In order to further increase the transfer of transalpine traffic through Switzerland from road to rail, the Gotthard axis is to be improved to a 4 m corridor. For this purpose altogether 270 km of railway line between Basel and the Italian border is to be improved to a corner height of 4 m by 2020....

Ausführliche Beschreibung

Gespeichert in:
Bibliographische Detailangaben
Veröffentlicht in:Geomechanik und Tunnelbau 2018-02, Vol.11 (1), p.62-75
Hauptverfasser: Zieger, Thomas, Bühler, Martin, Rick, Beat, Schmid, Werner, Grossauer, Karl
Format: Artikel
Sprache:eng
Online-Zugang:Volltext
Tags: Tag hinzufügen
Keine Tags, Fügen Sie den ersten Tag hinzu!
container_end_page 75
container_issue 1
container_start_page 62
container_title Geomechanik und Tunnelbau
container_volume 11
creator Zieger, Thomas
Bühler, Martin
Rick, Beat
Schmid, Werner
Grossauer, Karl
description In order to further increase the transfer of transalpine traffic through Switzerland from road to rail, the Gotthard axis is to be improved to a 4 m corridor. For this purpose altogether 270 km of railway line between Basel and the Italian border is to be improved to a corner height of 4 m by 2020. The largest individual structure is the new Bözberg Tunnel in the canton Aargau. Various options were investigated for the preliminary design. The best variant turned out to be the new construction of a two‐track tunnel parallel to the existing tunnel. The existing two‐track Bözberg Tunnel, which is not suitable for upgrading to the 4 m standard, will be used as a service and escape tunnel. Various emergency exits lead through five cross passages from the new to the old tunnel. The short construction time of five years until opening on the one hand, and the challenging geology in the Faltenjura with swelling rock mass on the other pose great problems for client, designers, and the contractor. This article reports on these challenges and describes how they have also led to innovative solutions. Um die Verlagerung der alpenquerenden Gütertransporte von der Straße auf die Schiene durch die Schweiz weiter zu steigern, soll die Gotthard‐Achse zu einem 4‐Meter‐Korridor ausgebaut werden. Dabei werden insgesamt 270 km Eisenbahnstrecke zwischen Basel und der italienischen Grenze bis 2020 für Transporte mit einer Eckhöhe von 4 m ausgebaut. Das größte Projekt ist dabei der Neubau Bözbergtunnel im Kanton Aargau. Im Vorprojekt sind verschiedene Varianten untersucht worden. Als Bestvariante erwies sich der Neubau eines doppelspurigen Tunnels in Parallellage zum bestehenden Tunnel. Der bestehende zweispurige und nicht 4‐Meter taugliche Bözbergtunnel wird künftig als Dienst‐und Rettungsstollen genutzt. Verschiedene Notausgänge führen dabei über fünf Querverbindungen vom neuen zum alten Tunnel. Die kurze Bauzeit von fünf Jahren bis zur Inbetriebnahme einerseits und die anspruchsvolle Geologie im Faltenjura mit quellhaften Gebirge andererseits stellen Bauherr, Planer und ausführende Baufirma vor besondere Herausforderungen. In diesem Beitrag wird über diese Herausforderungen berichtet und dargestellt, wie sich daraus auch innovative Lösungen ergeben haben.
