatorcontrib><creatorcontrib>F.G. Montoya</creatorcontrib><creatorcontrib>A. Filgueira-Vizoso</creatorcontrib><collection>CrossRef</collection><jtitle>RE&amp;PQJ</jtitle></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext</fulltext></delivery><addata><au>L. Castro-Santos</au><au>P. Rubial-Yáñez</au><au>I. Lamas-Galdo</au><au>D. Cordal Iglesias</au><au>A. Alcayde</au><au>F.G. Montoya</au><au>A. Filgueira-Vizoso</au><format>journal</format><genre>article</genre><ristype>JOUR</ristype><atitle>Reconversion of the shipbuilding sector: from production by project to mass production. What is its effect on the LCOE of a wave energy farm?</atitle><jtitle>RE&amp;PQJ</jtitle><date>2023-12-28</date><risdate>2023</risdate><volume>21</volume><issue>1</issue><issn>2172-038X</issn><eissn>2172-038X</eissn><abstract>The objective of this work has been to analyze the variation of different economic parameters (Levelized Cost Of Energy and Internal Rate of Return) for two possible ways of manufacturing: production by project to mass production. For this, 6 possible scenarios have been considered, taking into account the number of equipment manufactured and the economic parameters have been calculated in order to know which alternative provides greater economic viability, thus making the project more profitable.</abstract><doi>10.24084/repqj21.214</doi><oa>free_for_read</oa></addata></record>
fulltext fulltext
identifier ISSN: 2172-038X
ispartof RE&PQJ, 2023-12, Vol.21 (1)
issn 2172-038X
2172-038X
language eng
recordid cdi_crossref_primary_10_24084_repqj21_214
source EZB-FREE-00999 freely available EZB journals
title Reconversion of the shipbuilding sector: from production by project to mass production. What is its effect on the LCOE of a wave energy farm?
url https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2025-01-06T01%3A04%3A55IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-crossref&rft_val_fmt=info:ofi/fmt:kev:mtx:journal&rft.genre=article&rft.atitle=Reconversion%20of%20the%20shipbuilding%20sector:%20from%20production%20by%20project%20to%20mass%20production.%20What%20is%20its%20effect%20on%20the%20LCOE%20of%20a%20wave%20energy%20farm?&rft.jtitle=RE&PQJ&rft.au=L.%20Castro-Santos&rft.date=2023-12-28&rft.volume=21&rft.issue=1&rft.issn=2172-038X&rft.eissn=2172-038X&rft_id=info:doi/10.24084/repqj21.214&rft_dat=%3Ccrossref%3E10_24084_repqj21_214%3C/crossref%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_id=info:pmid/&rfr_iscdi=true