Distribution Transformer Capacity Planning Based On Load Characteristics According To Electric Power Requirements At The Mugarsari Campus, Siliwangi University

Siliwangi University is currently building a second campus in the Mugarsari Tasikmalaya area. With the construction of this second campus, it is necessary to plan the transformer capacity in accordance with the installed electrical power requirements. In terms of designing electrical installations a...

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Veröffentlicht in:Jurnal Teknik Elektro Indonesia 2024-08, Vol.5 (2), p.369-377
Hauptverfasser: Azizah, Faridah Nafa, Andang, Asep, Sutisna, Sutisna
Format: Artikel
Sprache:eng
Online-Zugang:Volltext
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
container_end_page 377
container_issue 2
container_start_page 369
container_title Jurnal Teknik Elektro Indonesia
container_volume 5
creator Azizah, Faridah Nafa
Andang, Asep
Sutisna, Sutisna
description Siliwangi University is currently building a second campus in the Mugarsari Tasikmalaya area. With the construction of this second campus, it is necessary to plan the transformer capacity in accordance with the installed electrical power requirements. In terms of designing electrical installations and the need for electrical power to be installed, proper planning is needed. In this research, the distribution transformer capacity value planning has been carried out in accordance with the installed electrical power requirements by considering load characteristics, namely demand factors and diversity factors. The aim of this research is to determine the capacity of the distribution transformer along with an analysis of the distribution transformer loading so that it complies with PLN standards. The total installed load is 1,566 kVA. In this study, calculations were carried out based on load characteristics, namely diversity factors and needs factors . The distribution transformer capacity obtained by considering load characteristics is 1,220 kVA with a loading percentage of 81% . The results of the loading that have been carried out are still in accordance with the Electricity Planning Projections through the 2020 RUPTL.
doi_str_mv 10.24036/jtein.v5i2.674
format Article
fullrecord <record><control><sourceid>crossref</sourceid><recordid>TN_cdi_crossref_primary_10_24036_jtein_v5i2_674</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><sourcerecordid>10_24036_jtein_v5i2_674</sourcerecordid><originalsourceid>FETCH-crossref_primary_10_24036_jtein_v5i2_6743</originalsourceid><addsrcrecordid>eNqVkLFOwzAQhi0EEhV0Zr0HoK2TNCmMEIoYQFQQ5uhwnPSqxA5np1WfhlfFrRhYme6G__9-6RPiKpLTeC6TbLbxmsx0m1I8zRbzEzGKF3EykenN7emf_1yMndtIKZMkStIsHYnvB3Ke6XPwZA0UjMbVljvNkGOPivweVi0aQ6aBe3S6glcDzxYryNfIqLzmACDl4E4py9UhV1hYtloFrIKV3QXWm_4aiHWnjQ9BD8Vaw8vQIDtkCktdP7hreKeWdmgagg9DW80urF-Ksxpbp8e_90LMHpdF_jRRbJ1jXZc9U4e8LyNZHlWURxXlQUUZVCT_b_wAJwdtOA</addsrcrecordid><sourcetype>Aggregation Database</sourcetype><iscdi>true</iscdi><recordtype>article</recordtype></control><display><type>article</type><title>Distribution Transformer Capacity Planning Based On Load Characteristics According To Electric Power Requirements At The Mugarsari Campus, Siliwangi University</title><source>DOAJ Directory of Open Access Journals</source><creator>Azizah, Faridah Nafa ; Andang, Asep ; Sutisna, Sutisna</creator><creatorcontrib>Azizah, Faridah Nafa ; Andang, Asep ; Sutisna, Sutisna</creatorcontrib><description>Siliwangi University is currently building a second campus in the Mugarsari Tasikmalaya area. With the construction of this second campus, it is necessary to plan the transformer capacity in accordance with the installed electrical power requirements. In terms of designing electrical installations and the need for electrical power to be installed, proper planning is needed. In this research, the distribution transformer capacity value planning has been carried out in accordance with the installed electrical power requirements by considering load characteristics, namely demand factors and diversity factors. The aim of this research is to determine the capacity of the distribution transformer along with an analysis of the distribution transformer loading so that it complies with PLN standards. The total installed load is 1,566 kVA. In this study, calculations were carried out based on load characteristics, namely diversity factors and needs factors . The distribution transformer capacity obtained by considering load characteristics is 1,220 kVA with a loading percentage of 81% . The results of the loading that have been carried out are still in accordance with the Electricity Planning Projections through the 2020 RUPTL.</description><identifier>ISSN: 2723-0589</identifier><identifier>EISSN: 2723-0589</identifier><identifier>DOI: 10.24036/jtein.v5i2.674</identifier><language>eng</language><ispartof>Jurnal Teknik Elektro Indonesia, 2024-08, Vol.5 (2), p.369-377</ispartof><lds50>peer_reviewed</lds50><woscitedreferencessubscribed>false</woscitedreferencessubscribed></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><link.rule.ids>314,777,781,861,27905,27906</link.rule.ids></links><search><creatorcontrib>Azizah, Faridah Nafa</creatorcontrib><creatorcontrib>Andang, Asep</creatorcontrib><creatorcontrib>Sutisna, Sutisna</creatorcontrib><title>Distribution Transformer Capacity Planning Based On Load Characteristics According To Electric Power Requirements At The Mugarsari Campus, Siliwangi University</title><title>Jurnal Teknik Elektro Indonesia</title><description>Siliwangi University is currently building a second campus in the Mugarsari Tasikmalaya area. With the construction of this second campus, it is necessary to plan the transformer capacity in