doi_str_mv 10.1002/geot.201800005
format Article
fullrecord <record><control><sourceid>crossref</sourceid><recordid>TN_cdi_crossref_primary_10_1002_geot_201800005</recordid><sourceformat>XML</sourceformat><sourcesystem>PC</sourcesystem><sourcerecordid>10_1002_geot_201800005</sourcerecordid><originalsourceid>FETCH-crossref_primary_10_1002_geot_2018000053</originalsourceid><addsrcrecordid>eNqVjk0KwjAQhYMoWLRb17lAa9LaH7cWxbV0H2Kd_khMJEkrejAv4MVsRdw7mzfvvRn4EFpQ4lNCgmUFyvoBoSnpJxohh6Zx5CVhuh7_9jiYIteY83AS0lWSxA46ZDUXAmQFBnN5wo2UquO26QAbJVrbKNkXFtsasIQbLnpvdVsMBVblJ9-8no8j6ArnrZQg5mhScmHA_eoM-bttnu29QitjNJTsqpsL13dGCRvg2QDPfvDh3w9vNDFOUQ</addsrcrecordid><sourcetype>Aggregation Database</sourcetype><iscdi>true</iscdi><recordtype>article</recordtype></control><display><type>article</type><title>Challenges and innovative solutions at the new construction of the Bözberg Tunnel: Herausforderungen und innovative Lösungen beim Neubau des Bözbergtunnels</title><source>Wiley Online Library All Journals</source><creator>Zieger, Thomas ; Bühler, Martin ; Rick, Beat ; Schmid, Werner ; Grossauer, Karl</creator><creatorcontrib>Zieger, Thomas ; Bühler, Martin ; Rick, Beat ; Schmid, Werner ; Grossauer, Karl</creatorcontrib><description>In order to further increase the transfer of transalpine traffic through Switzerland from road to rail, the Gotthard axis is to be improved to a 4 m corridor. For this purpose altogether 270 km of railway line between Basel and the Italian border is to be improved to a corner height of 4 m by 2020. The largest individual structure is the new Bözberg Tunnel in the canton Aargau. Various options were investigated for the preliminary design. The best variant turned out to be the new construction of a two‐track tunnel parallel to the existing tunnel. The existing two‐track Bözberg Tunnel, which is not suitable for upgrading to the 4 m standard, will be used as a service and escape tunnel. Various emergency exits lead through five cross passages from the new to the old tunnel. The short construction time of five years until opening on the one hand, and the challenging geology in the Faltenjura with swelling rock mass on the other pose great problems for client, designers, and the contractor. This article reports on these challenges and describes how they have also led to innovative solutions. Um die Verlagerung der alpenquerenden Gütertransporte von der Straße auf die Schiene durch die Schweiz weiter zu steigern, soll die Gotthard‐Achse zu einem 4‐Meter‐Korridor ausgebaut werden. Dabei werden insgesamt 270 km Eisenbahnstrecke zwischen Basel und der italienischen Grenze bis 2020 für Transporte mit einer Eckhöhe von 4 m ausgebaut. Das größte Projekt ist dabei der Neubau Bözbergtunnel im Kanton Aargau. Im Vorprojekt sind verschiedene Varianten untersucht worden. Als Bestvariante erwies sich der Neubau eines doppelspurigen Tunnels in Parallellage zum bestehenden Tunnel. Der bestehende zweispurige und nicht 4‐Meter taugliche Bözbergtunnel wird künftig als Dienst‐und Rettungsstollen genutzt. Verschiedene Notausgänge führen dabei über fünf Querverbindungen vom neuen zum alten Tunnel. Die kurze Bauzeit von fünf Jahren bis zur Inbetriebnahme einerseits und die anspruchsvolle Geologie im Faltenjura mit quellhaften Gebirge andererseits stellen Bauherr, Planer und ausführende Baufirma vor besondere Herausforderungen. In diesem Beitrag wird über diese Herausforderungen berichtet und dargestellt, wie sich daraus auch innovative Lösungen ergeben haben.</description><identifier>ISSN: 1865-7362</identifier><identifier>EISSN: 1865-7389</identifier><identifier>DOI: 10.1002/geot.201800005</identifier><language>eng</language><ispartof>Geomechanik und Tunnelbau, 2018-02, Vol.11 (1), p.62-75</ispartof><lds50>peer_reviewed</lds50><woscitedreferencessubscribed>false</woscitedreferencessubscribed><cites>FETCH-crossref_primary_10_1002_geot_2018000053</cites></display><links><openurl>$$Topenurl_article</openurl><openurlfulltext>$$Topenurlfull_article</openurlfulltext><thumbnail>$$Tsyndetics_thumb_exl</thumbnail><link.rule.ids>314,780,784,27923,27924</link.rule.ids></links><search><creatorcontrib>Zieger, Thomas</creatorcontrib><creatorcontrib>Bühler, Martin</creatorcontrib><creatorcontrib>Rick, Beat</creatorcontrib><creatorcontrib>Schmid, Werner</creatorcontrib><creatorcontrib>Grossauer, Karl</creatorcontrib><title>Challenges and innovative solutions at the new construction of the Bözberg Tunnel: Herausforderungen und innovative Lösungen beim Neubau des Bözbergtunnels</title><title>Geomechanik und Tunnelbau</title><description>In order to further increase the transfer of transalpine traffic through Switzerland from road to rail, the Gotthard axis is to be improved to a 4 m corridor. For this purpose altogether 270 km of railway line between Basel and the Italian border is to be improved to a corner height of 4 m by 2020. The largest individual structure is the new Bözberg Tunnel in the canton Aargau. Various options were investigated for the preliminary design. The best variant turned out to be the new construction of a two‐track tunnel parallel to the existing tunnel. The existing two‐track Bözberg Tunnel, which is not suitable for upgrading to the 4 m standard, will be used as a service and escape tunnel. Various emergency exits lead through five cross passages from the new to the old tunnel. The short construction time of five years until opening on the one hand, and the challenging geology in the Faltenjura with swelling rock mass on the other pose great problems for client, designers, and the contractor. This article reports on these challenges and describes how they have also led to innovative solutions. Um die Verlagerung der alpenquerenden Gütertransporte von der Straße auf die Schiene durch die Schweiz weiter zu steigern, soll die Gotthard‐Achse zu einem 4‐Meter‐Korridor ausgebaut werden. Dabei werden insgesamt 270 km Eisenbahnstrecke zwischen Basel und der italienischen Grenze bis 2020 für Transporte mit einer Eckhöhe von 4 m ausgebaut. Das größte Projekt ist dabei der Neubau Bözbergtunnel im Kanton Aargau. Im Vorprojekt sind verschiedene Varianten untersucht worden. Als Bestvariante erwies sich der Neubau eines doppelspurigen Tunnels in Parallellage zum bestehenden Tunnel. Der bestehende zweispurige und nicht 4‐Meter taugliche Bözbergtunnel wird künftig als Dienst‐und Rettungsstollen genutzt. Verschiedene Notausgänge führen dabei über fünf Querverbindungen vom neuen zum alten Tunnel. Die kurze Bauzeit von fünf Jahren bis zur Inbetriebnahme einerseits und die anspruchsvolle Geologie im Faltenjura mit quellhaften Gebirge andererseits stellen Bauherr, Planer und ausführende Baufirma vor besondere Herausforderungen. In diesem Beitrag wird über diese Herausforderungen berichtet und dargestellt, wie sich daraus auch innovative Lösungen ergeben haben.</description><issn>1865-7362</issn><issn>1865-7389</issn><fulltext>true</fulltext><rsrctype>article</rsrctype><creationdate>2018</creationdate><recordtype>article</recordtype><recordid>eNqVjk0KwjAQhYMoWLRb17lAa9LaH7cWxbV0H2Kd_khMJEkrejAv4MVsRdw7mzfvvRn4EFpQ4lNCgmUFyvoBoSnpJxohh6Zx5CVhuh7_9jiYIteY83AS0lWSxA46ZDUXAmQFBnN5wo2UquO26QAbJVrbKNkXFtsasIQbLnpvdVsMBVblJ9-8no8j6ArnrZQg5mhScmHA_eoM-bttnu29QitjNJTsqpsL13dGCRvg2QDPfvDh3w9vNDFOUQ</recordid><startdate>201802</startdate><enddate>201802</enddate><creator>Zieger, Thomas</creator><creator>Bühler, Martin</creator><creator>Rick, Beat</creator><creator>Schmid, Werner</creator><creator>Grossauer, Karl</creator><scope>AAYXX</scope><scope>CITATION</scope></search><sort><creationdate>201802</creationdate><title>Challenges and innovative solutions at the new construction of the Bözberg Tunnel</title><author>Zieger, Thomas ; Bühler, Martin ; Rick, Beat ; Schmid, Werner ; Grossauer, Karl</author></sort><facets><frbrtype>5</frbrtype><frbrgroupid>cdi_FETCH-crossref_primary_10_1002_geot_2018000053</frbrgroupid><rsrctype>articles</rsrctype><prefilter>articles</prefilter><language>eng</language><creationdate>2018</creationdate><toplevel>peer_reviewed</toplevel><toplevel>online_resources</toplevel><creatorcontrib>Zieger, Thomas</creatorcontrib><creatorcontrib>Bühler, Martin</creatorcontrib><creatorcontrib>Rick, Beat</creatorcontrib><creatorcontrib>Schmid, Werner</creatorcontrib><creatorcontrib>Grossauer, Karl</creatorcontrib><collection>CrossRef</collection><jtitle>Geomechanik und Tunnelbau</jtitle></facets><delivery><delcategory>Remote Search