accordance with the installed electrical power requirements. In terms of designing electrical installations and the need for electrical power to be installed, proper planning is needed. In this research, the distribution transformer capacity value planning has been carried out in accordance with the installed electrical power requirements by considering load characteristics, namely demand factors and diversity factors. The aim of this research is to determine the capacity of the distribution transformer along with an analysis of the distribution transformer loading so that it complies with PLN standards. The total installed load is 1,566 kVA. In this study, calculations were carried out based on load characteristics, namely diversity factors and needs factors . The distribution transformer capacity obtained by considering load characteristics is 1,220 kVA with a loading percentage of 81% . The results of the loading that have been carried out are still in accordance with the Electricity Planning Projections through the 2020 RUPTL.</description><issn>2723-0589</issn><issn>2723-0589</issn><fulltext>true</fulltext><rsrctype>article</rsrctype><creationdate>2024</creationdate><recordtype>article</recordtype><recordid>eNqVkLFOwzAQhi0EEhV0Zr0HoK2TNCmMEIoYQFQQ5uhwnPSqxA5np1WfhlfFrRhYme6G__9-6RPiKpLTeC6TbLbxmsx0m1I8zRbzEzGKF3EykenN7emf_1yMndtIKZMkStIsHYnvB3Ke6XPwZA0UjMbVljvNkGOPivweVi0aQ6aBe3S6glcDzxYryNfIqLzmACDl4E4py9UhV1hYtloFrIKV3QXWm_4aiHWnjQ9BD8Vaw8vQIDtkCktdP7hreKeWdmgagg9DW80urF-Ksxpbp8e_90LMHpdF_jRRbJ1jXZc9U4e8LyNZHlWURxXlQUUZVCT_b_wAJwdtOA</recordid><startdate>20240810</startdate><enddate>20240810</enddate><creator>Azizah, Faridah Nafa</creator><creator>Andang, Asep</creator><creator>Sutisna, Sutisna</creator><scope>AAYXX</scope><scope>CITATION</scope></search><sort><creationdate>20240810</creationdate><title>Distribution Transformer Capacity Planning Based On Load Characteristics According To Electric Power Requirements At The Mugarsari Campus, Siliwangi University</title><author>Azizah, Faridah Nafa ; Andang, Asep ; Sutisna, Sutisna</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-crossref_primary_10_24036_jtein_v5i2_6743</frbrgroupid><rsrctype>articles</rsrctype><prefilter>articles</prefilter><language>eng</language><creationdate>2024</creationdate><toplevel>peer_reviewed</toplevel><toplevel>online_resources</toplevel><creatorcontrib>Azizah, Faridah Nafa</creatorcontrib><creatorcontrib>Andang, Asep</creatorcontrib><creatorcontrib>Sutisna, Sutisna</creatorcontrib><collection>CrossRef</collection><jtitle>Jurnal Teknik Elektro Indonesia</jtitle></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext</fulltext></delivery><addata><au>Azizah, Faridah Nafa</au><au>Andang, Asep</au><au>Sutisna, Sutisna</au><format>journal</format><genre>article</genre><ristype>JOUR</ristype><atitle>Distribution Transformer Capacity Planning Based On Load Characteristics According To Electric Power Requirements At The Mugarsari Campus, Siliwangi University</atitle><jtitle>Jurnal Teknik Elektro Indonesia</jtitle><date>2024-08-10</date><risdate>2024</risdate><volume>5</volume><issue>2</issue><spage>369</spage><epage>377</epage><pages>369-377</pages><issn>2723-0589</issn><eissn>2723-0589</eissn><abstract>Siliwangi University is currently building a second campus in the Mugarsari Tasikmalaya area. With the construction of this second campus, it is necessary to plan the transformer capacity in accordance with the installed electrical power requirements. In terms of designing electrical installations and the need for electrical power to be installed, proper planning is needed. In this research, the distribution transformer capacity value planning has been carried out in accordance with the installed electrical power requirements by considering load characteristics, namely demand factors and diversity factors. The aim of this research is to determine the capacity of the distribution transformer along with an analysis of the distribution transformer loading so that it complies with PLN standards. The total installed load is 1,566 kVA. In this study, calculations were carried out based on load characteristics, namely diversity factors and needs factors . The distribution transformer capacity obtained by considering load characteristics is 1,220 kVA with a loading percentage of 81% . The results of the loading that have been carried out are still in accordance with the Electricity Planning Projections through the 2020 RUPTL.</abstract><doi>10.24036/jtein.v5i2.674</doi></addata></record>
fulltext fulltext
identifier ISSN: 2723-0589
ispartof Jurnal Teknik Elektro Indonesia, 2024-08, Vol.5 (2), p.369-377
issn 2723-0589
2723-0589
language eng
recordid cdi_crossref_primary_10_24036_jtein_v5i2_674
source DOAJ Directory of Open Access Journals
title Distribution Transformer Capacity Planning Based On Load Characteristics According To Electric Power Requirements At The Mugarsari Campus, Siliwangi University
url https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2025-01-21T00%3A00%3A01IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-crossref&rft_val_fmt=info:ofi/fmt:kev:mtx:journal&rft.genre=article&rft.atitle=Distribution%20Transformer%20Capacity%20Planning%20Based%20On%20Load%20Characteristics%20According%20To%20Electric%20Power%20Requirements%20At%20The%20Mugarsari%20Campus,%20Siliwangi%20University&rft.jtitle=Jurnal%20Teknik%20Elektro%20Indonesia&rft.au=Azizah,%20Faridah%20Nafa&rft.date=2024-08-10&rft.volume=5&rft.issue=2&rft.spage=369&rft.epage=377&rft.pages=369-377&rft.issn=2723-0589&rft.eissn=2723-0589&rft_id=info:doi/10.24036/jtein.v5i2.674&rft_dat=%3Ccrossref%3E10_24036_jtein_v5i2_674%3C/crossref%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_id=info:pmid/&rfr_iscdi=true