Resource</delcategory><fulltext>fulltext</fulltext></delivery><addata><au>Zieger, Thomas</au><au>Bühler, Martin</au><au>Rick, Beat</au><au>Schmid, Werner</au><au>Grossauer, Karl</au><format>journal</format><genre>article</genre><ristype>JOUR</ristype><atitle>Challenges and innovative solutions at the new construction of the Bözberg Tunnel: Herausforderungen und innovative Lösungen beim Neubau des Bözbergtunnels</atitle><jtitle>Geomechanik und Tunnelbau</jtitle><date>2018-02</date><risdate>2018</risdate><volume>11</volume><issue>1</issue><spage>62</spage><epage>75</epage><pages>62-75</pages><issn>1865-7362</issn><eissn>1865-7389</eissn><abstract>In order to further increase the transfer of transalpine traffic through Switzerland from road to rail, the Gotthard axis is to be improved to a 4 m corridor. For this purpose altogether 270 km of railway line between Basel and the Italian border is to be improved to a corner height of 4 m by 2020. The largest individual structure is the new Bözberg Tunnel in the canton Aargau. Various options were investigated for the preliminary design. The best variant turned out to be the new construction of a two‐track tunnel parallel to the existing tunnel. The existing two‐track Bözberg Tunnel, which is not suitable for upgrading to the 4 m standard, will be used as a service and escape tunnel. Various emergency exits lead through five cross passages from the new to the old tunnel. The short construction time of five years until opening on the one hand, and the challenging geology in the Faltenjura with swelling rock mass on the other pose great problems for client, designers, and the contractor. This article reports on these challenges and describes how they have also led to innovative solutions. Um die Verlagerung der alpenquerenden Gütertransporte von der Straße auf die Schiene durch die Schweiz weiter zu steigern, soll die Gotthard‐Achse zu einem 4‐Meter‐Korridor ausgebaut werden. Dabei werden insgesamt 270 km Eisenbahnstrecke zwischen Basel und der italienischen Grenze bis 2020 für Transporte mit einer Eckhöhe von 4 m ausgebaut. Das größte Projekt ist dabei der Neubau Bözbergtunnel im Kanton Aargau. Im Vorprojekt sind verschiedene Varianten untersucht worden. Als Bestvariante erwies sich der Neubau eines doppelspurigen Tunnels in Parallellage zum bestehenden Tunnel. Der bestehende zweispurige und nicht 4‐Meter taugliche Bözbergtunnel wird künftig als Dienst‐und Rettungsstollen genutzt. Verschiedene Notausgänge führen dabei über fünf Querverbindungen vom neuen zum alten Tunnel. Die kurze Bauzeit von fünf Jahren bis zur Inbetriebnahme einerseits und die anspruchsvolle Geologie im Faltenjura mit quellhaften Gebirge andererseits stellen Bauherr, Planer und ausführende Baufirma vor besondere Herausforderungen. In diesem Beitrag wird über diese Herausforderungen berichtet und dargestellt, wie sich daraus auch innovative Lösungen ergeben haben.</abstract><doi>10.1002/geot.201800005</doi></addata></record>
fulltext fulltext
identifier ISSN: 1865-7362
ispartof Geomechanik und Tunnelbau, 2018-02, Vol.11 (1), p.62-75
issn 1865-7362
1865-7389
language eng
recordid cdi_crossref_primary_10_1002_geot_201800005
source Wiley Online Library All Journals
title Challenges and innovative solutions at the new construction of the Bözberg Tunnel: Herausforderungen und innovative Lösungen beim Neubau des Bözbergtunnels
url https://sfx.bib-bvb.de/sfx_tum?ctx_ver=Z39.88-2004&ctx_enc=info:ofi/enc:UTF-8&ctx_tim=2025-01-11T08%3A41%3A14IST&url_ver=Z39.88-2004&url_ctx_fmt=infofi/fmt:kev:mtx:ctx&rfr_id=info:sid/primo.exlibrisgroup.com:primo3-Article-crossref&rft_val_fmt=info:ofi/fmt:kev:mtx:journal&rft.genre=article&rft.atitle=Challenges%20and%20innovative%20solutions%20at%20the%20new%20construction%20of%20the%20B%C3%B6zberg%20Tunnel:%20Herausforderungen%20und%20innovative%20L%C3%B6sungen%20beim%20Neubau%20des%20B%C3%B6zbergtunnels&rft.jtitle=Geomechanik%20und%20Tunnelbau&rft.au=Zieger,%20Thomas&rft.date=2018-02&rft.volume=11&rft.issue=1&rft.spage=62&rft.epage=75&rft.pages=62-75&rft.issn=1865-7362&rft.eissn=1865-7389&rft_id=info:doi/10.1002/geot.201800005&rft_dat=%3Ccrossref%3E10_1002_geot_201800005%3C/crossref%3E%3Curl%3E%3C/url%3E&disable_directlink=true&sfx.directlink=off&sfx.report_link=0&rft_id=info:oai/&rft_id=info:pmid/&rfr_iscdi=true